Based on the material covered in class and using the following information about the activities of a project, please identify:
1. the shortest amount of time in which the project schedule can be crashed without exceeding $7K and
2. the project critical path that resulted from crashing the project
Activity
ID
Predecessor
Estimated Optimistic Time
Estimated Most
Likely Time
Estimated Pessimistic Time
Reduction
Time
Goal
Normal Costs
Costs of Reduction
a
-
15
20
85
10
$1,000
$867
b
25
40
235
$400
$262
c
60
100
500
140
$347
d
a, b
30
125
$800
$560
e
45
50
145
$200
$120
f
220
65
$100
$53
g
d, f
130
$1,600
Notes:
This assignment explain the supply chain management process of cwc. What is the current annual supply chain cost?
Identify a number of the typical criteria used when making new location decisions
Determine the mean critical path for Brent's job search process. What is the variance of the project duration?
Please compare and contrast economic, market, and relevancy value.
Health system in Pennsylvania
Supply chain strategy
Nittany Fans of Lewistown, Pennsylvania, is a distributor of industrial fans used in plants, warehouses, and other industrial facilities.
What factors reduce the capacity of the organization to get its objectives?
What is the total annual cost
Briefly define the following two supply chain metrics: (i) inventory turnover ratio and (ii) supply chain velocity.
Explain the supply chain management concept, Differentiate between public and private sector organisations in terms of their supply chain objectives and strategies
How warehouses can add value in the supply chain
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd