Design feasibility study

Assignment Help Operation Management
Reference no: EM131700631

Specific to this assignment

1. Set this Exercise project plan toTask Type Fixed Duration. Start the project on December 1. Use the default Standard Calendar with no holidays.

2. Enter the following task names and durations.  Be sure the Timescale is set to Month/Year (Middle Tier) and Weeks (Bottom Tier).  Also, summarize tasks into phases.

Plan Phase

Plan the Project                      3d

Gather Requirements                8d

Review Requirements                2d

Design Phase

Design Feasibility Study            12d

Design / Analysis                     17d

Build Prototype Phase

1st Generation Build                  12d

Competitive Engine Evaluation    17d

Customer Input                       7d

Test Phase

1st Life Test                           32d

Final Design Life Test               17d

Performance Development         10d

Field Test                              32d

Production Rollout                   0d

3. Save the file with the following filename format, "Assign4<your_name> yymmdd,"  ie. Assign4DOlson171024.

4. Link the tasks shown below. Note that some tasks have more than one predecessor.

Task

Predecessor(s)

Plan the Project

 

Gather Requirements

Plan the Project

Review Requirements

Gather Requirements

 

 

Design Feasibility Study

Review Requirements

Design/Analysis

Design Feasibility Study

 

 

1st Generation Build

Design Feasibility Study

Competitive Engine Evaluation

1st Generation Build

Customer Input

1st Generation Build

 

 

1st Life Test

Design/Analysis

Competitive Engine Evaluation

Customer Input

Final Design Life Test

1st Life Test

Performance Development

Final Design Life Test

Field Test

Final Design Life Test

 

 

Production Rollout

Performance Development

Field Test

Assign the following Resources and Work estimates to the tasks listed below.  Use $50/hour as the rate for all resources.

Be sure that the project plan has the Task Type Fixed Duration. 

Task                                        Resource Name                     Work

 

Plan the Project                     Project Leader                    8h

                                          Design Engineer                   4h

                                          Product Marketing                4h

                                          Production Supervisor           4h

                                          Quality Control Specialist       4h

 

Gather Requirements              Project Leader                       16h

                                         Design Engineer                      8h

                                         Product Marketing                   8h

                                         Production Supervisor              8h

                                         Quality Control Specialist          8h

 

Review Requirements             Project Leader                        8h

                                         Design Engineer                      4h

                                         Product Marketing                   4h

                                         Production Supervisor              4h

                                         Quality Control Specialist         4h

 

Design Feasibility Study         Design Engineer                      30h

                                         Product Marketing                  20h

 

Design/Analysis                     Design Engineer                     30h

                                         Product Engineer                    45h

                                         Tooling Engineer                     8h

 

1st Generation Build               Production Engineer               10h

                                         Production Supervisor             5h

 

Competitive Engine Eval.        Design Engineer                     15h

                                         Test Technician                    15h

                                         Quality Control Specialist        15h

                                         Product Marketing                 8h

 

Customer Input                     Product Marketing                 10h

                                         Design Engineer                     1h

 

1st Life Test                        Test Technician                     30h

                                         Production Engineer               15h

 

Final Design Life Test            Design Engineer                     15h

                                        Quality Control Specialist         15h

                                        Test Technician                     15h

 

Performance Development     Design Engineer                      16h

                                        Production Engineer                 8h

                                        Product Marketing                   4h

 

Field Test                           Test Technician                      30h

Production Rollout                                                           -None-

5. Submit the MS Project Plan to the appropriate Dropbox.  Be sure to follow the Microsoft Project Guide example and the grading rubric for settings and final submission format of the plan.

Reference no: EM131700631

Questions Cloud

The organization of logistics activities within firm : Discuss several issues that influence the organization of logistics activities within a firm.
Consider before engaging in international marketing : In your opinion, what is the most important factor a company should consider before engaging in international marketing?
Evaluate your level of multicultural awareness : Were some questions more difficult to answer than others? Based on your answers to the survey questions, how would you evaluate your level of multicultural
Compute the amount of service costs : Using the data above, please compute the amount of service costs that would be allocated under the Direct, Step Allocation, and reciprocal method
Design feasibility study : Enter the following task names and durations. Be sure the Timescale is set to Month/Year (Middle Tier) and Weeks (Bottom Tier).
Describe two biases you experienced in your examination : Describe at least two biases you experienced in your examination of the topic. How did the biases support or contradict the position you took?
Kodak fails to focus on the big picture : Explain how—theoretically, anyway—making “change innovations” in each of the following Areas of Organizational Change might have helped
Analyse the companys history and growth : Analyse the companys history and growth - Competitive advantage is an advantage over competitors gained by offering consumers greater value
Describe a protagonist and an antagonist in your section : Name and describe a protagonist and an antagonist (person or thing) in your section and analyze the characters based on strengths and weaknesses.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd