Critical path activities problem

Assignment Help Other Subject
Reference no: EM13765763

The following data were obtained from an in-house MIS project:

Activity Duration Predecessors

Activity Duration Predecessors 

A        3 Days   ---          

B        6 Days   ---          

C        3 Days   B            

D        2 Days   A            

E        3 Days   C,D          

F        2 Days   A            

G        4 Days   F            

H        7 Days   B

I        2 Days   C,D

J        4 Days   H,I

K        8 Days   H,I

L        5 Days   E,G,J

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity C? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity E? Show your calculations.

f) What is the slack or float for Activity J? Show your calculations.

Problem 2.

A project to remodel an office area has the following activities.

Activity

Duration

Predecessors

A

3 months

---

B

2 months

---

C

3 months

---

D

4 months

A, B

E

3 months

A

F

2 months

B, C

G

2 months

F

H

1 month

G

I

4 months

D, E, F

J

5 months

H

a) What are the critical path activities? (5 points)

b) What is the project's scheduled completion time? (5 points)

c) What is the slack or float for Activity B? Show your calculations. (1 point)

d) What is the slack or float for Activity D? Show your calculations. (1 point)

e) What is the slack or float for Activity F? Show your calculations. (1 point)

f) What is the slack or float for Activity I? Show your calculations. (1 point)

Problem 3

Information from a room addition project:

 

 

Duration

Predecessors

 

A

2 wks

 

 

B

3 wks

 

 

C

5 wks

 

 

D

7 wks

   A

 

E

3 wks

    B

 

F

2 wks

    C

 

G

4 wks

     F

 

H

1 wk

      A

 

I

8 wks

    D, E, G

 

J

5 wks

             F

 

K

2 wks

  D, E, G, H

 

 

 

 

 

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity A? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations

e) What is the slack or float for Activity H? Show your calculations.

f) What is the slack or float for Activity K? Show your calculations

Problem 4

InformAtion from a site renovation project:

Task     Duration            Predecessors

A          2 wks               _

B          5 WKS             A

C          3 WKS             B

D          15 WKS           B

E          8 WKS             C

F          10 WKS           C

G         2 WKS             D

H          6 WKS             E, F, G

I           5 WKS             H

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity C? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity I? Show your calculations.

f) What is the slack or float for Activity K? Show your calculations.

Reference no: EM13765763

Questions Cloud

Executive producer for epic productions : Suppose Ben decides to reorder 35 mm film when there are 86 rolls left in stock. How much safety stock is implied by this reorder point?
What is a lan : A metropolitan area network, or MAN, is a network that's smaller than a typical WAN but larger than a LAN. Typically, a MAN connects two or more LANs within a same city but are far enough apart that the networks can't be connected using a simple c..
Lockes expansive vision of toleration useful and ethical : Do you find Locke's expansive vision of toleration useful and ethical? Why or why not? and Do you believe that it is ever acceptable for individuals' religious beliefs to affect the administration of law? Why or why not
Security features linux web servers : Describe built-in security features existing in the Linux Web servers
Critical path activities problem : What is the slack or float for Activity C? Show your calculations.
Summarize and comment on the facts in the eeoc claim : Summarize and comment on the facts in the EEOC claim and Explain the values of the company and its policy on race and gender discrimination
Explain leadership and ethical behaviors : Explain leadership and ethical behaviors. Propose two ethical concerns that management may need to address. Create the context in which such concerns may or may not be ethical in nature.
Measure client progress and compliance with court orders : How can a behavior plan be used to measure client progress and compliance with court orders
Database environment : Analyze the database environmen

Reviews

Write a Review

Other Subject Questions & Answers

  Cross-cultural opportunities and conflicts in canada

Short Paper on Cross-cultural Opportunities and Conflicts in Canada.

  Sociology theory questions

Sociology are very fundamental in nature. Role strain and role constraint speak about the duties and responsibilities of the roles of people in society or in a group. A short theory about Darwin and Moths is also answered.

  A book review on unfaithful angels

This review will help the reader understand the social work profession through different concepts giving the glimpse of why the social work profession might have drifted away from its original purpose of serving the poor.

  Disorder paper: schizophrenia

Schizophrenia does not really have just one single cause. It is a possibility that this disorder could be inherited but not all doctors are sure.

  Individual assignment: two models handout and rubric

Individual Assignment : Two Models Handout and Rubric,    This paper will allow you to understand and evaluate two vastly different organizational models and to effectively communicate their differences.

  Developing strategic intent for toyota

The following report includes the description about the organization, its strategies, industry analysis in which it operates and its position in the industry.

  Gasoline powered passenger vehicles

In this study, we examine how gasoline price volatility and income of the consumers impacts consumer's demand for gasoline.

  An aspect of poverty in canada

Economics thesis undergrad 4th year paper to write. it should be about 22 pages in length, literature review, economic analysis and then data or cost benefit analysis.

  Ngn customer satisfaction qos indicator for 3g services

The paper aims to highlight the global trends in countries and regions where 3G has already been introduced and propose an implementation plan to the telecom operators of developing countries.

  Prepare a power point presentation

Prepare the power point presentation for the case: Santa Fe Independent School District

  Information literacy is important in this environment

Information literacy is critically important in this contemporary environment

  Associative property of multiplication

Write a definition for associative property of multiplication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd