Project Management Exercise -
The Beta project team has started gathering the information necessary to develop the project network diagram - predecessor activities and durations in weeks. The results of their meeting are found in the following table.
Activity
Description
Duration
Predecessor
1
Define Scope
6
None
2
Define Customer Problems
3
Define data records and relationship
5
4
Mass Storage Requirements
2, 3
Consultant Needs Analysis
11
Prepare Installation Network
7
Estimate Costs and Budgets
8
Design Section Point System
4, 5
9
Write Request Proposal
10
Compile Vendor List
Prepare MGMT Control System
6, 7
12
Prepare Comparison Report
9, 10
13
Compare System Philosophies
8, 12
14
Compare Total Installation
15
Compare Cost of Support
16
Compare Customer Satisfaction Level
17
Assign Philosophies Points
18
Assign Installation Cost
19
Assign Support Cost
20
Assign Customer Satisfaction Points
21
Select Best System
11, 17, 18, 19, 20
22
Order System
The project team has requested that you create a network diagram for the project, identify the critical path, and determine if the project can be completed in 50 weeks.
You are to first do a "hand drawn" solution, and then use Microsoft Project to create network diagram again. Assumptions: Start date is October 3, 2016, one shift per day, no overtime, no weekends, and all traditional holidays to be observed.
What difficulties can occur if the contractors have decided on work assignments, and what changes may be necessary if problems occur?
The decision makers are polarized along ethical and religious lines. Since this is a potentially emotional issue, what would you do in order to break this impasse?
project scope managementwhy is project scope management important to the success or failure of a
Think of an IT project that you would like to start as a project initiator or sponsor. Conceptualize and define the overall goal of the project, and how it adds tangible value to an organization
As part of the management team for PPQ Parts manufacturing company, you are tasked with selecting the best software packages for the firm's materials requirements planning (MRP), capacity requirement planning (CRP), and enterprise resource plannin..
operating cash flow for a proposed projectestimate the first-year operating cash flow at t1 for a proposed project. the
What are some sources of barriers to group effectiveness that this group may face in trying to meet its goals and show the teams progress on your project.
Distinguish between capital project funds and debt service funds. How are they related and how are they different?
(a) Does the line graph flatten out? (b) If so, after how many stakeholders? (c) What conclusions can be drawn about the policy problems in the issue area?
What if she were only given a quarter share? - What would be the lowest share she would accept to manage the firm?
Develop a high-level project schedule using MS Project. In your schedule, identify the milestones and assign durations to tasks.
What is the first step in the project management "cycle"?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd