Reference no: EM131229817
1. Which of the following describes a critical path?
a. The path taking longest time through this network of activities
b. The path taking shortest time through this network of activities
c. Hierarchy of project tasks, subtasks, and work packages
d. Stable workforce, variable work hours
2. Which of the following describes a pure project?
a. Inventory on hand and financing costs for that inventory
b. A self-contained team works full time on the project
c. Project houses within a functional division
d. Blend of pure and functional project structures
3. Which of the following describes the benefit of a functional project?
a. The project manager has full authority over the project
b. Team pride, motivation, and commitment are high
c. Technical expertise is maintained within the functional area
d. Needs of the client are secondary and are responded to slowly
Minimum number of female applicants the company should hire
: Central Valdosta Manufacturing Corporation had 100 male applicants last year. They hired 60 of them. They also had 50 female applicants of which they hired 20. In order to avoid adverse impact, what is the minimum number of female applicants the comp..
|
Consider the two auto manufacturing plants
: Consider the two auto manufacturing plants below: How much is the annual output of each plant? How much is the flow time in each plant? How much is the WIP inventory in each plant?
|
How should project risks be monitored and controlled
: How should the risks be prioritized? Who should do the prioritization of the project risks? How should project risks be monitored and controlled? Who should develop risk responses and contingency plans? Who should own these responses and plans?
|
What should be considered when identifying risks
: Assume you have just been assigned to a project risk team composed of five members. Your task, as project manager, is to develop a process for handling risks to the project. What methods should be used for identifying risks? Who should be involved in..
|
Describes critical path and pure project
: Which of the following describes a critical path? Which of the following describes a pure project? Which of the following describes the benefit of a functional project?
|
Independent hotel-caters to both business-leisure travelers
: The Evanstonian is an upscale independent hotel that caters to both business and leisure travelers. On average, one-third of the guests checking in each day are liesure travelers. Leisure travelers generally stay for 3.6 nights-twice a long as the av..
|
Ethics-business organizations
: In hiring a prospective employee, there are legitimate reasons for not hiring someone. For example, the prospective employee may not meet legal requirements. Identify and clearly define the relevant law utilized by the court in determining the outcom..
|
About diversity in a multicultural environment
: Write a paper with at least 300 words about Diversity in a Multicultural Environment. Make a summary and give a reference or two to how you personally can use and implement this information in your life. This is a reflection paper.
|
Why should skipper products implement a ppm
: You are the CEO for Skipper Products. The business has had a great year and you see that a PPM is needed to manage all the projects that are currently in progress, along with future projects. Why should Skipper Products implement a PPM?
|