Describe one plausible risk response for each of the risks

Assignment Help Project Management
Reference no: EM133564377

Case Scenario:

The Quick Drop 100 transition team has met to identify project risks, explore contingency plans, and assign owners to watch for symptoms and address the risks. The team surfaced the following information:

  1. Julie is scheduled for a one week vacation during month three of the project.
  2. The supplier of a common set of hand tools for the manufacturing floor notified the Roto Air Purchasing department that the tools will not be available until one month after manufacturing is scheduled to start. Alternative suppliers are available.
  3. The Human Resources department has indicated that despite their best recruiting efforts the two openings for skilled welders have resulted in no qualified local applicants.
  4. The manufacturer of the custom-built rotor forming machine now expects to be one month past the last acceptable date for installing the machine. No other suppliers exist for this item.
  5. Roto Air uses a Just In Time (JIT) delivery system for major components used at the Florida plant. Hurricane season often interrupts or delays deliveries during one of the scheduled months of the project.

Assignment Instructions

This week you will be essentially doing two related assignment in one MS Word document. The first part is a status report. The second part is an academic paper.

Part 1 Status Report:

Prepare a simple status report for senior management by creating a table within a MS Word. For each of the five risks include in the table the following:

  1. Determine if each risk should be classified as low, medium, or high based on its impact to the project.
  2. Differentiate the risk classifications in the table using red, yellow, and green shading using, red for high, yellow for medium, and green for low to produce a status report that immediately signals the severity of the impact without reading the details.
  3. Describe one plausible risk response for each of the risks.
  4. Identify a team member to be responsible for monitoring each risk.

Reference no: EM133564377

Questions Cloud

Using what you have learned about genetics : Using what you have learned about genetics, explain how baby Sally could inherit Fanconi anemia even though neither parent suffers from it.
Explain why you have chosen the model : Models can be found in leadership, business, education, and technology. Explain why you have chosen the model. Apply the model to your advanced practice role.
Which would have the largest influence on the employees : Do you think that it would be easy to influence a subordinate's attitudes, values, or emotions? Why? Which would have the largest influence on the employee
Has this issue been addressed by management to date : Is the issue a common issue in healthcare or nursing practice, or is this issue? Has this issue been addressed by management to date? If so, how?
Describe one plausible risk response for each of the risks : Determine if each risk should be classified as low, medium, or high based on its impact to the project. Differentiate the risk classifications in the table
Discuss some of the data that you found interesting : Discuss some of the data that you found interesting and include what you believe the purpose (intent) of sharing these results.
Discuss common issues leaders should understand regarding : discuss common issues leaders should understand regarding liabilities and equity." Brief Introduction, (accounts payable, retained earnings, short term debt
How course helped you begin to form professional identity : Include how this course helped you begin to form your professional identity as a nurse. Include how you will continue to form your professional identity.
In what ways does lean encourage participation : What are ways to keep staff engaged in outcome measures? In what ways does Lean encourage participation by frontline staff members?

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd