Create a work breakdown structure

Assignment Help Project Management
Reference no: EM132944386

BSBPMG531 Manage Project Time

Assessment Task

Task summary
This assessment task requires you to create a Work Breakdown Structure, a Project Management plan, and a Project Schedule in consultation with your team and to review documents based on team feedback.

Required
• Access to textbooks/other learning materials
• Computer with Microsoft Office and internet access
• Draft Project Management Plan Template
• Draft Project Schedule Template
• Conference Program
• Place for a meeting
• Roleplay participants

Assessment Task 2 Instructions

Carefully read the following:

Manager Networks is an organisation that provides networking events for business people across Australia. The company runs regular networking events but has now decided to start an annual conference event focussing on an area of business considered to be of key importance. It is hoped that the conference will provide information on cutting edge leadership topics that focus on leadership skills, knowledge and trends.
It should also promote Management Networks, as well as providing professional development for its clients.

As the Administration Manager for Manager Networks, you have been asked by the CEO to develop and implement a project schedule for the conference. Although the CEO has ultimate responsibility for the conference, you will be responsible for the ongoing development of the congress in cooperation with several other staff members, who will use their expertise in different areas to support your project management.
Donna Chisholm, who is the co-ordinator of the Manager Networks' trainers, will help with contacting and lining up the speakers. She has already drafted a Conference Program, which can be used until the speakers have been finalised.
Dan Streep, the Administration Assistant has had experience with the ground level work required for a conference, and he will help to determine and prepare the venue.
Edith Partridge, the Chief Financial Officer will be in control of the finances of the congress.
Erin O'Donnell, the Manager Networks Marketing Manager, will co-ordinate the marketing material.

The conference will be conducted on 04 October 2020. It will be a one-day event, from 9 am to 4 pm. For the purposes of this assessment task, assume that the date of the project team meeting is 09 April 2020.

The conference style will be formal, with a balance of conference elements to ensure that outcomes are achieved.

Participant target group is managers in all industries. This group will be targeted by email using the Manager Networks data base and publicised through social media such as LinkedIn.

Conference facilities require a centrally located venue that has a conference room that can accommodate up to 150 people. Invited speakers will want to be accommodated nearby, so there will need to be an appropriate hotel in the vicinity.
The venue will also need to be able to provide onsite catering for the meeting attendees.

Budget: projected attendee numbers will be 150 people, and the suggested conference price for participants is $500 plus GST.
Speakers are to receive $400 each for their participation.

Complete the following activities:

1. Write a Work Breakdown Structure (WBS) for the conference.
Develop a WBS with sufficient detail to enable effective planning and control of the project.
The WBS may be in the form of a diagram or a list of activities, but it must contain sufficient detail to enable a Project Schedule to be developed from it.

2. Write a draft Project Management Plan (PMP).
Review the case study information, and research conference project management plans in the internet.
It is not possible for the information you are given on the case study to be exhaustive, so feel free to embellish you plan with tips from projects that you have participated in the past, or examples from the internet. The objective is that you demonstrate that you are capable of logically thinking through the issues involved in the case study situation.

Your PMP must include, as a minimum, the following:
• Project scope
• Milestones and mechanisms to measure, record and report progress of activities
• Roles and responsibilities
• Project stakeholders
• Project communication
• Change management
• Cost management
• Risk management
• Issue management
• Management plan approval process.

Use Project Plan Template to guide your work.
Your draft project management plan should be between 2 and 3 pages.
Print out a copy of this document to take to the project team meeting with you.

3. Write a draft Project Schedule (PS)
Use MS Excel to create a Project Schedule Gantt Chart that covers all of the tasks in your WBS.
For each task, estimate its duration and effort, then work out the sequencing and the dependencies between tasks.
Keep in mind that this will be a draft version only, and the baseline PS can only be established after you have incorporated the input from the rest of the project team.

Use Project Schedule Template to guide your work.
Print out a copy of this document to take to the project team meeting with you.

4. Send an email to the CEO (your assessor).
The text of the email should be in grammatically correct English, written in an appropriate (polite, business-like) style.
It should introduce and summarise the contents of the attachments and ask for details of your meeting with the project team.

Attach the following to the email:
• Work Breakdown Structure
• Draft Project Management Plan
• Draft Project Schedule

5. Meet with the project team.
The meeting's objective is to establish an agreed schedule baseline using contributions from your team members.
Begin the meeting by summarising the information in your Project Management Plan. Encourage discussion about the communication frequency and methods, and change management. You can return to these points at the end of the meeting if no agreement has been established yet.

Then ask each team member for their estimates of each task's duration and effort, sequencing and the dependencies.
Also ask each team member to estimate the risks involved with them completing their tasks on time, and what provisions should be made to allow for this. This may involve finding alternative activities, or sequencing changes. Encourage all participants to join in the discussions about resource requirements, costs and risks.

Review also the project's milestones from your PMP with the team and establish agreement on them.

Take notes at the meeting, as you will be required to adjust your documents to include the input from the other team members.

During the meeting, you will be required to demonstrate effective communication skills including:
• Speaking clearly and concisely
• Using non-verbal communication to assist with understanding
• Asking questions to identify required information
• Responding to questions as required
• Using active listening techniques to confirm understanding

6. Review your Project Management Plan
Include the input from the other project team members to revise the plan, establishing baselines for each item.

7. Send an email to all project team members (your assessor).
The text of the email should be in grammatically correct English, written in an appropriate (polite, business-like) style.
It should refer to the recent meeting, then introduce and summarise the contents of the attachments.
It should seek their feedback and approval of the documents, giving them a week to respond.

Attachment:- Manage Project Time.rar

Reference no: EM132944386

Questions Cloud

How much will connie employer remit to the us treasury : Assume a FICA for Social Security rate of 6.2%, How much will Connie's employer remit to the U.S. Treasury for federal taxes for only this one paycheck?
What is the effect of february transaction on solo : What is the effect of the February 13 transaction on Solo's financial statements? Solo Inc. reacquires 50,000 shares of its $1 par value common stock.
Should cash and carry be done with such bond today : Suppose the return for cash and carry is 1.8% per year. Should cash and carry be done with such bond today? Explain briefly why or why not.
How can ceta benefits canux : Canux hockey inc. ("canux") is a Canadian manufacturer of high-end hockey equipment based in Hamilton, Ontario. Established in 2017, Canux is still a relatively
Create a work breakdown structure : Create a Work Breakdown Structure, a Project Management plan, and a Project Schedule in consultation with your team and to review documents based on team
Discuss relationship between external and internal auditors : Discuss relationship between external auditors, internal auditors and good governance practices. (review an articles to support the answer)
What would be the net A-R on the Balance Sheet : Assume you estimate 8% of Accounts Receivable to eventually become Bad Debts. What would be the net A/R on the Balance Sheet
Prepare journal entries for transactions for sampson corp : Prepare journal entries for the above transactions. The current market price of the common shares is $15 per share. Sampson Corporation has 100,000 common share
Case study models a mobile phone company : Case study models a mobile phone company. The company has a number of phones that are sold by staff to various clients

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd