Case Study: The Problems of Multitasking

An eastern U.S. financial services company found itself way behind schedule and over budget on an important strategic program. Both the budget and schedule baselines had begun slipping almost from the beginning, and as the project progressed, the lags became severe enough to require the company to call in expert help in the form of a project management consulting firm. After investigating the organization’s operations, the consulting firm determined that the primary source of problems both with this project in particular and the company’s project management practices in general was a serious failure to accurately forecast resource requirements. In the words of one of the consultants, “Not enough full-time [human] resources had been dedicated to the program.”

The biggest problem was the fact that too many of the project team members were working on two or more projects simultaneously—a clear example of multitasking. Unfortunately, the program’s leaders developed their ambitious schedule without reflecting on the availability of resources to support the project milestones. With their excessive outside responsibilities, no one was willing to take direct ownership of their work on the program, people were juggling assignments, and everyone was getting farther behind in all the work. Again, in the words of the consultant, “Project issues would come up and there would be nobody there to handle them [in a timely fashion].” Those little issues, left unattended, eventually grew to become big problems. The schedule continued to lag, and employee morale began to bottom out.

Following their recognition of the problem, the first step made by the consultants was to get top management to renegotiate the work assignments with the project team. First, the core team members were freed from other responsibilities so they could devote their full-time attention to the program. Then, other support members of the project were released from multitasking duties and assigned to the project on a full-time or near full-time basis as well. The result, coupled with other suggested changes by the consultants, was to finally match up the project’s schedule and activity duration estimates with a realistic understanding of resources needs and availability. In short, the program was put back on track because it was finally resource-leveled, particularly through creating full-time work assignments for the project team that accurately reflected the need to link resource management with scheduling.

Briefly summarize the situation in the case.

Explain how multitasking can create confusion in project team personnel availability.

How does multitasking or assigning employees to participate in several projects contaminate activity duration?

Why does multitasking “decouple” activity duration estimates from the project schedule?

“In modern organizations, it is impossible to eliminate multitasking for the average employee.” Do you agree or disagree? Explain your position.

Reference no: EM132126830

Questions Cloud

Determine critical path by doing forward and backwards pass : Critical Path. determine the critical path by doing a forward and backwards pass. Then identify the critical path and the longest duration.
Recover for environmental damage under the common law : In suing to recover for environmental damage under the common law, plaintiffs generally have had causes of action in:
Track projects to prevent surprises such as overruns-delayes : Determine a system to monitor and track projects to prevent surprises such as overruns and delays.
CERCLA is an act that and To establish private nuisance : NEPA requires that the EIS contain. To establish a private nuisance, a plaintiff. CERCLA is an act that:
Create confusion in project team personnel availability : Explain how multitasking can create confusion in project team personnel availability.
Control the human side of project management better : As the project manager, what steps would you take to control the "human" side of project management better?
Cassandra have the right to disaffirm financing agreement : According to the majority rule, would Cassandra have the right to disaffirm the financing agreement?
Briefly summarize the project sponsor and stakeholder : Briefly summarize the project sponsor and stakeholder for upgrading employee desktop computers and software for three regional offices,
Draw product structure tree with low level coding : Draw the product structure tree with low level coding. Draw the corresponding time - phased diagram showing lead times to scale.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd