The following is a table of activities associated with a project , their duration and what activities each must precede: Activity duration(weeks) precedes A start 1 B,C B 1 E C 4 F E 2 F F end 2 - .
a) Draw an AON diagram of the project, including activity durations.
b) Define the critical path, listing all critical activities in chronological order.
c) What is the project duration (in weeks)?
d) What is the slack (in weeks) associated with any and all noncritaths through the project?
A project to develop a county park has an actual cost in month 12 of $140,000, a planned cost of $190,000, and a value completed of $180,000
When calculating a local basis, the trader must take into consideration a number of variables. Briefly describe each of the variables that can influence the basis.
Assuming this aircraft will give Airbus a competitive advantage in the segment of the airliner business which supplies airplanes for long international flights, why did Boeing not respond.
What types of retailers will your company use for distributing your product? Discuss the advantages and disadvantages of using this type of retailer.
Custom Computers, Inc. assembles custom home computer systems. The fan assemblies needed are bought for $24 each and are ordered in quantities of 1500 units.
The local convenience store makes personal pan pizzas. Currently, their oven can produce 50 pizzas per hour. It has a fiixed cost of $2,000, and a variable cost of $0.25 per pizza.
Might some managers attempt to implement a particular intervention, such as TQM, without first diagnosing whether the intervention would be appropriate for their organization's problems?
A firm that produces wood shutters and bookcases has received two orders for shutters: one for 100 shutters and one for 150 shutters.
Review organization's vision also mission statements. Evaluate information also write an outline for a presentation (2-3 minutes) telling class explain why Toastmasters would or would not help you also your classmates write also deliver an effect..
Whatever your management role in an organization, one of your responsibilities is to control operating costs. In the 21st Century, all organizations face rising information technology costs.
Use different scheduling rules to achieve different objectives as listed below also provide a rationale for each of the responses: Minimize the throughput time. Minimize the lateness of all jobs.
Explain how would you structure agreements to address your concerns and capture any pros you have identified. Illustrate what governance mechanisms would you design for agreements.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd