Activity Days * Immediate Predecessor
a m b
A 8 10 12 -
B 6 7 9 -
C 3 3 4 -
D 10 20 30 A
E 6 7 8 C
F 9 10 11 B,D.E
G 6 7 10 B,D,E
H 14 15 16 F
I 10 11 13 F
J 6 7 8 G, H
K 4 7 8 I, J
L 1 2 4 G, H
* a=Optimistic time
m=Most probable or likely time
b=Pessimistic time
Solve for:
A) Construct a network for this problem
B) Determine expected time and variance for each activity
C) Determine Earliest Start time (ES), Earliest Finish time (EF), Latest Start time (LS), Latest finish time(LF), and slack time for each activity
D) Determine critical path and project completion time
E) Determine the probability that the project will be finished in 70 days or less
F) Determine the probability that the project will be finished in 80 days or less
G) Determine the probability that the project will be finished in 90 days or less
Please use Excel or QM for windows and explain as much as possible.
Collapse of monarchy predictable outcome of historical
: Was the collapse of monarchy in February 1917 predictable outcome of historical developments before 1914? Or was Tsarism probable to have survived had it not been for First World War?
|
Number of individuals responding favorably recorded
: An experimental drug is administered to 30 randomly selected indivduals, with the number of individuals responding favorably recorded. Does this represent a binomial experiment.
|
Describe research methods and process for limiting
: Please describe research methods and process for limiting the uncertainty in the decision to purchase a home or not. 700 word limit. Research Comprise how you applied concepts to formulate the decision.
|
Explain how does the answer change if a discount
: Suppose Sandra’s fears about increasing out-sourcing costs come to fruition and the cost rises to Rs. 22/unit for subcontracting. Does this change the decision when the discount is Rs. 5?
|
Description of pert problem
: Determine critical path and project completion time. Determine the probability that the project will be finished in 70 days or less. Determine the probability that the project will be finished in 80 days or less
|
Calculate the heat lost by each body
: Imagine that a hypothetical life form is discovered on our moon and transported to Earth. On a hot day, this life form begins to sweat, and it is determined that the heat of vaporization of its sweat is 365 cal/g.
|
Explain how much more will tickets cost foe lower bowl
: Fans sitting in the best seats in the upper deck will pay an increase from $440 to $540. Explain how much more will 2 tickets cost foe lower bowl?
|
What is the speed v_f of the package
: For all parts, assume that the "island" refers to the point at a distance D from the point at which the package is released. Ignore the height of this point above sea level. Assume that the acceleration due to gravity is g = 9.80m/s^2. What is the..
|
Conducting the one-tailed hypothesis test
: Conduct a one-tailed hypothesis test given the information below. A certain brand of Green Energy light bulbs was advertised as having an average illumination life-span of 2,500 hours.
|