Create a wbs and carry out a bottom-up cost estimate

Assignment Help Financial Management
Reference no: EM132015613

Assignment

PART 1:

1) Following are elements of a WBS for a project to build a bunk bed. Using the information supplied here, create a WBS and carry out a bottom-up cost estimate.

2) Following is a listing of items to be considered in costing a PC game development project.  Use this data to develop a parametric estimate of the cost of the project.

3) For the table below

  1. Create a PERT/CPM chart
  2. Identify the critical path and compute project duration
  3. Compute Latest Start, Earliest Start, and Float (Slack)

PART 2:

1) The following table shows the allocation of work assignments and resources needed for an investment firm to make a decision on investing in company XYZ.

  1. Create Responsibility Matrix
  2. Create Resource Gantt Chart
  3. Create Resources Loading Chart

2) Building a swimming pool

  1. Create a Gantt chart from the work breakdown structure.
  2. Create a PERT/CPM network showing the interdependencies of the different activities.   How long will the project take?  (Note:  Don't forget to take "elapsed time" into account.)
  3. Using the information in your Gantt chart, as well as the information on wage rates and cost of materials, put together a budget showing planned total expenditures for the project.

3) Following are cost and schedule data for a project that is underway.

  1. Using the cost data in the cost table above, create a cumulative cost curve comparing actual versus planned costs
  2. Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance
  3. Summarize in words what you see project status to be at this time. What do you predict regarding the final cost and final schedule for the project?

PART 3: Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.

 

Budget

Begun?

Complete?

Actual cost

Earned Value

Task A

3,100

Yes

Yes

3,100

 

Task B

4,000

Yes

Yes

4,500

 

Task C

2,500

Yes

Yes

2,250

 

Task D

4,000

Yes

No

3,500

 

Task E

3,500

Yes

Yes

4,000

 

Task F

2,500

No

No

0

 

  1. Using the 50-50 Rule, what is earned value for this project?
  2. Using the 0-100 Rule, what is earned value for this project?
  3. Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.
  4. Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?
  5. What is the schedule performance index (SPI)?
  6. Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?
  7. What is the cost performance index (CPI)?
  8. If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).

9) Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also,provide projections for future status.

Reference no: EM132015613

Questions Cloud

What is the magnitude of the average torque : What is the magnitude of the average torque acting on the flywheel about its central axis during this period?
How economists are both scientists and policymakers : How economists are both scientists and policymakers and what principles society uses to allocate its scarce resources.
Double the mass of moving cart a : What happens on a momentum experiment when stationary cart B has double the mass of moving cart A? What type of collision is it?
How much slower is this than the earth escape velocity : How much slower is this than the earth's escape velocity?
Create a wbs and carry out a bottom-up cost estimate : Following are elements of a WBS for a project to build a bunk bed. Using the information supplied here, create a WBS and carry out a bottom-up cost estimate.
Discuss about supply chain innovations by wal-mart : Wal-Mart is well know to be a leader in Supply Chain Management. This week's writing assignment is related to Wal-Mart. Search the internet, the library.
Required yield to maturity on comparable-risk bond : the market's required yield to maturity on a comparable-risk bond is 15 percent.
How do you measure uncertainty : How do you measure uncertainty when doing a measurements experiment?
Stocks purchased with the market index increased : Correlation of stocks purchased with the market index increased from .6 to .8, and standard deviation of the stock and market index is 25.7%.

Reviews

Write a Review

Financial Management Questions & Answers

  Best estimate of the firm corporate cost of capital

A relatively small medical group practice is trying to estimate its corporate cost of capital. What is best estimate of the firm's corporate cost of capital?

  What is net present value of project

What is the present value of a $400 payment in one year when the discount rate is 5 percent? A proposed project has an initial cost of $70,500 and is expected to produce cash inflows of $31,200, $50,100, and $42,500 over the next 3 years, respectivel..

  Is your hourly wage rate an accurate reflection

You are forced to work either 20 hours or 40 hours per week. Is your hourly wage rate an accurate reflection of the value of your time?

  What is the firms net income

A firm has total assets of $280,000, a total asset turnover rate of 1.6, a debt-equity ratio .4, and a return on equity of 13.25 percent. What is the firm's net income?

  Simple interest versus compound interest

First City Bank pays 6 percent simple interest on its savings account balances, whereas Second City Bank pays 6 percent interest compounded annually. If you made a deposit of $9,000 in each bank, how much more money would you earn from your Second Ci..

  Two different capital structures-What is the break-even EBIT

Kyle Corporation is comparing two different capital structures, an all-equity plan (Plan I) and a levered plan (Plan II). Under Plan I, Kyle would have 715,000 shares of stock outstanding. Assume that EBIT is $1.6 million. Compute the EPS for both Pl..

  Credit union pays an annual interest rate

Janet Boyle intends to deposit $300 per year in a credit union for the next 10 years, and the credit union pays an annual interest rate of 8%. Determine the future value that Janet will have at the end of 10 years, given that end-of- period deposits ..

  Calculate annual operating break-even points

Build Income Statement for MS High-Tech Inc. from 2017 to 2020. Calculate Break-even points and conduct leverage analysis. Enter the above data into the worksheet. Build Income Statement for MS High-Tech Inc. from 2017 to 2020. Calculate annual opera..

  About publically traded health care organizations

publically traded health care organizations

  Residual dividend policy-what will be total dividend payment

The capital budget of Creative Ventures Inc. is $1,000,000. The company wants to maintain a target capital structure that is 30% debt and 70% equity. The company forecasts that its net income this year will be $800,000. If the company follows a resid..

  What is amount of the annual depreciation tax shield

Northern Lights is trying to decide whether to lease or buy some new equipment. The equipment costs $51,000, has a 5-year life, and will be worthless after the 5 years. The company has a tax rate of 34 percent, a cost of borrowed funds of 8.75 percen..

  Capital structure-taxes and firm value

Firm M will operate from time 0 to time 1, then shut down. At time 1, its EBIT will be 250. The tax rate on firm profits is 20%. The cost of capital is 25% for all cash flows regardless of risk. First, assume that the firm is all equity financed. Wha..

Free Assignment Quote