Decisions made in this project represent system thinking

Assignment Help Operation Management
Reference no: EM132128095

Case: Life and Death of an Aircraft Development Project

Law and Callon31 described the history of a large British aerospace project in terms of two entities: the global system and the project itself. The global system comprised parties and organizations out- side the project that had a stake in the project; theproject comprised everything within the project, including all work and the organizations con- tracted to do it.

THE GLOBAL SYSTEM

The principal stakeholders in the global system were:

The Royal Air Force (RAF), which initiated the project with a request for a new supersonic air- craft with short take-off capability. The aircraft would be a “tactical strike and reconnaissance fighter” called TSR.

The Ministry of Defence (MOD), which wanted an aircraft that would best fit the nation’s cur- rent overall defense needs.

The Treasury, which wanted an inexpensive aircraft that would have market appeal for sale outside the UK, such as to the Royal Aus- tralian Air Force (RAAF).

The Royal Navy (RN), which wanted to buy a different aircraft but was under pressure by MOD to buy the TSR.

The Ministry of Supply (MOS), which wanted an aircraft that would be produced by a con- sortium of several UK airframe and engine manufacturers.

As is typical of most projects, each stakeholder in the global system conceptualized the project differently: to the RAF and MOD it would yield an aircraft for a specific mission; to the Trea- sury it would fit the defense budget and gener- ate revenue; to the RN it was a competitive threat to the aircraft they really wanted; and to the MOS it was an instrument of industrial policy. The parties had different reasons for contribut- ing resources and support: some were economic (in return for funds, an aircraft would be built); some political (in return for a demonstrated need, objections of the RN would be overruled); some technical (in return for engineering and technical effort, the aircraft would meet RAF performance requirements); and some industrial (in exchange for contracts, the aircraft industry would be con- solidated).

THE PROJECT

The Treasury would not approve project funding until the aircraft’s basic design, manufacturer, cost, and delivery date were defined. The RAF and MOD sent requests to the aircraft industry for design ideas, and selected two manufacturers: Vickers Corp. and English Electric (EE). They favored Vickers for its integration capability (com- bining aircraft, engine, armaments, and support equipment into a single weapons package), but they also liked EE for its design experience with supersonic aircraft. So they decided to contract with both companies and adopt a design that would utilize features from both. The idea was approved by all other parties in the global system, and funding for the project was released.

The project grew as Vickers and EE hired sub- contractors and expanded their teams for design, production, and management. The two companies and several other contractors merged to form a single new organization called the British Aircraft Corporation (BAC).

RELATIONSHIPS BETWEEN THE GLOBAL SYSTEM AND THE PROJECT

As the project grew, so did the problems between it and the global system. The MOS wanted central- ized control over all aspects of the project, and all transactions between the project and stakeholders in the global system. Although BAC was the prime contractor and ostensibly responsible for manag- ing the project, the MOS would not confer upon it the necessary management authority. Rather, the MOS formed a series of committees with members from the global system and gave them primary responsibility to manage the project. This led to serious problems:

The committees were allowed to make or veto important project-related decisions. They, not BAC, awarded important contracts; when the RAF wanted to change its requirements, it consulted with the committees, not with BAC.

The committees often lacked sufficient infor- mation or knowledge. Technical committees made decisions without regard to costs; cost committees made decisions without regard to technical realities. Decisions focused on par- ticular aspects of the project; seldom did they account for impacts on other parts of the proj- ect, or the project as a whole.

Distrust grew between BAC and the MOS; neither was able to effectively integrate the resources, information, and decisions flowing between parties in the project and the global system. Subcon- tractors became difficult to control. Many ignored

BAC and worked only with the MOS and RAF to get favorable treatment.

GLOBAL SYSTEM RESHAPED

Everyone knew the project was in trouble. Project costs doubled. One of the test engines exploded, and the RAF recognized it might take years to understand the cause. In addition, the RAAF announced that it would not order the TSR but was instead buying the US-built F-111. Opposition to the project grew, and in the upcoming general election the Labour Party promised that if elected it would review the project. When the Labour Party won, it immediately began an assessment of the project, which included comparing the TSR to the F-111—considered by now an alternative to the TSR. As cost overruns and schedule delays continued, the MOS slowly withdrew support. The RAF then withdrew its support, when it dis- covered that the F-111, which was already in pro- duction, would meet all of its requirements. The project was canceled.

1. Do you feel that important decisions made in this project represent “system thinking”? Explain.

Reference no: EM132128095

Questions Cloud

Create a concept map of the workings of neurons : Create a concept map of the workings of neurons and neurotransmitters from the subject of psychopharmacology. Your concept map needs to provide a holistic.
Design and costs of an organization benefits plans : The overall design and costs of an organization's benefits plans are an important part of their people strategy for attracting and retaining talented workforce
Implement corporate policy on umbrella branding : As a brand manager, you submit a recommendation to the board of directors to implement a corporate policy on umbrella branding.
Ensure swift facilitation of registration at venue : Outline the procedures you would establish to ensure swift facilitation of registration at the venue.
Decisions made in this project represent system thinking : Do you feel that important decisions made in this project represent “system thinking”? Explain.
What is the required safety stock : What is the economic order quantity? What is the required safety stock? What is the reorder point?
Main factors that contributed to cancellation of project : What are the main factors that contributed to cancellation of the project? Which of these factors would you characterize as project management?
Describe interaction between the system and its environment : Law and Callon31 described history of large British aerospace project in terms of two entities, Describe interaction between the system and its environment.
What effect did the leader actions have on team performance : Without including names, describe a situation in which you have witnessed a leader acting in an unethical manner. What effect did the leader's actions.

Reviews

Write a Review

Operation Management Questions & Answers

  Determine coordinates of the central location

A small rural county has experienced unprecedented growth over the past 6 years, and as a result, the local school district built the new 500-student North Park Elementary School.

  Hand drawn diagram receives score of zero

Draw a network diagram (use an MS Office tool—Do not hand draw. A hand drawn diagram receives a score of zero) representing the following logic: As the project starts, activities A and B can be performed concurrently. When activity A is finished, act..

  Product using the four bases for segmenting consumer markets

Describe how you can segment the potential market for the product using the four bases for segmenting consumer markets.

  How might have eric rationalized his fraudulent behavior

According to the definitions of the ethical principles previously defined in this book. How might have Eric rationalized his fraudulent behavior?

  Discusse the eight voice of the customer methods

Discuss the advantages and disadvantages of each method, as applicable to a potential Six Sigma project at your workplace.

  Motivation is a key component in employee productivity

Motivation is a key component in employee productivity and overall organizational success.

  Osha involves employers-stakeholders and trade associations

OSHA involves employers, stakeholders, and trade associations, as well as the general public, in OSHA rulemaking. Each has an opportunity to provide comments on any proposed rule, and can challenge a final rule before it goes into effect. Give an exa..

  Illustrate similarities of effective and ineffective cycles

Illustrate what are similarities of effective and ineffective cycles. Building a culture that was inclusive of diverse cultures and accommodates highly creative technical staff.

  Localization be on collection of international statistics

Many countries take a major terminology such as ICD and customize it to suit their local needs. Discuss the costs and benefits of this approach from an individual country’s point of view. What could the impact of Localization be on the collection of ..

  Boundaries between private life and work life

Do you think the boundaries between private life and work life are blurred by communication technology such as social networking? What standards or principles do you want to use the key parts of your private life separate from your colleagues?

  Describe how organizations combine incentive plans

Describe how organizations combine incentive plans in a balanced scorecard.

  About sexual harassment by one of the assistant coaches

You are an athletic director. One of your student-athletes has complained to you about sexual harassment by one of the assistant coaches in department.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd