Create a work breakdown structure

Assignment Help Other Subject
Reference no: EM131453937

OPTION 1

You are the Project Manager for the refurbishment of an 8-storey tower block of offices at an educational institution (see photo of external elevation). The project scope comprises three major components:
A. Section A: Upgrading (i.e. replacement) of the two lifts.

B. Section B: Refurbishment of staff offices to the existing floors (new decoration, lighting, ventilation systems, fixtures and fittings, furniture).
C. Section C: Replacement of all the windows with double glazing system.

Each floor comprises 15 offices for academic and administrative staff (see floor plan). Typically staff currently have their own office (i.e. 1 member of staff to each office). The floor plan for each floor is similar.

Work is to be scheduled so as to minimise disruption to staff working in the offices as far as possible. The scope of the works includes decanting of staff from their offices into refurbished offices as the works progress. Alternative space in limited. Staff can share an office if necessary (2 staff to an office) during the refurbishment works.

674_Figure.jpg

Figure 2: Typical Floor Plan

Section B works may overlap with Section A, but completion of Section B is not necessary until approximately 3 months after Section A. Section C may be undertaken concurrently with Sections A and B as appropriate.

Ignore the ground floor / entrance area (assume these areas have previously been refurbished). Access can be gained via the rear of the building.

The budget is $10m (split between the 3 Parts).

Required:-

1. Create a Work Breakdown Structure (WBS) for the project. As a guide the WBS should contain between 60 and 75 activities. Do not exceed 80 task-level activities. Present the WBS in a hierarchical structure diagram.

2. Create a schedule for the project. Determine the overall duration and when activities and events are planned to happen. The schedule is to include activities and their logical dependencies, with estimations of activity durations. Use the summary tasks, tasks and sub-tasks from the WBS for your schedule activities. Use Critical Path Scheduling techniques for the preparation of your project schedule. The start date for the project is the first working Monday after your Birthday this year. Adopt NZ industry standard holidays (Christmas, Easter, ANZAC day etc). Present your schedule as a Gantt Chart, using suitable scales. Use MS Project planning software and upload a soft copy of your MS Project file onto Canvas. Clearly identify the critical path(s).

3. When construction of Part A is 50% complete according to the original time line (i.e. half the original time estimated for completion), unexpected design errors result in the need for strengthening of the existing structure. The cost of the re-work is estimated to be $1.5m and the associated delay to completion of Part A is estimated at 6 weeks. In addition, progress on site has been slow, and you are running 2 weeks behind on your planned programme. As a result the client has asked you, (the Project Manager), to attend a crisis meeting. Using the elements from 1-2 above, along with any other project control measures you are familiar with, develop a progress report for the client. Indicate the likely delays and revised finish date for the project, based on critical path analysis.

Develop your recommendations for:

a. Options on how to achieve the original planned completion dates for all 3 Parts. Clearly indicate the implications for accelerating the works.

b. Options on how to achieve the original project budget. Clearly indicate the implications upon scope and upon planned completion dates.

The client is open to suggestions on changes of scope, time and cost, but not prepared to relax the quality aspects of the project. Note that you should use MS Project to help answer this part of the assignment and use the outputs from the software to demonstrate implications and options, however a soft copy of your MS Project file is NOT required.

4. Comment on the benefits and limitations of critical path scheduling techniques. Identify and describe an alternative scheduling technique for management of time that might address some of the limitations of the critical path approach. Guide 1000-1500 words.

OPTION 2

Identify a major project of your own choice. This may be from any engineering or business disciple. Prepare a project scenario of your own type of project (e.g. software development, capital equipment development, etc), which your are sufficiently comfortable with. Once again, you are the Project Manager for the identified project scenario. Identify three major components for the project scope (similar to the split between Part A, B and C for Option 1).

Required:-

1. Create a Work Breakdown Structure (WBS) for the project. As a guide the WBS should contain between 60 and 75 activities. Do not exceed 80 task-level activities.

2. Create a schedule for the project. Determine the overall duration and when activities and events are planned to happen. The schedule is to include activities and their logical dependencies, with estimations of activity durations. Use the summary tasks, tasks and sub-tasks from the WBS for your schedule activities. Use Critical Path Scheduling techniques for the preparation of your project schedule. The start date for the project is the first working Monday after your Birthday this year. Adopt NZ industry standard holidays (Christmas, Easter, ANZAC day etc). Present your schedule as a Gantt Chart, using suitable scales. Use MS Project planning software and upload a soft copy of your MS Project file onto Canvas. Clearly identify the critical path(s). (20 marks)

3. When implementation is 50% complete according to the original time line (i.e. half the original time estimated for completion), unexpected risks result in the need for re-work to one of the major components of the project. The cost of the re-work is estimated to be 10% of the total project budget and the associated delay to the project completion date is estimated at 10% of the project duration. In addition, progress on the project has been slow, and you are running behind on your planned programme. As a result the client has asked you, (the Project Manager), to attend a crisis meeting. Using the elements from 1- 2 above, along with any other project control measures you are familiar with, develop a progress report the client. Indicate the likely delays and revised finish date for the project based on critical path analysis. Develop your recommendations for:

a. Options on how to achieve the original planned completion dates for all 3 Parts. Clearly indicate the implications for accelerating parts of the works with associated "crash costs".

b. Options on how to achieve the original total budget. Clearly indicate the implications upon scope and upon planned completion dates.

The client is open to suggestions on changes of scope, time and cost, but not prepared to relax the quality aspects of the project. Note that you should use MS Project to help answer this part of the assignment and use the outputs from the software to demonstrate implications and options, however a soft copy of your MS Project file is NOT required. (10 marks)

4. Comment on the benefits and limitations of critical path scheduling techniques. Identify and describe an alternative scheduling technique for management of time that might address some of the limitations of the critical path approach. Guide 1000-1500 words.

Verified Expert

The assignment consists of project management study of the 8-storey building for their refurbishment process. under refurbishment process, the basic concentration is done changes on lighting, flooring, painting and other processes. under this assignment, the basic study is done for managing the refurbishment process with an effective way using management tools such as CPM and Gantt chart.

Reference no: EM131453937

Questions Cloud

Determine the process capability : A turning process is in statistical control and the output is normally distributed, producing parts with a mean diameter = 30.020 mm and a standard deviation.
What keys to success did the leader describe : What keys to success did the leader describe? What are your thoughts on the leader's response? How you could implement their thinking in your own career?
Which topics should be expanded in their duration why : Which topics should be expanded in their duration? Why? Which topics should be refreshed and included in continuing education of experienced officers? Why?
Explain police discretion to the citizens group : How would you fully explain police discretion to the citizens' group? How do you explain the fostering of good ethical decision making and discretion
Create a work breakdown structure : CIVIL 703 - PROJECT MANAGEMENT - Create a Work Breakdown Structure (WBS) for the project. As a guide the WBS should contain between 60 and 75 activities. Do not exceed 80 task-level activities.
Property of consumer preferences : Harry's utility function is U = 5X + 15Y. Which property of consumer preferences does Harry's utility function violate? Explain your answer.
Finf the technical pattern of resistance area : Run a few of the lognormal price path simulations. Examine the price pattern for trends. Find one or more of the following technical patterns.
Low barriers to entry and one that has high barriers : Identify an industry that has low barriers to entry and one that has high barriers. Explain how the difference in entry barriers influences competitive behavior
What type of management style you perceive they used : Describe your best boss and write a short analysis on what type of management style you perceive they used. Share and compare with classmates.

Reviews

len1453937

4/7/2017 3:19:24 AM

Please look into the attached assignment. I want one of this done before 12th EOD of this month. please review and let me know the price to do the same. This assignment is worth 40% of the Project Management 1 Paper (i.e. 40 marks). • Submit all your answer in one document as a hard copy at the student services stall. In addition upload onto Canvas a soft copy of your submission document in PDF format, together with a soft copy of your MSProject File for Question 2. • This coursework is an individual piece of work and students must NOT work in collusion or in teams. Standard University guidelines for plagiarism and collusion apply. • This assignment has been developed in order to meet the needs of the various disciplines of students undertaking the course. There are two distinct options for students –COMPLETE ONE OPTION ONLY.

Write a Review

Other Subject Questions & Answers

  Cross-cultural opportunities and conflicts in canada

Short Paper on Cross-cultural Opportunities and Conflicts in Canada.

  Sociology theory questions

Sociology are very fundamental in nature. Role strain and role constraint speak about the duties and responsibilities of the roles of people in society or in a group. A short theory about Darwin and Moths is also answered.

  A book review on unfaithful angels

This review will help the reader understand the social work profession through different concepts giving the glimpse of why the social work profession might have drifted away from its original purpose of serving the poor.

  Disorder paper: schizophrenia

Schizophrenia does not really have just one single cause. It is a possibility that this disorder could be inherited but not all doctors are sure.

  Individual assignment: two models handout and rubric

Individual Assignment : Two Models Handout and Rubric,    This paper will allow you to understand and evaluate two vastly different organizational models and to effectively communicate their differences.

  Developing strategic intent for toyota

The following report includes the description about the organization, its strategies, industry analysis in which it operates and its position in the industry.

  Gasoline powered passenger vehicles

In this study, we examine how gasoline price volatility and income of the consumers impacts consumer's demand for gasoline.

  An aspect of poverty in canada

Economics thesis undergrad 4th year paper to write. it should be about 22 pages in length, literature review, economic analysis and then data or cost benefit analysis.

  Ngn customer satisfaction qos indicator for 3g services

The paper aims to highlight the global trends in countries and regions where 3G has already been introduced and propose an implementation plan to the telecom operators of developing countries.

  Prepare a power point presentation

Prepare the power point presentation for the case: Santa Fe Independent School District

  Information literacy is important in this environment

Information literacy is critically important in this contemporary environment

  Associative property of multiplication

Write a definition for associative property of multiplication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd