Description of pert problem

Assignment Help Basic Statistics
Reference no: EM13103298

Activity Days * Immediate Predecessor

a m b

A 8 10 12 -

B 6 7 9 -

C 3 3 4 -

D 10 20 30 A

E 6 7 8 C

F 9 10 11 B,D.E

G 6 7 10 B,D,E

H 14 15 16 F

I 10 11 13 F

J 6 7 8 G, H

K 4 7 8 I, J

L 1 2 4 G, H

* a=Optimistic time

m=Most probable or likely time

b=Pessimistic time

Solve for:

A) Construct a network for this problem

B) Determine expected time and variance for each activity

C) Determine Earliest Start time (ES), Earliest Finish time (EF), Latest Start time (LS), Latest finish time(LF), and slack time for each activity

D) Determine critical path and project completion time

E) Determine the probability that the project will be finished in 70 days or less

F) Determine the probability that the project will be finished in 80 days or less

G) Determine the probability that the project will be finished in 90 days or less

Please use Excel or QM for windows and explain as much as possible.

Reference no: EM13103298

Questions Cloud

Collapse of monarchy predictable outcome of historical : Was the collapse of monarchy in February 1917 predictable outcome of historical developments before 1914? Or was Tsarism probable to have survived had it not been for First World War?
Number of individuals responding favorably recorded : An experimental drug is administered to 30 randomly selected indivduals, with the number of individuals responding favorably recorded. Does this represent a binomial experiment.
Describe research methods and process for limiting : Please describe research methods and process for limiting the uncertainty in the decision to purchase a home or not. 700 word limit. Research Comprise how you applied concepts to formulate the decision.
Explain how does the answer change if a discount : Suppose Sandra’s fears about increasing out-sourcing costs come to fruition and the cost rises to Rs. 22/unit for subcontracting. Does this change the decision when the discount is Rs. 5?
Description of pert problem : Determine critical path and project completion time. Determine the probability that the project will be finished in 70 days or less. Determine the probability that the project will be finished in 80 days or less
Calculate the heat lost by each body : Imagine that a hypothetical life form is discovered on our moon and transported to Earth. On a hot day, this life form begins to sweat, and it is determined that the heat of vaporization of its sweat is 365 cal/g.
Explain how much more will tickets cost foe lower bowl : Fans sitting in the best seats in the upper deck will pay an increase from $440 to $540. Explain how much more will 2 tickets cost foe lower bowl?
What is the speed v_f of the package : For all parts, assume that the "island" refers to the point at a distance D from the point at which the package is released. Ignore the height of this point above sea level. Assume that the acceleration due to gravity is g = 9.80m/s^2. What is the..
Conducting the one-tailed hypothesis test : Conduct a one-tailed hypothesis test given the information below. A certain brand of Green Energy light bulbs was advertised as having an average illumination life-span of 2,500 hours.

Reviews

Write a Review

Basic Statistics Questions & Answers

  Probability of average iq from random sample

What is the probability that the average IQ, from a random sample of 64 individuals, is greater than 102?

  Random variable representing a test score

Let x be a random variable that represents a test score. What is the lowest score that would still place a student in the top 40% of the scores?

  Probability distribution for the number of travelers

Develop a probability distribution for the number of travelers who plan their trips within two weeks of departure.

  Estimating sample size for population mean

We want to estimate the population mean within 5, with a 99% confidence level. The population std dev is estimated to be 15.  How large is the required sample size?

  Reasons for studying statistics

Critically discuss the reasons for studying statistics? Choose five random numbers between 70-100. Calculate the mean, and midrange of these numbers.

  Control limits for mean and range

Determine the control limits for the mean and the range. Plot the control limits for the mean outside diameter and the range.

  Treatments and blocking variables

Support your contention with three examples from your experience at other organizations or departments. Where applicable, for each example, indicate what are the treatments and blocking variables.

  Mcqs-uniform probability

It takes between 6 to 7.5 hours to drive from Panama City to Boquete, and the drive time is uniformly distributed.

  Caribbean following the normal distribution

The number of passengers on the Carnival Sensation during one-week cruises in the Caribbean follows the normal distribution.

  Computing confidence interval-absent for sickness

Create a 95% confidence interval for the population mean days absent for sickness based on this sample. Select the answer closest to your results.

  Probability-surgery is successful for at least four patients

A surgical technique is performed on seven patients. You are told there is a 70% chance of success. Find the probability that the surgery is successful for at least four patients.

  Probability distribution-mean and variance

The following problem develop the concept of determining the probability distribution of random variable and its mean and variance.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd