Create a gantt chart and network diagram

Assignment Help Project Management
Reference no: EM133088254

Leadership in IT Project Management - Project Time Management

Objective 1: Appreciate the importance of scheduling on projects.
Objective 2: Develop a milestone report.
Objective 3: Recognise reasons for creating dependencies.
Objective 4: Develop network diagrams applying the ADM and the PDM techniques.
Objective 5: Identify and apply different types of relationships between activities.
Objective 6: Describe and apply different estimation techniques.
Objective 7: Create a Gantt chart and network diagram.
Objective 8: Apply the critical path method.
Objective 10: Apply critical chain scheduling
Objective 11: Describe the PERT technique.

Question 5.1 - Schedule Conflicts *
Why do you think schedule issues often cause the most conflicts on projects?

Question 5.2 - Defining Activities
Refer to the case study Dog Shelter App. Complete the Define Activities process by using the template provided (see Table 1) to develop a milestone list for the WBS (see Figure 1). Identify at least one milestone for each process group heading.
Note the following assumptions.
1. the project will take 6 months (24 weeks) to complete
2. all executing activities will have F-S relationships
3. the project manager will be available one day p/week to manage project, status reports and updates will be provided on Fridays weekly throughout project lifecycle
4. the activities review existing processes, and conduct research, take 2 weeks each commencing in week 1
5. the activities gather database historical content, database design, database construction, and database testing will take 4 weeks each
6. the activities database promotion and database roll-out will take 2 weeks each

Question 5.3 - Sequence Activities
Complete the Sequence Activities process by identifying logical relationships (dependencies or predecessors) between activities in the WBS provided (see Table 2). Possible task dependencies include: Finish-to-start (FS), Start-to-start (SS), Finish-to-finish (F) and Start-to-finish (SF).
• Complete the type of dependency in the Type column (this is FYI only). Types of dependencies can be selected from mandatory (M), discretionary (D) and external (E).
• Enter WBS from Figure 1, and draft task dependencies into MS Project (or similar software).

The next process in Project Time Management is completing the Estimate Activity Durations process. Many project managers use the expert judgment technique to approximate the number of work periods needed to complete each activity in the WBS. Project Managers use the duration of time (duration includes the actual amount of time worked on an activity plus the elapsed time), as opposed to the effort (which is the time used for billing).

Question 5.4 - Estimate Activity Durations
Develop a Summary Schedule (use Table 3). Estimate the approximate maximum time frame for each WBS Summary Task (useFigure 2).The initiating process group has been completed for you. Remember the project duration is 6 months (24 weeks).

Question 5.5 - Develop Schedule
UsingMS Project (or similar software), complete the Develop Schedule process for the Dog Shelter App project.
• Update any task dependencies.
• Enter start and finish times for each activity being careful to stick to the Summary Schedule timelines you developed in Question 5.4.
• Include the key milestones you created in Question 5.2 (hint: give them a 0 duration, and they will appear as black diamonds on the Gantt chart).
• Add any activity resources.
• Use the Precedence Diagramming Method (PDM) in MS Project (or similar software), to generate a network diagram for the Dog Shelter App Project. Answer the following questions:
1. How many paths are on this network diagram? How long is each path?
2. Which is the critical path? What is the shortest amount of time needed to complete this project?
3. What slack or float time is available on the non-critical tasks of this project?
4. What does the critical path really mean? How might this information be valuable to the project manager of this project?

Question 5.6 - Critical Path
Calculate the critical path by sketching an Activity on Node (AON) project network diagram, from the information in Table 4.
1. Alternatively sketch and AON diagram using the Gantt chart provided in Figure 3.
2. Identify all of the paths on the network diagram and note how long they are.
3. Which is the critical path for this project and how long is it?

Question 5.7 - Task Dependencies
Phil is the project manager of a network upgrade. All of the client workstations are to be replaced, and this task has been assigned to Steve, Harry, and Beth. Once the physical workstations are in place, Sam will release an automated script to deploy an operating system to each of the new workstations. What type of relationship (or dependency) describes these two tasks? What other types of relationships might be evident on a project like this one, give examples.

Question 5.8 - Case Study
Read the case study Bryce Power Tool Company. Is this technique a reasonable way to schedule the IT resources of Bryce? Why or why not? What complication is added by dividing this into four separate projects?

Attachment:- Leadership in IT Project Management.rar

Reference no: EM133088254

Questions Cloud

Identify 3 to 5 leadership actions : Identify 3 to 5 leadership actions that build trust between leaders and followers. Use several resources such as your textbook, module resources, or peer-review
Price of french cheeses : A Canadian cheese dairy decide export to France a variety of traditional cheeses. The demand for these products is very high in this country and there are many
By how much did BlubBlub Co deferred tax assets decrease : The federal corporate income tax rate is 21%. By how much did BlubBlub Co's deferred tax assets decrease in 2019
Perspective of environment dependent organizational : Discuss your ideas from the perspective of environment dependent organizational, process oriented and alternative choices.
Create a gantt chart and network diagram : Develop network diagrams applying the ADM and the PDM techniques and Describe and apply different estimation techniques
Achieve organizational results : In an era when the health care environment is changing dramatically, opportunities are created for health care leaders who are able to show effective skills to
How much would the manufacturing overhead for the year : The actual direct labor cost incurred on jobs during the year was $208,000. How much would the manufacturing overhead for the year
Create a concept map showing the interrelatedness : Create a concept map showing the interrelatedness of the different functional of areas of management. Make it creative as possible.
Adhered to or monitored by management : What happens to a team if group norms are not adhered to or monitored by management? Explain using an example.

Reviews

Write a Review

Project Management Questions & Answers

  Project management questionyou are designing a grocery

project management questionyou are designing a grocery delivery business. via the internet your company will offer

  Does a durable good monopolist have an incentive

If a durable good monopolist cannot commit to future prices, does the number of consumers matter? Explain.-  Does a durable good monopolist have an incentive to set its prices flexibly in each period? Discuss.

  Discuss ten characteristics of a servant leader

Discuss ten characteristics of a servant leader as posit by greenleaf according to Larry Spears and give some examples.

  Improve the organizations learning and growth

Identify at least three objectives for improving the organization's learning and growth, and show how they relate to the mission, vision and strategy of the organization and develop at least one meaningful performance measure

  Chart a course for a substantial industry project

Chart a course for a substantial industry project and Ensure the project bridges theory and practice - Integrate technology into learning environment

  Future of project management

Write a 5 -to- 6-page research paper - Future of project management. Research relevant to the aviation and aerospace industry and the paper must meet APA format

  Organization anti-corruption policies and procedures

Organization's anti-corruption policies and procedures.

  Global supply chain management strategy

Identify and research a company with a successful global supply chain management strategy and provide basic background information.

  Models in project managementplease provide guidance on how

models in project managementplease provide guidance on how i should develop this paper. your help is greatly

  Effective communication in project management

Are there any disadvantages to comes with using Direct negotiation as the best approach for conflicts in projects?

  Describe the issues of the current ethical culture

Describe the issues of the current ethical culture. Formulate a plan to change the ethical culture. Convince the CEO and shareholders of importance of changes.

  Implement course-of-action controls to correct

Describe how you would use the project buffer to determine the point at which you would implement course-of-action controls to correct an unacceptable

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd