Describe the ideal approach for a project manager

Assignment Help Management Theories
Reference no: EM131465203

1. A good starting point for developing time and cost estimates is:

A. past experience

B. work packages

C. time and motion studies

D. a Work Breakdown Structure

2. Which of the following is a reason to estimate?

A. To support good decisions

B. To determine whether the project is worth doing

C. To determine how long the project should take and its overall cost

D. All the given answers are correct.

3. John is looking over the actual results of projects and comparing them to what was estimated. He notices that projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is he recognising?

A. Padding estimates

B. Planning horizon

C. Project structure

D. People

4. Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $25 000 in expenses will cover her needs. Because management typically insists on reducing forecasts by 20 per cent, she increases her estimates to allow for that reduction. Which of the following factors is illustrated in this situation?

A. Padding estimates

B. Planning horizon

C. Project structure

D. People

5. Which of the following is a good condition for top-down estimating?

A. Cost and time important

B. Fixed price contract

C. Customer wants details

D. Internal, small project

6. Which of the following is a good condition for bottom-up estimating?

A. Internal, small project

B. Fixed price contract

C. High uncertainty

D. Both B and C are good conditions for bottom-up estimating

7. Which of the following methods is not considered a top-down approach to estimating project time and cost?

A. Ratio

B. Template

C. Apportion

D. Learning curve

8. Fred is forecasting project time and cost for constructing a new building by multiplying the total square footage by a given dollar amount. Which of the following methods is he using?

A. Parametric

B. 3-point (PERT)

C. Learning curves

D. Analogous

9. Sean is forecasting the time and cost of developing a customised software program by looking at the number of inputs, outputs, inquiries, files and interfaces. Which of the following methods is he using?

A. Parametric

B. 3-point (PERT)

C. Function point

D. Analogous

10. Laura is forecasting the time and cost of developing an intranet for a new customer. Her department has completed six such intranets for customers during the last two years. Although the proposed system is about the same size as the others she estimates that it will take about 10 per cent less time and money. Which of the following methods is she using?

A. Parametric

B. Learning curves

C. Function point

D. Analogous

11. Which of the following would be the best method for projects where the final product is not known and there is a lot of uncertainty?

A. Function point

B. Template

C. Learning curve

D. Phase estimating

12. What elements of a work package are estimated?

A. Time (duration)

B. Cost

C. Resources (labour and other)

D. All the given answers are correct.

13. Which of the following would be considered a direct project cost?

A. Labour

B. Materials

C. Equipment

D. All the given answers are correct.

14. Resource shortages, in the form of people, equipment or materials, is a good example of:

A. hidden interaction costs

B. things going wrong on a project

C. normal conditions not applying

D. changes in project scope

15. A manager getting further into a project and obtaining a better understanding of what needs to be done to accomplish a project is an example of:

A. hidden interaction costs

B. things going wrong on a project

C. normal conditions not applying

D. changes in project scope

16. Design flaws being revealed after the fact, extreme weather conditions and accidents occurring are all examples of:

A. hidden interaction costs

B. things going wrong on a project

C. normal conditions not applying

D. changes in project scope

17. Project estimates should be broken down into as much detail with as much accuracy as possible.

True False

18. The use of past experience is almost always used primarily in the initial phases of a project.

True False

19. The project structure chosen to manage the project will have little impact on the actual project work to be accomplished.

True False

20. As long as everyone in a project adds just a little padding to reduce risk, the project duration and costs are probably overstated by only a small amount.

True False

21. Organisation culture can significantly influence project time and cost estimates.

True False

22. Identify and briefly describe the three major approaches to estimating project time, costs and resources.

23. Why are the estimates for a project's time and costs important for all phases of a project?

24. Identify the factors that should be considered to improve the quality of estimates for project times and costs.

25. Identify the three major categories of project costs and give an example of each.

26. ‘The best way to improve estimates is to collect and archive data on past project estimates and actuals.' Agree or disagree and support your answer.

27. Describe the ideal approach for a project manager to develop optimal estimates for a project's time and costs.

Reference no: EM131465203

Questions Cloud

Write a memo proposing and advocating for launch a product : Write a memo proposing and advocating for the launch of a new product or service to the company president.
Draw free-body diagrams and derive the equations of motion : The framed structure shown in Figure has two square floors. The bottom floor has mass m1 = 2000 kg and is supported to the foundation by four solid column
What is wrong with soda and fruit juices : What is wrong with soda and fruit juices? What is high fructose corn syrup, why is it being used and how is it damaging our health? What is leptin and ghrelin?
What is your best estimate of the damages : What is your best estimate of the damages that the plaintiff has suffered as a result of your client's breach of contract
Describe the ideal approach for a project manager : Describe the ideal approach for a project manager to develop optimal estimates for a projects time and costs - project costs and give an example of each.
Describe the processes of conceptual design : Describe the processes of conceptual design, logical design, and physical design.
Which size dna fragment did child inherit from her mother : Which size DNA fragment did the child inherit from her mother? Which alleged father, if any, can be definitively ruled out as the child's biological father?
What is a constant growth stock : Write out a formula that can be used to value any stock,regardless of its dividend pattern. What is a constant growth stock?
Conditions for using the standard deviation formula : What are the conditions for using the standard deviation formula when conducting a significance test? Be specific about p versus p-hat.

Reviews

Write a Review

Management Theories Questions & Answers

  Learning in action

Learning contract proposal that will form the basis of your learning contract report.

  Change is the only constant

"Change is the only constant " Evaluate the different types of change that have occurred in Sony.

  How do advertisers try to use group influence

How do advertisers try to use group influence?  Will you find any specific examples and explain the relevant theory of group behavior and influence?

  Case study:saving sony

You have been appointed by Sony as a consultant on change management. Advise Sony on how they could implement the change by using the various theories of change you have learnt.

  How the stock market works

The purpose of this project is to help you to gain an understanding of how the stock market works and of the relationship between theory and practice.

  Find the optimal production quantities

Find not only the optimal production quantities, but also the optimal total cost.

  Describe the management process

Describe the management process and identify the skills required to manage business organizations.

  Case study : bert''s bonsai and aquatic sport museum

Case Study : Bert's Bonsai and Aquatic Sport Museum Prepare a knowledge management system.

  Knowledge management techniques

Demonstrate understanding of the many-sided nature of knowledge management

  Theory of transtheoretical model

Demonstrate understanding of the many-sided nature of knowledge management

  Write a paper on historical trends of management

Write a paper on Historical Trends of Management.

  Theory of reasoned action

Theory of Planned Behavior and Integrated Behaviors Model

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd