On November 15, 1998, the Department of Energy Resources awarded Telestar a $475,000 contract for the developing and testing of two waste treatment plants. Telestar had spent the better part of the last two years developing waste treatment technology under its own R&D activities. This new contract would give Telestar the opportunity to "break into a new field" -that of waste treatment.

The contract was negotiated at a firm-fixed price. Any cost overruns would have to be incurred by Telestar. The original bid was priced out at $847,000. Telestar 's management, however, wanted to win this one. The decision was made that Telestar would "buy in" at $475,000 so that they could at least get their foot into the new marketplace.

The original estimate of $847,000 was very "rough" because Telestar did not have any good man-hour standards, in the area of waste treatment, on which to base their man-hour projections. Corporate management was willing to spend up to $400,000 of their own funds in order to compensate the bid of $475,000.

By February 15, 1999, costs were increasing to such a point where overrun would be occurring well ahead of schedule. Anticipated costs to completion were now $943,000, The project manager decided to stop all activities in certain functional departments, one of which was structural analysis. The manager of the structural analysis department strongly opposed the closing out of the work order prior to the testing of the first plant's high-pressure pneumatic and electrical systems.

Structures Manager: "You're running a risk if you close out this work order. How will you know if the hardware can withstand the stresses that will be imposed during the test? After all, the test is scheduled for next month and I can probably finish the analysis by then. "

* Revised, 2008.

Case Studies

Project Manager: "I understand your concern, but I cannot risk a cost overrun. My boss expects me to do the work within cost. The plant design is similar to one that we have tested before, without any structural problems being detected. On this basis, I consider your analysis unnecessary.

Structures Manager: "Just because two plants are similar does not mean that they will be identical in performance, there can be major structural deficiencies.

Project Manager: "I guess the risk is mine.

Structures Manager: "Yes, but I get concerned when a failure can reflect on the integrity of my department. You know, we 're performing on schedule and within the time and money budgeted. You're setting a bad example by cutting off our budget without any real justification.'

Project Manager: "I understand your concern, but we must pull out all the stops when overrun costs are inevitable. "

Structures Manager: "There's no question in my mind that this analysis should be completed. However, I'm not going to complete it on my overhead budget. I'll reassign my people tomorrow. Incidentally, you had better be careful; my people are not very happy to work for a project that can be canceled immediately. I may have trouble getting volunteers next time. "

Project Manager: "Well, I'm sure you'll be able to adequately handle any future work. I'll report to my boss that I have issued a work stoppage order to your department. "

During the next month 's test, the plant exploded. Post analysis indicated that the failure was due to a structural deficiency.

a. Who is at fault?

b. Should the structures manager have been dedicated enough to continue the work on his own?

c. Can a functional manager, who considers his organization as strictly support, still be dedicated to total project success?

Reference no: EM132395943

Questions Cloud

How are projects selected in project management : How are projects selected in project management? What kind of methods are used? Why is it important that the project aligns with the corporate strategy?
What is project integration management : What is project integration management? How does the process work? Why is it used? Why is it important in project management?
Construct the first diagram in a process model : We will concentrate on how to construct the first diagram in a process model called a context data flow diagram (CDFD). Give an illustration
Project manager intervene immediately : Can an organization establish formal organizational procedures for conflict resolution? Is this strategy likely to be successful?
Department of energy resources : On November 15, 1998, the Department of Energy Resources awarded Telestar a $475,000 contract for the developing and testing of two waste treatment plants.
Organization performance excellence : Explain to the board of directions to determine how the organization's performance excellence can be improved by transitioning to a divisional structure?
Briefly describe market penetration and market development : Briefly describe each strategy i.e market penetration, market development, and product development and then provide a real-world example of each.
Discuss about the use of medication : National Institutes of Health NIH.gov and put in the words ADHD and preschool in the search engine. Find one of the brief articles that are based.
Multiple projects under one mission or vision : Could you explain how a company might manage and lead multiple projects under one mission or vision? Can the same apply to a household?

Reviews

Write a Review

Project Management Questions & Answers

  Create a blog post that provides your analysis

Create a blog post that provides your analysis of how the organisation or product you selected was positively or negatively impacted by external environmental factors, and what, if anything, the organisation did in response. Be sure to support you..

  Describe the components of a situation analysis

Describe the components of a situation analysis. In the situation (or SWOT) analysis, the firm should identify its internal strengths (S) and weaknesses (W) and also examine external opportunities (O) and threats (T).

  Show the functional elements of parent organization

The functional elements of parent organization are adopted as the basis of administration of the project - Virtual project management is the system by which virtual teams collaborate for a finite period of time towards a specific goal

  Difference between line positions and staff positions

How would the span of control differ for a firm with numerous employees who perform similar tasks and for a firm with highly diverse tasks? What is decentralization?

  What production issues are not included in data presented

Monczka-Trent Shipping is the logistics vendor for Handfield Manufacturing Co. in Ohio.  -Which option is more economical?  - What production issues are not included in the data presented?

  What facts gave rise to the thornhill indictment

State the gist of Section 3448 of the Alabama Code.- What facts gave rise to the Thornhill indictment?- Did the Supreme Court hold Section 3448 invalid on its face?

  Since the hospitals project budgeting approach is under the

since the hospitals project budgeting approach is under the microscope due to several large public budget overruns

  How well the data collection process worked or did not work

How well the data collection process worked or did not work, how you compiled the data for the purposes of feedback, and the subsequent analysis.

  Retail store major project proposal

Develop a major project proposal to be undertaken by your employer (WAL-MART) - You may decide to expand your product offerings or open an additional store

  Develop an appropriate metric

Develop an appropriate metric - this sets the target and expectation of all the stakeholders. Identification of specific deliverables for the project as whole

  Explaining need for project trade-offs

When managing project trade-offs it is important to understand the root cause of the conflict and why the need for trade-offs exists.

  What type of information would be useful for feedback

A marketing plan is a written document that covers the situation, objectives, and actions for an organization for the time period covered by the plan.The time period covered by the plan depends on the volatility of that organization's market:Annu..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd