Reference no: EM131018973
Scenario:
Your PM7010 Group has been awarded a service contract by a local travel agent to plan an eight-day/seven-night trip for a group party of 50 people. The destination for the trip could be one of the following:
- Orlando, Florida
- Maui, Hawaii
- Rome, Italy
- Kiev, Ukraine
- Location of YOUR choosing!
The trip will be a delivered in phases. Your planning for the project will be based on a work breakdown structure that supports a phased project. Following are the main elements of the work breakdown structure:
1. Publicity
2. Itinerary
3. Reservations
4. Registration
5. Travel
6. Project Management
The project is complete once everyone returns from the trip.
The contract terms and conditions require a scope validation meeting be held at each milestone for the project for the customer (travel agent) to accept the work completed and move forward with the next project phase.
Items that have been agreed upon between your group and the travel agent:
The agency assures your group that once the mailing of the brochure is complete, it will take six (6) weeks to fill the trip.
Publicity will be on-going until the registration is complete.
The budget will allow for two people to make a three-day/two-night scouting trip and for two people to make the actual trip with the group.
The agency requires a trifold brochure, which must include current photos of the destination. The brochure will be mailed to the agency's customer base. The budget will allow for a single printing and mailing. Ensure that the brochure will effectively answer any basic questions someone would want to know if they were considering taking the trip.
Your group will make all reservations for transportation, lodging, meals, and attractions.
The travel agency informs your group that you must use the most economical prices available. Therefore, all reservations/confirmations must be made two weeks in advance of the actual date of travel.
The printing and mailing of 5,000 brochures will take five working days.
The contract was awarded on June 1st, 20xx. Travel begins 60 days after contract award. The short suspense date will require your company to have concurrent activities and more than one path in the project network.
The trip should include one "free" day for the tour members, an opening or closing banquet, and arrangements to visit the appropriate tourist sites for the chosen area.
Travel to the initial destination should be by airline. Upon arrival, appropriate arrangements should be made for travel by bus, ferry, or train.
Assume a 40-hour work week for team members when not traveling.
Questions
The following are the minimum items to be included in your group project:
- Develop a project charter (see Lesson 3) in accordance with the content described in Section 4.1.3.1, PMBOK 5e. Your company has been hired by the travel agency. Essentially, you are a sub-contractor for this job. Roles:
- Project Sponsor: Course Instructor
- Project Manager: Group Leader
- Project Team Members: Remaining members of your group
- Develop a Stakeholder Register, Stakeholder Analysis, and Communication Plan (Lesson 4)
- Prepare a WBS with WBS dictionary (see Lesson 5)
- Prepare a Gantt chart project schedule (with dependencies) and identify the critical path (see Lesson 6).
Provide an answer to the question-"can the project be completed in 60 days?"
Determine the degree of operating leverage for each approach
: Determine the degree of operating leverage for each approach at current sales levels. How much would the company's net income decline under each approach with a 10% decline in sales?
|
State the domain and range of the given function
: Write this equation in function notation. State the domain and range of this function. Graph this function for pendulums up to 20m in length.
|
Because of this fasb is considering allowing
: The readings for this week talk about restatements and touch on a topic called "dark periods". This is the time it takes a company to restate their financial statements after determining that a material misstatement has occurred either through error ..
|
Find the information to analyze expected changes
: Would you, as the CFO, finance your projects as soon as possible if cost of capital was expected to drop
|
Destination for the trip
: Your PM7010 Group has been awarded a service contract by a local travel agent to plan an eight-day/seven-night trip for a group party of 50 people. The destination for the trip could be one of the following:
|
How much overhead was allocated to each of the two models
: Write a brief report to President Brahms explaining your conclusions and the benefits of your suggestions. What are the lessons learned from this case that can help him understand cost allocation.
|
What is the amount anne will pay
: Anne, Mary, Susie, and Rochelle go out to dinner and together spend $68.00 on the meal. They agree that they will split the tab for the meal evenly and that they will pay the waiter a 20% tip. What is the amount Anne will pay
|
Project for advertising and public relations
: Your individual Final Project for Advertising and Public Relations is intended to showcase the analytical and creative public relations skills you've learned in MAR342. This project can be an exhibit in your senior portfolio presented to prospecti..
|
Give compound annual growth rates for key categories
: Give compound annual growth rates for key categories (such as revenue, but you must decide which others will contribute to your understanding of the company )
|