Question: Your company has been hired to act as a constructi...

Your company has been hired to act as a construction manager for the construction of a bookstore for a fixed fee of $32,000. When the design was 90% complete, you prepared a budget for the project, which is shown in Figure 4-12.

During the buyout, the subcontracts shown in Figure 4-13 were signed and the purchase orders shown in Figure 4-14 were issued. No additional costs are expected for the contracts in Figure 4-13 and the purchase orders in Figure 4-14. A purchase order has been issued for concrete for $115 per cubic yard. This price is 4% below the costs used in the budget. You have a meeting with the project's owner to discuss the financial status of the project. Using the committed cost worksheet in Figure 4-l of the textbook, update the estimated cost at completion and determine if the project is over or under budget.

a. Over budget; $69,948

b. Under budget; $6,150

c. Under budget; $5,616

d. Under budget; $5,825

e. Over budget; $5,825

Reference no: EM131251332

Questions Cloud

General sales tax-two of which have corporate income tax : Jurisdiction B’s tax system consists of a 6.5 percent general sales tax on retail goods and selected services. Over the past decade, the average annual volume of sales subject to this tax was $860 million. Jurisdiction B borders four other taxing jur..
Did anything that learned cause you to understand an issue : Reflect on what you found interesting, surprising, or confusing in this past week. Did anything that you learned cause you to understand an issue and event differently? Have you discovered any habits or tips that help you to complete your course w..
Draw a block diagram for your design : Design a TDM PCM system that will accommodate four 300-bit/s (synchronous) digital inputs and one analog input that has a bandwidth of 500 Hz. Assume that the analog samples will be encoded into 4-bit PCM words
Draw a block diagram for your design : Draw a block diagram for your design, and indicate the data rate at various points on your diagram. Explain how your TDM scheme works.
Determine if the project is over or under budget : Your company has been hired to act as a constructi... Your company has been hired to act as a construction manager for the construction of a bookstore for a fixed fee of $32,000. When the design was 90% complete, you prepared a budget for the project..
Compute and analyze the financial data : Compute and analyze the financial data using a Microsoft® Excel® spreadsheet. Make sure all calculations can be seen in the background of the applicable spreadsheet cells. In other words, leave an audit trail so others can see how you arrived at y..
Sketch the corresponding pwm signal : Assume that a sine wave is sampled at four times the Nyquist rate using instantaneous sampling.
Find the yield-to-call on a semiannual coupon bond : Find the Yield-to-Call on a Semiannual Coupon Bond with a Price of $1085, a Face Value of $1000, a Call Price of $1069.5, a Coupon Rate of 6.95%, 18 years remaining until Maturity, and 10 years remaining until the Call Date.
Problem regarding the risk adjusted return : You are an analyst comparing the performance of two portfolio managers using the Sharpe Ratio measurement. Manager A shows a return of 20% with a standard deviation of 16%. Manager B shows a return of 13% with a standard deviation of 7%. If the ri..

Reviews

Write a Review

Financial Accounting Questions & Answers

  Financial statement analysis and preparation

Financial Statement Analysis and Preparation

  Shareholder of a company

Describe the ways that a person can become a shareholder of a company. Why Wal-Mart would split its stock?

  Financial and accounting principles

An understanding of financial and accounting principles can be a valuable tool for managers. While not all managers will find themselves calculating financial ratios or preparing annual financial data.

  Prepare a statement of cash flow using the direct method

Prepare a Statement of Cash Flow using the Direct Method and Prepare the Operations section of the Statement of Cash Flow using the Indirect Method.

  Financial accounting assignment

This assignment has one case study and two question apart from case study. Questions related to document Liquidation question and Company financial statements question - Torquay Limited

  Prepare general journal entries for goela

Prepare general journal entries for Goela Ltd

  Principles of financial accounting

Prepare the journal entry to record the acquisition of the assets.

  Prepare general journal entries to record the transactions

Prepare general journal entries to record the transactions, assuming use of the periodic inventory system

  Global reporting initiative

Compare the view espoused by the economist Milton Friedman about the social responsibilities of business with the views express by Stigler.

  Explain the iasb conceptual frameworks

Explain the IASB Conceptual Framework's perspective of users and their decisions.

  Determine the company''s financial statements

T he focus of the report is to determine the extent to which you are comfortable relying on the financial statements as presented by management .

  Computation of free cash flow

Computation of Free Cash Flow

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd