Determine if the initial schedule is feasible

Assignment Help Operation Management
Reference no: EM131749707

You own a small construction company which specializes in finishing houses. Another contractor has subcontracted to you the job of finishing a house. The foundation, basic framework, and plumbing have been completed. Upon agreeing to terms, you sit down and analyze the problem confronting you. Assuming carpenters and electricians are available, you can simultaneously install the wiring (2 workers for 3 days), lay the floor (1 worker for 4 days), hang the doors (2 workers for 1 day) and finish the exterior (3 workers for 5 days). After the wiring has been installed, you can finish the interior walls (3 workers for 3 days) and then after that hook up the electrical fixtures (2 workers for i day). Once the doors are hung, you can install the windows (2 workers for 2 days). As soon as the exterior is finished you can make the necessary hookups to bring electricity in from the existing power lines (2 workers for 1day).

You are faced with the following constraints. Electricians and carpenters are not allowed to work in areas other than those specifically related to their trade. The electricians will perform the following activities: install electrical wiring, hook up electrical fixt hook up to existing power line s; the carpenters will perform the rest of activities.

1) Prepare an AON network diagram and determine the critical path by computing Early Start, Early Finish, Late Start, Late Finish and float.

2) Prepare daily basis assuming all activities are scheduled at their early start time (i.e each activity performed as soon as possible and project completing in minimum time).

3) Assuming the firm has only two electricians and four carpenters. Determine if the initial schedule is feasible. If the initial schedule is not feasible, develop a feasible schedule using the sequential heuristic method. Use the following priority rules a time-phased resource utilization showing resource requirements on a o . 1. Earliest start time 2. Minimum float 3. Shortest duration.

Reference no: EM131749707

Questions Cloud

View of the market versus a resource-based view : How do these features fit into an Industrial Organization (IO) view of the market versus a Resource-Based View (RBV)?
How do counter terror operations combat it : What is militant theology, and how do counter terror operations combat it?
What is a patent intended to protect : What is a patent intended to protect? What is the policy or purpose behind this right?
What is evaluation research and business research : What is business research? What is evaluation research? Explain privacy? What is unethical research?
Determine if the initial schedule is feasible : Assuming the firm has only two electricians and four carpenters. Determine if the initial schedule is feasible.
Consumers need information to make buying decisions : Consumers need information to make buying decisions. Knowing where they get this information from helps sellers target their marketing programs.
Experience in fundamentals of leadership : Reflect upon your experience in fundamentals of leadership and identify three key concepts you have learned that will help you in your current.
Perspectives of the employer and the employees involved : Identify the pros and cons from the perspectives of the employer and the employees involved.
Diversification vertical integration strategic alliances : Horizontal related diversification Conglomerate unrelated diversification Vertical integration Strategic alliances

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd