Create a work breakdown structure

Assignment Help Other Subject
Reference no: EM131453937

OPTION 1

You are the Project Manager for the refurbishment of an 8-storey tower block of offices at an educational institution (see photo of external elevation). The project scope comprises three major components:
A. Section A: Upgrading (i.e. replacement) of the two lifts.

B. Section B: Refurbishment of staff offices to the existing floors (new decoration, lighting, ventilation systems, fixtures and fittings, furniture).
C. Section C: Replacement of all the windows with double glazing system.

Each floor comprises 15 offices for academic and administrative staff (see floor plan). Typically staff currently have their own office (i.e. 1 member of staff to each office). The floor plan for each floor is similar.

Work is to be scheduled so as to minimise disruption to staff working in the offices as far as possible. The scope of the works includes decanting of staff from their offices into refurbished offices as the works progress. Alternative space in limited. Staff can share an office if necessary (2 staff to an office) during the refurbishment works.

674_Figure.jpg

Figure 2: Typical Floor Plan

Section B works may overlap with Section A, but completion of Section B is not necessary until approximately 3 months after Section A. Section C may be undertaken concurrently with Sections A and B as appropriate.

Ignore the ground floor / entrance area (assume these areas have previously been refurbished). Access can be gained via the rear of the building.

The budget is $10m (split between the 3 Parts).

Required:-

1. Create a Work Breakdown Structure (WBS) for the project. As a guide the WBS should contain between 60 and 75 activities. Do not exceed 80 task-level activities. Present the WBS in a hierarchical structure diagram.

2. Create a schedule for the project. Determine the overall duration and when activities and events are planned to happen. The schedule is to include activities and their logical dependencies, with estimations of activity durations. Use the summary tasks, tasks and sub-tasks from the WBS for your schedule activities. Use Critical Path Scheduling techniques for the preparation of your project schedule. The start date for the project is the first working Monday after your Birthday this year. Adopt NZ industry standard holidays (Christmas, Easter, ANZAC day etc). Present your schedule as a Gantt Chart, using suitable scales. Use MS Project planning software and upload a soft copy of your MS Project file onto Canvas. Clearly identify the critical path(s).

3. When construction of Part A is 50% complete according to the original time line (i.e. half the original time estimated for completion), unexpected design errors result in the need for strengthening of the existing structure. The cost of the re-work is estimated to be $1.5m and the associated delay to completion of Part A is estimated at 6 weeks. In addition, progress on site has been slow, and you are running 2 weeks behind on your planned programme. As a result the client has asked you, (the Project Manager), to attend a crisis meeting. Using the elements from 1-2 above, along with any other project control measures you are familiar with, develop a progress report for the client. Indicate the likely delays and revised finish date for the project, based on critical path analysis.

Develop your recommendations for:

a. Options on how to achieve the original planned completion dates for all 3 Parts. Clearly indicate the implications for accelerating the works.

b. Options on how to achieve the original project budget. Clearly indicate the implications upon scope and upon planned completion dates.

The client is open to suggestions on changes of scope, time and cost, but not prepared to relax the quality aspects of the project. Note that you should use MS Project to help answer this part of the assignment and use the outputs from the software to demonstrate implications and options, however a soft copy of your MS Project file is NOT required.

4. Comment on the benefits and limitations of critical path scheduling techniques. Identify and describe an alternative scheduling technique for management of time that might address some of the limitations of the critical path approach. Guide 1000-1500 words.

OPTION 2

Identify a major project of your own choice. This may be from any engineering or business disciple. Prepare a project scenario of your own type of project (e.g. software development, capital equipment development, etc), which your are sufficiently comfortable with. Once again, you are the Project Manager for the identified project scenario. Identify three major components for the project scope (similar to the split between Part A, B and C for Option 1).

Required:-

1. Create a Work Breakdown Structure (WBS) for the project. As a guide the WBS should contain between 60 and 75 activities. Do not exceed 80 task-level activities.

2. Create a schedule for the project. Determine the overall duration and when activities and events are planned to happen. The schedule is to include activities and their logical dependencies, with estimations of activity durations. Use the summary tasks, tasks and sub-tasks from the WBS for your schedule activities. Use Critical Path Scheduling techniques for the preparation of your project schedule. The start date for the project is the first working Monday after your Birthday this year. Adopt NZ industry standard holidays (Christmas, Easter, ANZAC day etc). Present your schedule as a Gantt Chart, using suitable scales. Use MS Project planning software and upload a soft copy of your MS Project file onto Canvas. Clearly identify the critical path(s). (20 marks)

3. When implementation is 50% complete according to the original time line (i.e. half the original time estimated for completion), unexpected risks result in the need for re-work to one of the major components of the project. The cost of the re-work is estimated to be 10% of the total project budget and the associated delay to the project completion date is estimated at 10% of the project duration. In addition, progress on the project has been slow, and you are running behind on your planned programme. As a result the client has asked you, (the Project Manager), to attend a crisis meeting. Using the elements from 1- 2 above, along with any other project control measures you are familiar with, develop a progress report the client. Indicate the likely delays and revised finish date for the project based on critical path analysis. Develop your recommendations for:

a. Options on how to achieve the original planned completion dates for all 3 Parts. Clearly indicate the implications for accelerating parts of the works with associated "crash costs".

b. Options on how to achieve the original total budget. Clearly indicate the implications upon scope and upon planned completion dates.

The client is open to suggestions on changes of scope, time and cost, but not prepared to relax the quality aspects of the project. Note that you should use MS Project to help answer this part of the assignment and use the outputs from the software to demonstrate implications and options, however a soft copy of your MS Project file is NOT required. (10 marks)

4. Comment on the benefits and limitations of critical path scheduling techniques. Identify and describe an alternative scheduling technique for management of time that might address some of the limitations of the critical path approach. Guide 1000-1500 words.

Verified Expert

The assignment consists of project management study of the 8-storey building for their refurbishment process. under refurbishment process, the basic concentration is done changes on lighting, flooring, painting and other processes. under this assignment, the basic study is done for managing the refurbishment process with an effective way using management tools such as CPM and Gantt chart.

Reference no: EM131453937

Questions Cloud

Determine the process capability : A turning process is in statistical control and the output is normally distributed, producing parts with a mean diameter = 30.020 mm and a standard deviation.
What keys to success did the leader describe : What keys to success did the leader describe? What are your thoughts on the leader's response? How you could implement their thinking in your own career?
Which topics should be expanded in their duration why : Which topics should be expanded in their duration? Why? Which topics should be refreshed and included in continuing education of experienced officers? Why?
Explain police discretion to the citizens group : How would you fully explain police discretion to the citizens' group? How do you explain the fostering of good ethical decision making and discretion
Create a work breakdown structure : CIVIL 703 - PROJECT MANAGEMENT - Create a Work Breakdown Structure (WBS) for the project. As a guide the WBS should contain between 60 and 75 activities. Do not exceed 80 task-level activities.
Property of consumer preferences : Harry's utility function is U = 5X + 15Y. Which property of consumer preferences does Harry's utility function violate? Explain your answer.
Finf the technical pattern of resistance area : Run a few of the lognormal price path simulations. Examine the price pattern for trends. Find one or more of the following technical patterns.
Low barriers to entry and one that has high barriers : Identify an industry that has low barriers to entry and one that has high barriers. Explain how the difference in entry barriers influences competitive behavior
What type of management style you perceive they used : Describe your best boss and write a short analysis on what type of management style you perceive they used. Share and compare with classmates.

Reviews

len1453937

4/7/2017 3:19:24 AM

Please look into the attached assignment. I want one of this done before 12th EOD of this month. please review and let me know the price to do the same. This assignment is worth 40% of the Project Management 1 Paper (i.e. 40 marks). • Submit all your answer in one document as a hard copy at the student services stall. In addition upload onto Canvas a soft copy of your submission document in PDF format, together with a soft copy of your MSProject File for Question 2. • This coursework is an individual piece of work and students must NOT work in collusion or in teams. Standard University guidelines for plagiarism and collusion apply. • This assignment has been developed in order to meet the needs of the various disciplines of students undertaking the course. There are two distinct options for students –COMPLETE ONE OPTION ONLY.

Write a Review

Other Subject Questions & Answers

  Discuss the methods of support or treatment

Describe how sex/sexuality and power are used as it relates to your topic and the theories behind it. Discuss the methods of support or treatment as it relates to your topic

  What are some of the philosophies that influenced latin

1. what are some of the philosophies that influenced latin america? in what way did they impact the cultures of latin

  Compare gilgamesh and odysseus as to their heroic qualities

Compare Gilgamesh and Odysseus as to their heroic qualities, noting similarities and differences, using specific examples from the epics.

  Putting pressure on you to get a project started

Imagine your manager is putting pressure on you to get a project started and feels the project charter can be developed as the project gets underway. Develop a brief response to his or her request.

  Prepare a union position on the issue of future health care

Assuming that these issues will be major ones in the upcoming negotiations, prepare either a union or a management position on the issue of future health care benefits at GMFC.

  Would that behaviorist use a different approach with a child

Describe how that behaviorist would teach an adult a new skill. Be specific; what is the skill? What steps would the behaviorist use? Would that behaviorist use a different approach with a child?

  Find elements concerning characteristics of communication

Introduce the setting, plot, and the main characters of the movie? Find three elements concerning the characteristics of communication from your text and course notes and apply them to the movie, make sure you cite your source(s) using APA.

  Assure of job gaining

Write an attractive (assure of  job gaining) experience letter on one year office experience of computer maintenance, networking etc. keep in mind the format of experience letter.

  Calculate the monthly average cost of equity capital

Estimate the systematic risk measured in terms of the beta coefficient obtained using monthly return data for the last 5 years - Calculate the monthly average cost of equity capital for the firm using the standard Capital Asset Pricing Model

  Program to track hourly employee arrival and departure times

A company hires you to write a program to track hourly employee arrival and departure times from work. In essence, you are tasked to make an online time clock. The time clock shall keep a history of an employee’s hours for a two-week pay period.  The..

  Do the civil damages include the possibility of prison

"One of the firm's lawyers has asked you to conduct research on behalf of a client. The client is the victim of a sexual assault and did not report the event to the police. The client wants to know if she can sue the offender, and if so, for what can..

  This question has five parts one of the cornerstones of

this question has five parts. one of the cornerstones of freudian theory is the concept of the unconscious not to be

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd