Reference no: EM13127566
The marketing department at Bodnar Industries is developing a promotional campaign to introduce a new product. A listing of the various activities required, their immediate predecessors, and estimates of their times (in days) is given below.
a) Draw the precedence diagram for this network.
b) Find the means and standard deviations of the activity times.
c) Find the expected early and late start and finish times.
d) Identify the critical path, the expected length of the critical path and the expected slack times for each activity.
e) What is the probability that the project will be completed in less than 60 days? More than 65 days?
f) How many days should the marketing manager allow for completion of the project if he wants to be 99% sure that the project will be completed within this allowed time?
Activity Description Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time
A Rough brochure layout -- 2 3 5
B Review brochure A 6 8 10
C Final brochure layout B 4 6 8
D Final brochure artwork C 5 7 11
E Design display -- 12 15 20
F Rough display artwork E 2 3 4
G Review display E 6 8 10
H Revise display G 2 3 4
I Final display artwork F,H 1 2 4
J Make display plates I 18 23 26
K Make brochure plates D,I 10 13 16
L Make and ship displays J 7 10 14
M Print and ship brochures K 6 8 10
What are the different ways to account for write-offs
: Everyone wants to get paid for their work. However, sometimes companies don't receive timely payments from customers and must write-off amounts. What are the different ways to account for write-offs?
|
Differences between ifrs and gaap
: Discuss at least three significant differences between IFRS and GAAP.
|
What are some internal control procedures over cash
: Internal controls help ensure the safeguarding of the company's assets. One of the major areas that need to be safeguarded is cash. What are some internal control procedures over cash?
|
Explain ph of acetylsalicylic acid
: PH of Acetylsalicylic Acid, The active ingredient in aspirin is acetylsalicylic acid (HC9H7O4), a monoprotic acid with a Ka = 3.3x10-4
|
Critical path-precedence diagrams start and finish dates
: The marketing department at Bodnar Industries is developing a promotional campaign to introduce a new product. A listing of the various activities required, their immediate predecessors, and estimates of their times (in days) is given below.
|
How many grams of sucrose must be added
: How many grams of sucrose must be added to 552g of water to give a solution with a vapor pressure 2.o mmHg less than that of pure water at 20 celsius?
|
What was the amount of the gain or loss
: On March 31, 2009, Hanson Corporation sold $7,000,000 of its 8%, 10-year bonds for $6,730,500 including accrued interest. The bonds were dated January 1, 2009.
|
Create linear model to estimate number of points score
: Create a linear model to estimate the number of points students will score on the next exam from the number of hours the student studies.
|
How many moles of ions are released
: How many moles of ions are released when 0.27 mol of cobalt(II) chloride, CoCl2, is dissolved in water?
|