Describe what the results of calculation mean

Assignment Help Project Management
Reference no: EM132348412

Use the following information to answer parts athrough h. Describe what the results of each calculation mean to you as a project manager. What do you propose to do?

PV = $25,000 

EV = $30,000 

AC = $29,000 

BAC = $1,000,000 

a. Schedule variance (SV) 

b. Cost variance (CV) 

c. Schedule performance index (SPI) 

d. Cost performance index (CPI) 

e. Estimate to complete (ETC-first method) 

f. Estimate to complete (ETC-second method) 

g. Estimate at completion (EAC) 

h. To-complete performance index (TCPI)

Reference no: EM132348412

Questions Cloud

Guidelines for heuristic evaluation of interface : Using the guidelines for a heuristic evaluation of an interface from chapter 15 of the textbook,
Completion of a project benefit the project manager : How does celebrating the completion of a project benefit the project manager?
Provide an example of at least one team member : Explain how you identified the need for coaching, the details of the coaching you delivered and the result. how did you know if it was successful or not?
Advice on the practical application of theory : Building and Marketing High Performing Organisations - MKT11445 - Edinburgh Napier University - briefly introduce your chosen organisation to familiarise
Describe what the results of calculation mean : Use the following information to answer parts athrough h. Describe what the results of each calculation mean to you as a project manager.
Success of pricing strategy depends upon customers : The Nagle, et.al. textbook states: "Ultimately, the success of pricing strategy depends upon customers being willing [and able] to pay the price you charge."
Element of the worker compensation claim process : Importance and methods of investigating and documenting work-related injuries as an element of the worker's compensation claim process
Already approved project scope : Your client has requested a change that is considered feasible but is outside of the already approved project scope. What should occur if the change is approved
How it might impact our lives-associated security concerns : This has impacted the way live, work and do business. Research an evolving technology and discuss how it might impact our lives and associated security concerns

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd