Critical ratio of the project using earned value calculation

Assignment Help Operation Management
Reference no: EM13968969

Peak Lighting, Inc. develops stages, lighting systems, and special effects for the concert tours of major musical acts. Recently, they were approached by Bullwhip, a popular band, to develop the stage, lighting, and special effects for its upcoming tour. Currently, the project is at the end of its seventh week.

The project includes five major tasks. It starts with task A that lasts for 4 weeks, and task D that lasts for 5 weeks. Task A is to develop a sound track for the concert based on the song list the band provides it for the tour. Using the sound track, Peak's supporting staff develop a synchronized lighting and special effects show on a computer that allows them to view an animated stage with lighting and special effects as the sound track is being played. The budget cost of Task A is $400, and the actual cost at the seventh week is $500 with 100% completion. Task D, which starts at the same time with Task A, is to recruit project team members working on the stage construction, lighting and special effects later. The budget cost is $900, and the actual cost at the seventh week is $900 with 100% completion.

After finishing task A, task B and task E start in parallel. Task B lasts for 2 weeks. It involves ordering the required materials for the stage, lighting, and special effects from outside suppliers. The budget cost of task B is $300, and its actual cost at the seventh week is $350 with 100% completion. For task E, it lasts for 4 weeks. Task E is to file the sound control plan with the related government departments. It takes 4 weeks for this process. The budget cost of task E is $600, and the actual cost at the seventh week is $500 with 20% of completion.

Task C is the last task in this project, and it lasts for 5 days. It starts after the completion of both task B and task D. Task C involves constructing the stage with the lighting and special effects. Also, the lighting and special effects are tested and enhanced in this task. The budget cost of it is $750, and the actual cost at the seventh week is $400 with 10% completion.

Eric Page was recently hired as Peak's VP of Operations. All the project managers that oversee the stage and lighting projects report to Eric. He is reviewing the most recent progress report for the Bullwhip project using value earned method. Based on the above information, please help to ask the following questions from Eric.

1- What is the Planned Value of the project?

2-What is the Actual Value of the project?

3-What is the Earned Value?

4-What is the Critical Ratio of the project using earned value calculations?

5-What is the Budget at Completion for the project?

Reference no: EM13968969

Questions Cloud

Applied case study-strategic management : In this chapter, refer back to three organizational charts that are illustrated. Southwest Airline, Hersey Foods and Microsoft. For each chart, identify four shortcomings based on the guidelines presented in this chapter. (Applied Case Study-Strategi..
Documentation for management tools to utilize with system : First, provide the meaning of the acronym SMART with respect to training goals. Then, consider these four training objectives. Rewrite them as two SMART training goals. The use of the software and documentation for better management tools to utilize ..
Uses a periodic review inventory system : Fan manufacturer uses a periodic review inventory system to purchase electric motors. The review period is 4 weeks and the lead time is 2 week. Demand for electric motors is normally distributed with a mean of 800 per week and a standard deviation of..
Combinations of product-communications strategies : There are various combinations of product/communications strategies available to global marketers. Research and discuss several companies that you think exhibit successful strategies in their global communication strategies.
Critical ratio of the project using earned value calculation : Peak Lighting, Inc. develops stages, lighting systems, and special effects for the concert tours of major musical acts. Recently, they were approached by Bullwhip, a popular band, to develop the stage, lighting, and special effects for its upcoming t..
Develops a strategy for effective advertising appeals : Assume that you are the marketing director for a global project. What issues would you make sure that your art directors and copywriters take into account as your company develops a strategy for effective advertising appeals?
What are the advantages of early globalization : What are the advantages of early globalization? What are the disadvantages of early globalization?
Total cost to the garage for purchsing this item annually : A service garage uses 120 boxes of cleaning cloths per year. The boxes cost $6/each. Ordering costs are $3/order. Holding cost is 10% of the purchase price per unit per year. What is the total cost (TC) to the garage for purchsing this item annually ..
The supplier is offering a purchase price break : A service garage uses 120 boxes of cleaning cloths per year. The boxes cost $6/each. Ordering costs are $3/order and holding cost is 10% of the purchase price per box per year. The supplier is offering a purchase price break. If the garage orders 50 ..

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd