Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
A project has the following activities, precedence relationships, and time estimates in days:
Activity Predecessor Optimistic Most likely PessimisticActivities Time Time TimeA -- 6 7 8B A 4 4 4C A 5 6 8D B 8 10 10E B 7 10 15F C 9 9 13G C 7 7 7H D 4 6 8I E, F 6 9 11J G 8 9 10K H, I, J 3 5 6
Compute the earliest start, earliest finish, latest start, latest finish, and slack for each activity
What are the critical path and duration of the project?
What is the probability that the project will take longer than 38 days?
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd