Critical path to be taken for reducing the project time

Assignment Help Operation Management
Reference no: EM13824684

Consider the project-related information below.

Activity

Preceding Activities

Time (Weeks)

Crash Time

Crash Cost per week

A

-  

3

2

$7000

B

A

4

2

$5000

C

A, B

2

1

$6000

D

A

3

2

$4000


Which one of the following options is the appropriate course of action to take if you want to reduce the project time by two weeks?

A. Crash A for two weeks because it is the only activity that reduces the time on both critical paths.

B. Crash D for two weeks because you should always crash the least costly alternative first.

C. Crash D for one week and B for one week because you should always crash the least costly alternative on each critical path first.

D. Crash B for two weeks because it is the least costly alternative on the critical path.

Additional Requirement

This question belongs to Operations Management and it discusses about on the appropriate critical path to take which can decrease the project time by two weeks.

Reference no: EM13824684

Questions Cloud

How will you deal with concept of reflection and empowerment : How will you deal with the concepts of reflection and empowerment of learners? How and why will you adapt your current teaching style to become more of a facilitator and less of an instructor?
Provide general journal entries in general journal form : provide general journal entries in general journal form for the above transactions. create a trial balance at July 31 fully taking into account the beginning balances and the general journal entries
Identify a feature-length film : Explain genre theory and, using Chapter 4 of the text as a reference, thoroughly describe the conventions and attributes of your selected genre. Identify a feature-length film that fits this genre and provide a basic summary of the movie. As you deve..
What will you do to build a sense of online community : What will you do to build a sense of online community? Develop the course competencies and learning objectives for your course at VGU.
Critical path to be taken for reducing the project time : Critical Path To Be Taken For Reducing The Project Time
How can audio and video tool replicate traditional education : How can the audio and video tools replicate traditional education? What components (if any) could not be replicated with audio and video tools?
Primary or secondary source : Primary  or   secondary  source?  Identify   each   of  the  following  ten items  as  either  a  primary source or secondary  source
Research various rapid prototypes of learning objects : Using the professional literature, research various rapid prototypes of learning objects to establish a foundation for your work. The literature may include the University online library resources and scholarly Internet sources.
Employers should be able to replace permanent : "Consider the following statement: "Employers should be able to replace permanent workers during a strike." Do you agree? Explain why."

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd