1) Brainstorming is a fundamental tool of problem solving

2) A process is capable if the variations fall within +- 3 standard deviation

3) Random variationsfall outside the control limits.

4) Control charts are used to determine if there are special cause variation in the process.

5) 3 items in parallel, each having a reliability of 0.90 have an overall system reliability of 0.999.

6) nP chart is used when the number of defects per unit is fixed at n

7) A process in control may produce unacceptable output.

8) A Six Sigma process must have a process capability index of 6.

9) For a Normally distributed process the control limits are + - 3 times the standard deviation

10) A Control Chart is a Trend Chart (or Run Chart) that has control limits

Part B.

1. Which of the following tools are used to get the shape of the distribution.
A) Matrix diagram
B) Histogram
C)Affinity Diagram
D) Check sheets
E) Process map

2. Which of the following tools are used to find the relationship between two variables?

A) Process Map
B) Fishbone diagram
C) Pareto Chart
D) Scatter plot
E) Control chart

3. Which of the following is true of special cause variation?

A) It is uncontrollable.
B) It is centered around the mean.
C) It is inherent in the process.
D) All of the above.
E) None of the above

4. A true 3 Sigma Process should not have more than _______defects per million opportunities
A. 6,210
B. 3.4
C. 2700
D. 45500

5. An R chart is used to monitor __________.

A. Variation of the Mean
B. Process Dispersion
C. Trend in mean value
D. Trend in standard deviation

Part C

1) 97. 1) A product is made up of two subsystems in series. The first subsystem consists of 20 components in series. The second subsystem consists of 3 components in parallel. The components in subsystem 1 are all of the same design and each has a 1/10,000 chance of failure. The parallel components each has a 3/10,000 chance for failure. What is the overall reliability of the system?

2) A quality control engineer monitors the quality of a cylinder production line. He regularly selects a sample of 5 units and measures the diameters. The specification requires the diameter to be 6 inches plus/minus 0.1 inch. The following is a record of the measurements.Is the production process in control? Please use X bar and R charts to make an assessment.

Sample

item 1

item 2

item 3

item 4

item 5

1

6.10

6.15

5.35

5.98

5.95

2

6.35

6.02

6.20

6.10

5.70

3

5.85

5.90

6.20

6.12

6.08

4

6.00

5.80

5.70

6.04

6.17

5

6.15

5.60

6.25

5.99

6.01

6

6.13

6.05

5.89

6.00

5.87

7

5.88

6.03

5.76

6.1 3

6.00

8

6.12

5.45

6.15

6.04

5.91

3) A customer relationship manager decided to track customer complaints as part of his ongoing customer satisfaction improvement program. After collecting data for two months, their check sheet appears as follows:

Type of Problem

Frequency

(number of times)

Call went to voice mail

8

Items damaged when received

21

Literature not in the box

9

Parts missing

13

Unit not working

2

Delivery was late

3

Construct a Pareto chart including the cumulative % frequency.What is the cumulative percentage of the two leftmost bars?

4) A project manager at Global Design Corporation has collected the following data on the size of software programs and the length of programming time. The company is bidding on a new system that is estimated to consist of 250,000 lines of code. Use the data to find the correlation function of coding time to the program size and estimate the number of days it would take to code the system.

Module

Size in 1000 lines of code (KLOC)

Number of days to code

1

160

68

2

158

66

3

148

70

4

135

59

5

178

72

6

170

68

7

158

64

8

138

65

9

200

70

10

195

68

11

189

65

12

173

68

13

159

70

14

163

71

15

150

66

16

140

65

17

206

73

18

144

64

19

157

70

20

183

74

21

195

75

22

190

77

23

182

69

24

152

65

25

174

69

5) Describe the Sources of Team Conflict

6) Describe the 5 principles of Lean

Reference no: EM131945336

Questions Cloud

What is the net annual cash flow : The equipment has a five-year life and an estimated salvage value of $50,000. What is the net annual cash flow
How is time management an example of reaping what we sow : As you review your time chart, what changes will you need to make to be successful in your schoolwork? If you do not see the need for change, explain why.
Write the null and alternative hypotheses for test : a. Write the null and alternative hypotheses for this test:
Operations are compliant to current environmental laws : CFO of Cero Inc.: Our operations are compliant to the current environmental laws
Describe the sources of team conflict : Describe the Sources of Team Conflict and Describe the 5 principles of Lean - Which of the following tools are used to get the shape of the distribution
How you rate as a disease detective based on points earned : Identify the outbreak you had chosen to solve. Discussed how you rate as a disease detective based on points earned in the game?
What amount of revenue should indigo cellular recognize : Students may renew the service for each year they are on campus, What amount of revenue should Indigo Cellular recognize in the first year of the contract
What will be optimal cash return point : HotFoot Shoes would like to maintain its cash account at a minimum level of $39,000, What will be its optimal cash return point?
Prepare stockholders equity section for whispering company : Preferred Stock, 160,200 shares $ 3,204,000. Prepare the stockholders' equity section for Whispering Company at December 31, 2018

Reviews

Write a Review

Project Management Questions & Answers

  Developing an implementation plan

Prepare an approach for estimating project time and cost and develop a resource scheduling process.

  Question about systems analysisprepare a paper that

question about systems analysisprepare a paper that analyzes an it work-related project or fictitious project using

  Disaster recovery plan - project manageryou have been

disaster recovery plan - project manageryou have been appointed as a project manager in charge of security setup and

  Using the assembly-line balancing procedure

Using the assembly-line balancing procedure, what is the theoretical minimum number of workstations if the task times for the six tasks that make up the job

  Define and discuss the agile project management model

a) Define and discuss the Agile project management model and explain what the SCRUM approach is in this context.

  Steps to starting project size of directed research project

What do you feel are important first steps when it comes to starting a project the size of the directed research project?

  Project management-questionneed a suggestion on what would

project management-questionneed a suggestion on what would be good source to research a recent project on project

  Develop an infrastructure of your projects management system

Describe to your project sponsor how you intend to develop and implement an infrastructure of your project's management systems.

  Project risks1 consider you are the project manager of a

project risks1. consider you are the project manager of a team of software specialists working on a project to produce

  What was the scoop deliverable and results of the project

What was the scoop, deliverable, and results of the project? What constraints did you experience and how did you handle them?

  How would you identify a key stakeholder

How would you identify a key stakeholder? Then, once you have identified that key stakeholder, how would you determine which form of communication to use? Can (and should) you have multiple forms of communication going for each of your key stakeho..

  Risk management in any environment

Are you directed not to take risks, or does your company encourage risk taking if you can justify the results perhaps having a greater reward than the costs

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd