Question 1
As a project manager, you can always shorten the duration of the critical path by shifting resources to those tasks.
Select one:
True
False
Question 2
In order for any project to get approved in a business, it must support the increase of revenues.
Select one:
True
False
Question 3
For the network diagram shown, what is the critical path? (Select 1)
Select one or more:
a. ADFG
b. ABCEG
c. ABEG
d. ACEG
Question 4
It is common for the critical path to shift through the execution of a project.
Select one:
True
False
Question 5
In a functional organizational structure: (select 2 or more)
Select one or more:
a. Staff will usually report to more than one boss.
b. Teams are organized according to the project they are working on.
c. Staff are organized by their job responsibility
d. Staff will usually become very specialized in their discipline
Question 6
Explain the differences between unit testing and system testing. Please include insight on who typically conducts each of these test types.
Question 7
Which of the following is an example of a systems development life cycle? (select 2 or more)
Select one or more:
a. Risk management model.
b. Incremental model.
c. Work breakdown structure.
d. Waterfall model.
Question 8
The Agile Manifesto values "Working software over comprehensive documentation". Explain how this is in contrast to the predictive life cycle and the concept of tracking progress through task completion.
Question 9
Write a brief paragraph describing the systems development life cycle (SDLC) you recommend that your team use for the implementation phase for your project. Explain why you recommend this approach.
Question 10
Why should you always create a project charter at the start of a project (select 1 or more)?
Select one or more:
a. To get project team members aligned on the business value of the project and key success criteria.
b. Because it is important to identify clearly all of the tasks and milestones for the project before you start.
c. To ensure stakeholders in the organization have a clear understanding of the goals of the project.
Question 11
Scope management only applies to projects with an IT focus.
Select one:
True
False
Question 12
The primary contributor to cost for a software development project is: (select 1)
Select one or more:
a. Facilities, including desktop computers for development
b. Hardware for test and development
c. Software licenses
d. Labor
Question 13
For the defect histogram shown, what defects should we focus on addressing first? Use the Pareto principle. (Select 2 or more)
Select one or more:
a. User interface bug
b. Logic error
c. Database transaction
d. Network interruption
Question 14
If you were managing an agile development project, explain how you would build your work breakdown structure (WBS)
Question 15
For the project you selected to implement as a team (next term), identify three risks that could impact your ability to successfully deliver on your project goal. For each risk, indicate the following: (1) HIGH or LOW probability of occurring, (2) HIGH or LOW impact on the project.
Question 16
Traditional project manager's use earned value management to track costs and task completion on a project. On an agile project, the project manager would use this similar chart: (select 1)
Select one or more:
a. Network dependency graph
b. Product backlog burndown chart
c. PERT chart
d. Work breakdown structure
Compare and contrast this with the ea methodology
: The collaborative planning Methodology is the full planning and implementation lifecycle for use at all levels of scope defined in the common approach to federal enterprise architecture for the United States. A summary of the methodology is shown ..
|
Find the core
: Larger amounts of money invested in things like CDs (certificates of deposit) get a better rate of return. Suppose the rates of return depend on the amount invested as follows.
|
Describe sampling technique and method of data collection
: What are the essential questions that the research sets out to answer? What is the researcher's hypothesis? Describe the sampling technique and the method of data collection.
|
Future value in four years of ordinary annuity cash flow
: What is the future value in 4 years of an ordinary annuity cash flow of $942 every quarter of a year at the end of the period at an annual interest rate of 8.79 percent per year compounded quarterly. Round to two decimal places
|
Describe the systems development life cycle
: Explain the differences between unit testing and system testing. Please include insight on who typically conducts each of these test types.Which of the following is an example of a systems development life cycle?
|
Create legal precedent employees disclose information
: If arbitration decisions do not create legal precedent then can employees disclose information discussed in arbitration hearings to other parties without the company's consent, such that it may be used in subsequent disputes?
|
Find the characteristic function
: Consider the bimatrix game with (a) Find the characteristic function of this game. (b) Find the core of the game C(0). (c) Find the least core.
|
What is your definition of risk management
: Conduct a survey of at least five people in your organization. The five people (preferably more) should be from different departments of your organization and preferably at different levels of seniority. What is your definition of risk? What is your ..
|
What will be the price of each bond if their yields increase
: Consider three bonds with 5.5% coupon rates, all making annual coupon payments and all selling at a face value of $1,000. The short-term bond has a maturity of 4 years, the intermediate-term bond has maturity 8 years, and the long-term bond has matur..
|