Determine a sequence that will minimize makespan time

Assignment Help Engineering Mathematics
Reference no: EM131150770

12. Use the assignment method to obtain a plan that will minimize the processing costs in the following table under these conditions:

 

 

WORKER

 

 

A

B

C

D

E

 

1

14

18

20

17

18

 

2

14

15

19

16

17

Job

3

12

16

15

14

17

 

4

11

13

14

12

14

 

5

10

16

15

14

13

a. The combination 2-D is undesirable.

b. The combinations 1-A and 2-D are undesirable.

13. The following table shows orders to be processed at a machine shop as of 8:00 a.m. Monday. The jobs have different operations they must go through. Processing times are in days. Jobs are listed in order of arrival.

Job

Processing
Time (Days)

Due Date
(Days)

Remaining Number
of Operations

A

8        

20

2

B

10        

18

4

C

5        

25

5

D

11        

17

3

E

9        

35

4

a. Determine the processing sequence at the first work center using each of these rules: (1) First come, first served, (2) Slack per operation.

b. Compute the effectiveness of each rule using each of these measures: (1) average completion time, (2) average number of jobs at the work center. (Round your answers to 2 decimal places.)

14. The times required to complete each of eight jobs in a two-machine flow shop are shown in the table that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B.

 

TIME (hours)

Job

Machine A

Machine B

a

16        

5        

b

3        

13        

c

9        

6        

d

8        

7        

e

2        

14        

f

12        

4        

g

18        

14        

h

20        

11        

a. Determine a sequence that will minimize makespan time.

b. Find machine B's idle time.

c. For the sequence determined in part a, how much would machine B's idle time be reduced by splitting the last two jobs in half?

16.For each of the following network diagrams, determine both the critical path and the expected project duration. The numbers on the arrows represent expected activity times.

a. Activity-on-arrow diagram

The expected project duration is .

b. Activity-on-node diagram

The critical path is .

The expected project duration is .

c. Activity-on-arrow diagram

The critical path is .

The expected project duration is .

17.For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish time, and slack time. List the critical activities, and determine the expected duration of the project.

a. Activity-on-arrow diagram

b. Activity-on-node diagram

c.

Activity

Immediate
Predecessor

Estimated Time (days)

A

-

15

B

A

12

C

B

6

D

B

5

E

C

3

F

-

8

G

F

8

H

F

9

I

G

7

J

H

14

K

J

6

End

D, E, I, K

 

18. Reconsider the network diagram. Suppose that after 12 weeks, activities 1-2, 1-3, and 2-4 have been finished; activity 2-5 is 75 percent finished; and activity 3-6 is half finished. How many weeks after the original start time should the project be finished?

Project can be completed in a total of weeks.

References

eBook& Resources

PROBLEM 2:

Problem 2-6

A manager checked production records and found that a worker produced 180 units while working 40 hours. In the previous week, the same worker produced 123 units while working 30 hours.

a. Compute Current period productivity and Previous period productivity.

b. Did the worker's productivity increase, decrease, or remain the same?

2-7

b. Suppose a new, more standardized procedure is to be introduced that will enable each employee to process one additional customer per day. Compute the expected labor and multifactor productivity rates for each unit.(Round your "Labor Productivity" answers to 1 decimal place and "Multifactor Productivity" answers to 4 decimal places.)

Use α=.5 and β=.1, and TAF of 250 for period 5. Obtain forecasts for periods 6 through 10. (Round your intermediate calculations and final answers to 2 decimal places.)

A manager of a store that sells and installs spas wants to prepare a forecast for January, February, and March of next year. Her forecasts are a combination of trend and seasonality. She uses the following equation to estimate the trend component of monthly demand: Ft = 100 + 2t, where t = 0 in June of last year. Seasonal relatives are 1.13 for January, 1.07 for February, and .92 for March. What demands should she predict? (Round your answers to 2 decimal places.)

https://www.dropbox.com/s/zslrs2qadw7h7e3/Review_Questions.rar?dl=0

Reference no: EM131150770

Questions Cloud

What are the pros and cons of job-based pay : What are the pros and cons of job-based pay? What are the pros and cons of person-based pay? How do you explain either of these pay structures to potential job candidates? In other words, what’s important to tell them?
Describe the current marketing communication : Describe the current marketing communication, identity, and brand position of Plaza Home Health Services - Conduct a Strengths Weaknesses Opportunities Threats (SWOT) analysis associated with the current marketing communication, identity, and brand ..
Earned value is method for measuring project performance : Earned value is '[a] method for measuring project performance. It compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance is as planned' (Project Management Institute, 2013). Is t..
Discuss ethical implications of clinical efficiency research : Analyze the impact of using the Internet to communicate consumer information. Assess the impact of organizational research and the use of IT to collect data.
Determine a sequence that will minimize makespan time : Compute Current period productivity and Previous period productivity. Did the worker's productivity increase, decrease, or remain the same? Determine a sequence that will minimize makespan time.
Project managers use earned value : Project managers use earned value because it provides an early warning sign if costs and schedules are not on track, and it gives them the opportunity to address these issues in their earliest stages. What are some ways to get back on track if we are..
Which challenges in long-term care system remain unmet : What changes can we expect to occur with the influx of baby boomers entering into the long-term care system? Why do you think technology is important to long-term care? Support your answer with relevant examples.
Describe theories of change implementation : Describe theories of change implementation that would have helped the administration at Springfield General Hospital solve the problem of medication mistakes
Define the main elements of the systems framework : Major Characteristics of U.S. Health Care Delivery Prompt: First, what are the 2 main objectives of a health delivery system? Next, what are the 10 characteristics of the U.S. health care system? What is the purpose of the systems framework? Name and..

Reviews

Write a Review

Engineering Mathematics Questions & Answers

  Prime number theorem

Dirichlet series

  Proof of bolzano-weierstrass to prove the intermediate value

Every convergent sequence contains either an increasing, or a decreasing subsequence.

  Antisymmetric relations

How many relations on A are both symmetric and antisymmetric?

  Distributed random variables

Daily Airlines fies from Amsterdam to London every day. The price of a ticket for this extremely popular flight route is $75. The aircraft has a passenger capacity of 150.

  Prepare a system of equations

How much money will Dave and Jane raise for charity

  Managing ashland multicomm services

This question is asking you to compare the likelihood of your getting 4 or more subscribers in a sample of 50 when the probability of a subscription has risen from 0.02 to 0.06.]  Talk about the comparison of probabilities in your explanation.

  Skew-symmetric matrices

Skew-symmetric matrices

  Type of taxes and rates in spokane wa

Describe the different type of taxes and their rates in Spokane WA.

  Stratified random sample

Suppose that in the four player game, the person who rolls the smallest number pays $5.00 to the person who rolls the largest number. Calculate each player's expected gain after one round.

  Find the probability density function

Find the probability density function.

  Develop a new linear programming for an aggregate production

Linear programming applied to Aggregate Production Planning of Flat Screen Monitor

  Discrete-time model for an economy

Discrete-time model for an economy

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd