ASSESSMENT TASK - ACTIVITY 1.2 - ALLOWANCES, DRAWINGS AND VARIATION
Part A
Complete the administrative processes outlined below in order to allow for adjustments to finances and timelines in accordance figures below from a residential/domestic building contact for project no.33837 Leary Ave in accordance with the project documentation provided in the project portfolio. You will need to access both project documents PN 33837 Leary Ave - Project Documentation and PN 33837 Leary Ave - Plan Pack.
The total cost of the project is $675,000. A percentage of this total amount is to be paid at each stage of development as outlined below. Calculate the amount to be paid at each stage of development based on the percentages listed.
When the contract was originally signed on 30/03/2016, an allowance had been made for the cost of the bathroom fixtures and fittings. This allowance was based on the cost of a standard bathroom fit out. However, on 14/05/2016, Cheryl contacted you by phone to say that she would like to use copper bathroom fixtures instead.
Later that day you rang the bathroom supplier to discuss these changes and was told that the difference in cost between these materials would be $8,500. The supplier also stated that the materials would need to be shipped in from Italy and that they would arrive on 21/06/2016. Based on the delivery date provided by the supplier, you predict that this will push the settlement date back by 14 days.
You are now required to prepare a report answering the following questions:
How should this additional cost be incorporated into the total cost of the build?
What action(s) must be taken if the cost cannot be incorporated in this way?
Request the appropriate parties to authorise an extension of time by drafting an email you would send to the parties. The email draft can be within the report, it does not have to be a separate document
How will I be assessed for this task?
For this task, you are required to submit the following:
Completed report covering above requirements
Report must be typed and formatted
Part B
The agreed upon colour of the paint for the internal walls is listed in the contract as, ‘Morning Moon.' After considering the impact of the new copper fixtures, Cheryl emailed you on the 19th of May asking to change this to, ‘Dogwood Blossom' as it better suits her new vision for the décor.
The paint order hasn't been fulfilled by the supplier yet so the change can be made.
You are now required to write a report and answer the following questions:
Is this considered a variation or a non-cost variation?
Should this change be documented? Why / why not?
Create a diary of all on-site communication and events that have been outlined in including communications with clients, contractors, and suppliers.
How will I be assessed for this task?
For this task, you are required to submit the following:
Completed report covering above requirements
Report must be typed and formatted
Attachment:- Allowances, Drawings And Variation.rar
What percentage of the total interest has been paid
: After 27 payments have been made, what percentage of the total interest has been paid ( round to the nearest percentage point)?
|
Unintended consequences of raising minimum wage
: Discuss the unintended consequences of raising minimum wage, as it relates to potential changes in the incentives for low skilled workers to increase their huma
|
Different options regarding how to charge the owners
: The Shoreline Condominium Association is considering whether to install a major new heating system
|
Determine the anticipated return after financing costs
: What will earnings per share be? Would it be higher or lower than the earnings per share computed for the most aggressive plan computed
|
Create a diary of all on-site communication and events
: How should this additional cost be incorporated into the total cost of the build and What action(s) must be taken if the cost cannot be incorporated in this way
|
Depreciation of a currency
: In a certain economy, when income is $100, consumer spending is $60. The value of the multiplier for this economy is 4. It follows that, when income
|
Equilibrium level of real gdp and the value
: The equilibrium level of real GDP and the value of the multiplier, respectively, are:
|
Determine which is the changes in equity
: Baldwin earned revenue of $184,898,675 and had expenses of $171,196,185. This will cause which of the following changes in equity?
|
Saving and investment identity
: As discussed in the class, total national saving equals to total investment spending in a closed economy. Now, let's replicate the work in the class
|