Create a work breakdown structure

Assignment Help Project Management
Reference no: EM132147787

You are recently assigned to manage an effort to upgrade about 200 desktops in your company to Windows 10. The project has 4 team members reporting directly to you and is estimated to last about 3 months. Per your company's project management standards, you are required to conduct the following activities.

1. Create a Work Breakdown Structure (WBS) that lists all tasks required for this project. Specifically,
- Construct the WBS in a tabular form
- Provide four levels of detail
- Describe best practices in general for constructing a good WBS (Note: additional research on this topic beyond the textbook is strongly encouraged)
- Articulate what best practices have been utilized in this assignment and what have not due to the constraints of this assignment

2. Develop a WBS dictionary to briefly describe each work package
3. Estimate duration for each work package, sequence activities at the work package level, and construct a Gantt Chart for this project

The assignment should be submitted according to the following requirements. Any submission that does not follow these requirements will be discounted.

- Due Date and Time: Sunday, Oct 28th, 11:00 PM
- Format: Single-spaced; 12 Point Times New Roman font; One inch margins
- Number of Pages: Not to exceed 5 pages. The 5-page limit includes supporting materials such as references, figures, or charts
- Student Name: Your name should be listed on the top-right corner of the first page
- Citations: Clear citations should be provided, in APA format, when applicable for all work that is not your own

Verified Expert

The solution file is prepared in ms project to create a work break down structure for upgrade 200 desktop to windows 10 in the tabular form. The work break down structure has four levels with details of sub task and discussed best practices in general for constructing a good WBS. Also discusses about Articulate what best practices have been utilized in this assignment and what have not due to the constraints of this assignment. The solution has all screen shots of work break down structure and gantt chart and references are included as per APA format.

Reference no: EM132147787

Questions Cloud

Overlook the on-boarding of new employees : Why do organizations so frequently overlook the on-boarding of new employees?
What is intrapreneurship : What is intrapreneurship? and How can it be enabled in an organization?
How is continuous improvement related to innovation : Total quality management involves a continuous improvement approach. 1. How is continuous improvement related to innovation?
Scoreboard approach has gained popularity in recent years : The balanced scoreboard approach has gained popularity in recent years. What is this approach and how does it integrate strategic and operational control?
Create a work breakdown structure : IS 669 Project Management Operations - Create a Work Breakdown Structure (WBS) that lists all tasks required for this project
What are the pros and cons of each : 1. Why is strategic control important in the strategy implementation process?
Develop a process map about the prescription filling process : Develop a process map about the prescription filling process for HMO's pharmacy, in which you specify the key problems .
What kind of challenges and opportunities : What kind of challenges and opportunities is Four Seasons Hotels facing in terms of processes and lateral capabilities?
Organizational and environmental pressures : What are the similarities of organizational and environmental pressures?

Reviews

urv2147787

11/29/2018 1:42:21 AM

Amazing job dear experts and thanks a lot to expertsmind to avail me such expert who followed every units instruction perfectly. I really amazed with the grades I received with your help. I am really thankful. I have passed the class with A grade. You are true lifesaver.

len2147787

10/23/2018 3:55:15 AM

The assignment should be submitted according to the following requirements. Any submission that does not follow these requirements will be discounted. Due Date and Time: Sunday, 28th, 11:00 PM Format: Single-spaced; 12 Point Times New Roman font; One inch margins Number of Pages: Not to exceed 5 pages. The 5-page limit includes supporting materials such as references, figures, or charts Student Name: Your name should be listed on the top-right corner of the first page Citations: Clear citations should be provided, in APA format, when applicable for all work that is not your own

len2147787

10/23/2018 3:54:58 AM

A good WBS needs to incorporate both PM concepts and realistic tasks to complete the project. First, this is a project manager class. Students from this class are encouraged to think more like project managers than engineers. Example of PM concepts that would be covered in the WBS include project integration, scope definition, monitoring, etc. Next, please include realistic tasks that will lead to the completion of this specific project, rather than general tasks that could apply to any project. A typical question one would ask after finishing a draft WBS is "If one were to transfer the WBS to another project manager, would he or she be able to finish the project?"

Write a Review

Project Management Questions & Answers

  Expand your analysis to address of business model

Expand your analysis to address only two of the given business model perspectives:business models as value proposition, business models as a set

  A project can be closed for several reasons.

A project can be closed for several reasons.

  Understand the genesis of project management

Assignments for CIS8010 Understand the genesis of project management and its importance to improving the success of information technology projects - understand the triple constraints of project management: scope, time, cost

  The studies and techniques developed by taylor

The studies and techniques developed by Taylor and the Gilbreths simply enabled employers to get more work out of their employees

  Determine the expected duration of the entire project

Determine the expected duration of the entire project, showing all of your work or reasoning. Determine the slack for project Activity E, showing all of your work or reasoning.

  Designing a quality power trim system

Design a quality power trim system. Design and build the equipment to produce such a system efficiently.

  Describe pareto diagrams and their use in project management

Describe the different quality activities involved in this project and each of their outcomes. Describe Pareto diagrams and their use in project management.

  Review the articles regarding the tacoma narrows bridge

Review the Articles and Videos regarding the Tacoma Narrows Bridge (Galloping Gertie) found in this week''s Supplemental Reading and how it failed the first time around. In your opinion, why did this project fail?

  Rsk management is a critical aspect of project management

risk management is a critical aspect of project management. the supply chain decisions that are made have risk

  Importance of enabling skills in project management

Explain in scholarly detail and relate your thoughts on the term "enabling skills" and give a relationship to importance of project management.

  Which genre had greater variation in total gross income

Which genre had greater variation in total gross income? Explain your reasoning behind your conclusion. Why is this important to know from business standpoint?

  What can acme corporation do about this

Acme Corporation has recently given out a nine-month contract to a construction subcontractor. What can Acme Corporation do about this? Explain how you would resolve this issue

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd