Determine a feasible schedule for the project

Assignment Help Data Structure & Algorithms
Reference no: EM131469585

Question: Consider the project network pictured in Figure. Activity times, measured in days, are shown in parentheses next to each activity label.

a. Determine the earliest and the latest starting and finishing times for all activities. Draw a Gantt chart based on earliest starting times, but indicate activity slack where appropriate. How many days are required to complete the project?

b. A single critical piece of equipment is required in order to complete the following activities: A, B, C, D, G, and H. Determine a feasible schedule for the project assuming that none of these activities can be done simultaneously.

c. Two resources, R1 and R2, are used for each activity. Assume that these are both consumable resources with daily requirements as follows:

2136_act 3.png

Determine resource loading profiles based on the schedule found in part (b).

d. Based on the results of part (c), determine the cumulative amounts of resources R1 and R2 consumed if the schedule found in part (b) is used.

990_10-22.png

Reference no: EM131469585

Questions Cloud

The center adds the server to the bottleneck resource : Assuming unlimited demand, what is the new flow rate if the center adds the server to the bottleneck resource?
What does this case suggest about doing business globally : What does this case suggest about doing business globally?
What are the five most important concepts : As you complete this course, look back on the experience. What are the five most important concepts that you have learned from the course?
Find what is the profitability index of a project : What is the profitability index of a project that has an initial cash outflow of $600, an inflow of $250 for the next 3 years and a cost of capital of 10 percen
Determine a feasible schedule for the project : Consider the project network pictured in Figure. Activity times, measured in days, are shown in parentheses next to each activity label.
What are the advantages and of going public with your firm : What are the advantages and of ‘going public’ with your firm? A primary source of funding for most smaller companies is
Certain sources of information are especially valuable : In determining a business location, certain sources of information are especially valuable.
The major distinction between cash-basis and accrual-basis : The major distinction between cash-basis and accrual-basis accounting is that the
Primary source of funding for most smaller companies : A primary source of funding for most smaller companies is

Reviews

Write a Review

Data Structure & Algorithms Questions & Answers

  Complete the step process for designing dimensional models

Complete the step process for designing dimensional models for each process you identify and create a dimensional model (star schema) for each process you identify Align

  What important lupus data features in building the tree

This problem illustrates the classification approach by using decision trees and the Lupus data. What are the most important three Lupus data features in building the tree

  Queue and content of countdown timer-using priority queue

At time 230 five processes (P1 - P5) are waiting for timeout signal. They are scheduled to wake up at times: 260, 320, 360, 430, 450. Using priority queue with time differences illustrate queue and content of countdown timer at time 230.

  Create algorithm to calculate union of two input sets-array

Create algorithm to calculate union of two input sets given as arrays, both of size O(n). The output must be array of distinct elements that form union of the sets.

  Design algorithm determining annual profit for company

Your goal is to solve the following simple programming exercise. You have been asked by your accounting department to design an algorithm determining the annual profit for your company.

  Saving contents of the richtextbox by creating a program

Create the statements to save the contents of the RichTextBox named rtbCurrent. Show a SaveFileDialog named sfdCurrent to get the name of the document from the user.

  What would be the slowest time the algorithm can run

What would be the slowest time the algorithm can run (in terms of n). What input would cause this slowest time. What would be the fastest time your algorithm could run (in terms of n). For what input would this fastest time be achieved.

  Declare a global array solution

Declare a global array Solution

  Design and develop a small or medium sized program

Write a C program that sorts strings into descending or ascending order (determined by the user of the program). develop your own program driver to illustrate that your program works. You may use any library functions you wish.

  Compute average memory access time of the processor

CSC531 Computer Architecture - What is the overall speedup by using the floating-point processor and What is the total size of the cache (in KB)?

  Write program that prompt users to pick either seat or price

Write a program that prompts users to pick either a seat or a price. Mark sold seats by changing the price to 0. When a user specifies a seat, make sure it is available.

  1 for a 77t truck with gross vehicle weight gvw of 136078

1. for a 77t truck with gross vehicle weight gvw of 136078 kg with dual rear tyres and a tyre inflation pressure is 120

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd