Define the critical path and listing all critical activities

Assignment Help Operation Management
Reference no: EM13781813

The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede:

Activity Duration (weeks) Precedes

A (start) 1 B, C

B 1 E

C 4 F

E 2 F

F (end) 2 _

a) Draw an AON diagram of the project including activity durations

b) Define the critical path, listing all critical activities in chronological order and list the project duration (in weeks)?

c) What is the project duration in weeks?

d) What is the slack in weeks with any and all noncritical paths through the project?

Reference no: EM13781813

Questions Cloud

Marketing plan for coach inc : Marketing Plan for Coach Inc:Advertising and Promotion? Marketing Research? Controls? Contingency Planning?
Calculate maximum change in money supply from transaction : Matthew and Kyle live and bank in Texas. The reserve requirement is 20%. If Matthew sells government bonds to Kyle for $1,000,000, will the money supply likely rise, fall, or not change?
Focus on the cons of technology and future technology : Mostly to focus on the Cons of Technology and future technology. No double space. Single space only. Times new roman. 12font. Also a page that includes the references.
Describe and implement virtual local area networks : Describe and implement Virtual Local Area Networks (VLANs) on a computing network. Compare and contrast dynamic routing, distance vector routing, and link-state routing protocols.
Define the critical path and listing all critical activities : The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede: Define the critical path, listing all critical activities in chronological order and list the project du..
Discuss substantive ways in which armed conflictcan contribu : Discuss substantive ways in which armed conflictcan contribute to or distract a developing economy and infrastructure.  Analyze specific reasons why developednations do not experience the same kinds of social upheaval.
What is a differentiation strategy : What is a differentiation strategy? How is it connected to market share gain? Profits? Competitive advantage? What are typical characteristics of a differentiation strategy? What are the challenges or potential disadvantages of this strategic initiat..
Model in formulating strategy : List the 5 intensity forces. Describe each force. Also describe how and why organizations use this model in formulating strategy.
Determine the top-two aspects of the selection process : Determine the top-two aspects of the selection process that you would focus on when selecting candidates for positions in an organization where you work or another company where you are familiar, and explain your rationale

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd