1. It is the end of the second week of July. Crystal Hamaty, the manager of a road construction project, has noted in her contract with the city of Hershey, Idaho that there will be a $15,000 per week penalty for every week that the project extends past its end-of-September due date. Additionally, the city has offered to pay a bonus of $20,000 if her crew can finish the project by the end of the third week of September. Ms. Hamaty plans to start work at the beginning of the third week of July. The mayor wishes to avoid problems with snow, which often arrives early because of Hershey's location at 5,853 feet (1,784 meters) above sea level. For the sake of simplicity, we assume exactly four weeks and 20 workdays for every month. The project network, with normal times, is displayed below:
a. Draw a network diagram for this project. Your diagram should show the ES, EF, LF, LS, and Slack. Follow the diagram structure we discussed in class.
b. Calculate the crash cost per week for each activity.
c. Show the sequence of crashing decisions you would make to compress this project most cost effectively. Calculate total cost. Keep in mind that the penalty is incurred for every week past the end of September, and remember to consider the bonus.
d. Explain your rationale and describe how you would present the options to the Hershey City Council.
Difference between psychology and physiology
: Identify abused substances and their various effects. Include the following: Explain the psychology and physiology of addiction and identify specific drug substances covering the following categories
|
What are the causes of her distress
: Explain what general type of distress does Andrea have here and what type of general reaction has she chosen? Support your answer.
|
Find the angular acceleration of the disk
: A wheel has eight spokes and a radius of 33.0 . It is mounted on a fixed axle and is spinning at 2.80 . You want to shoot a 38.0 long arrow through the wheel, parallel to this axle, without hitting any of the spokes. Assume that the arrow and the ..
|
What drives consumption of costs
: What drives consumption of costs? What are drivers and how do they help in the allocation process?
|
Depict a network diagram for this project
: Depict a network diagram for this project and Your diagram should show the ES, EF, LF, LS, and Slack. Follow the diagram structure we discussed in class.
|
Number of rtcp bandwidth allocated to receiver
: Let RTP session consisting of four users, all of which are sending and receiving packets to same multicast address. How much RTCP bandwidth will each receiver be allocated?
|
Classification of development costs
: Masters Golf Products, Corporation, spent 3 years and $1,000,000 to develop its new line of club heads to replace a line that is becoming obsolete. To start manufacturing them, the company will have to invest $1,800,000 in new equipment.
|
Fear or stress about big changes in a hospital setting
: What happened in hindsight - Was it really that bad and did you become more confident because new skills where acquired?
|
Finding optimal price and output levels
: Currently the total cost is given by TC = 100 + 10Q +Q^2 for sale shoe manufacturing company. The demand equation is given by P =-5Q +130.
|