Create a detailed and comprehensive timeline

Assignment Help Project Management
Reference no: EM131669737

Applied Project Management Case Assignments

Assignment 1 -

Using what you learned in Webinar 1 - Getting Started with MS Project, create a new MS Project file (blank file) and name it with your last name and ASMT1 (example: WilsonASMT1) as the file name. Use the Gantt Chart view and enter the tasks, durations, and dependencies from the basic WBS below. For the dates, use the start date of Monday of Module 3. Be sure that each task is auto-scheduled and be certain to include the non-workday "Company Picnic" that will occur on Thursday of Module 3.

Genesis System Upgrade Project WBS 

1. Evaluation & Recommendations (5 Days)

2. Develop Project Charter (10 Days) (Link to 1)

3. Sponsor Review/Approval (2 Days) (Link to 2)

4. Create Preliminary Scope Statement (5 Days) (Link to 3)

5. Determine Project Team (5 Days) (Link to 3)

6. Project Team Kickoff Meeting (1 Day) (Link to 5)

7. Develop Project Plan (10 Days) (Link to 6)

8. Verify & Validate User Requirements (14 Days) (Link to 7) 

9. Design System (14 Days) (Link to 8)

10. Procure Hardware/Software (14 Days) (Link to 9)

11. Install Preliminary System (2 Days) (Link to 10)

12. Test Preliminary System (5 Days) (Link to 11)

13. Install Live System (5 Days) (Link to 12)

14. User Training (2 Days) (Link to 13)

15. Audit Procurement (5 Days) (Link to 14)

16. Document Lessons Learned (2 Days) (Link to 15)

17. Update Files/Records (2 Days) (Link to 15)

18. Gain Formal Acceptance (5 Days) (Link to 14)

19. Archive Files/Documents (1 Day) (Link to 17)

20. Closeout Meeting (1 day) (Link to 19)

Assignment 2- Resources and Instructions

1. Use the Resource Sheet view in MS Project to enter the following names of personnel assigned to the project:

a. John

b. Mike

c. Nancy

d. Dave

e. Dr. Jackson

f. PMO

g. (YOUR NAME) as PM

h. Pindar

i. Emilio

j. Pam

k. Estaban

l. Craig

2. Use the Gantt Chart view to assign resources from the dropdown menu under the Resource Names field for each of the following tasks:

m. Evaluation & Recommendations - John, Mike

n. Develop Project Charter - John, Mike, Nancy, Dave

o. Sponsor Review/Approval - Dr. Jackson

p. Create Preliminary Scope Statement - Nancy

q. Determine Project Team - PMO

r. Project Team Kickoff Meeting - PM

s. Develop Project Plan - Dave, PM

t. Verify & Validate User Requirements - Pindar, Emilio, Pam

u. Design System - Pindar, Estaban

v. Procure Hardware/Software - Nancy, PMO

w. Install Preliminary System - Emilio, Estaban

x. Test Preliminary System - Pindar

y. Install Live System - Emilio, Estaban

z. User Training - Craig

aa. Audit Procurement - PMO

bb. Document Lessons Learned - PM

cc. Update Files/Records - PMO

dd. Gain Formal Acceptance - Dr. Jackson

ee. Archive Files/Documents - PMO, PM

ff. Closeout Meeting - PM

 3. Generate a Resource Overview report and save and name it by choosing File - Export - Create PDF/XPS - lastnameFirstname-REPORT1- Publish Range All (submit this file with your MS Project file).

4. Reduce the Design System by two days and allow Pindar and Estaban to work overtime to keep the schedule on track.  

5. As PM, Schedule yourself for a doctor's appointment on the final day of the project (moving it out one extra day) for the Closeout Meeting.

Assignment 3- Resources and Instructions

1. Using the Gantt Chart view, create a detailed and comprehensive timeline by taking the following steps:

a. Add an "End Project" milestone and link it to the final activity.

b. Add a "Charter Approved" milestone after the Sponsor Review/Approval activity.

c. Link the Create Preliminary Scope Statement and Determine the Project Team to the Charter Approved milestone (Hint: Use predecessor column).

d. Change the predecessors in the Project Team Kickoff Meeting activity to the two prior activities (Create Prelim Scope/Determine Project Team). 

e. Add a "Project Plan Approved" milestone and link it to the Develop Project Plan activity.

f. Link the Verify & Validate User Requirements activity to the Project Approved milestone.

g. Add a "Live Rollout" milestone after the link to User Training.

h. Link the Audit Procurement and Gain Formal Acceptance activities to the Live Rollout milestone.

2. Add the following Summary Tasks:

  • Initiation Phase - from Evaluation & Recommendation to Charter Approved milestone
  • Planning Phase - from Create Preliminary Scope to Project Plan Approved milestone
  • Execution Phase - from Verify & Validate User to Live Rollout milestone
  • Closeout Phase - from Audit Procurements to End Project milestone

3. Generate a timeline showing only the four phases above along with the milestones. 

a. Color-code each phase with a different color.  

b. Pull out the milestones from the timeline (if necessary). 

c. Create a presentation-size copy and paste it into a blank Word Document (may be helpful to use a landscape orientation). Save it, name it (lastnameTimeline), and submit this with your MS Project file.

Assignment 4- Resources and Instructions

1. Using the Gantt Chart view, take note of your current completion date for the project.

2. Set the Status Date of the project to today's date.

3. Set a Baseline for the entire project.

4. Show the baseline (gray bars) on your timeline.

5. Add the following completion percentages to the tasks below: 

a. Evaluation & Recommendation - 100% complete

b. Develop Project Charter - 95% complete

6. Move the Sponsor Review/Approval task out 2 business days (add two days) and keep the link to the next task.

7. Show the critical tasks on the timeline.

8. Adjust the Duration on critical tasks that can logically be changed to get your project back to its original completion date (cannot change Sponsor Review/Approval activity again)

9. Generate a Project Overview report by phase (default). Save and name the file: Choose File - save as - browse to where to save - from Save as type: dropdown - select PDF Files - rename lastname OVERVIEW (leave publish range set to "All").

10. Provide a Resource Overview report. Save and name the file: Choose File - save as - browse to where to save - from Save as type: dropdown - select PDF Files - rename lastname RESOURCE (leave publish range set to "All").

Assignment 5 - Resources and Instructions

1. Access the Resource View of your project.

2. Add the following Standard Rate for each of the employees or offices below (you must also enter Overtime rates for Pindar and Estaban):

a. John - $35/hr

b. Mike - $35/hr

c. Nancy - $35/hr

d. Dave - $35/hr

e. Dr. Jackson - $65/hr

f. PMO - $45/hr

g. Project Manager (student) - $40/hr

h. Pindar - $55/hr std. - $82.50/hr overtime

i. Emilio - $55/hr

j. Pam - $35/hr

k. Estaban - $55/hr std. - $82.50/hr overtime

l. Craig - $35/hr

3. Enter the following material costs to your sheet at the bottom.

a. Resource Name: Hardware - Type: Material - Material: Bundles

b. Resource Name: Software - Type: Material - Material: Flat Fee

4. Attach 3 Hardware Bundles and 1 Software Flat Fee to the Procure Hardware/Software task within the Execution phase.

5. Generate a Resource Cost Overview report. Save as a PDF file named lastnameCOST1.

6. Generate a Task Cost Overview report. Save as a PDF file named lastnameCOST2.

Attachment:- Assignment File.rar

Reference no: EM131669737

Questions Cloud

Employment and unemployment and potential gdp : Using the relevant graphs, show and explain the effect on wage, employment and unemployment and potential GDP.
What transfer price is economically optimal for gc : Assume that English tax laws permit transferring at either variable cost or market price. What transfer price is economically optimal for Gage Corporation?
Discuss financial impact with implementing each initiative : Discuss the financial impact, positive or negative, associated with implementing each initiative. Provide support for your rationale.
What serious threats does the united states face : What serious threats does the United States face? Explain. How significant are the threats posed compared to the other 5 topics? Why?
Create a detailed and comprehensive timeline : PRM 524 - Applied Project Management Case Assignments. Using the Gantt Chart view, create a detailed and comprehensive timeline
What are the primary motivations behind international terror : What are the primary motivations behind international terror organizations that continue to plan to or actively strike against Western nations? Explain.
Value and the challenges of applying complexity theory : Characteristics or techniques of Systems Dynamics is the development of models - implemented in the project, program and portfolio environment
Contrast the four marketing management philosophies : Compare and contrast the four marketing management philosophies that companies choose to adopt.
Explain the need for decision making and individual roles : Explain the need for decision making, individual roles, and why accepting duties of one's role is important to accomplishing objectives and goals of an agency.

Reviews

len1669737

10/6/2017 1:23:46 AM

Detailed Question: I need the information in the attachments completed using Microsoft project 2013. The information on the Gantt Chart is not correct, please revise. Using what you learned in Webinar 1 – Getting Started with MS Project, create a new MS Project file (blank file) and name it with your last name and ASMT1 (example: WilsonASMT1) as the file name. Use the Gantt Chart view and enter the tasks, durations, and dependencies from the basic WBS below. For the dates, use the start date of Monday of Module 3. Be sure that each task is auto-scheduled and be certain to include the non-workday “Company Picnic” that will occur on Thursday of Module 3. Thank you.

Write a Review

Project Management Questions & Answers

  Project scope and schedule for wal-mart

How would a consultant develop the project scope and schedule for Wal-mart?

  Why do you feel that the will allow for a successful project

How will your procurement process integrate with the rest of the project? Why do you feel that this will allow for a successful project? What procurement management processes will you use within your plan? Why?

  Explain types of risk that organizations face

Explain types of risk that organizations face - What are the different types of risk that organizations face? What are the benefits of risk management?

  Show the project management communication

Project management communication - explain what are the critical elements of a communication plan?

  Was it fair for the vietnamese catfish importers

Was it fair for the Vietnamese catfish importers to step in and capture market share while the market has been expanded due to the significant efforts and investments of the domestic industry.

  Explain what result in given situation

McJunkin filed a third-party complaint against Alaskan, alleging that Alaskan was liable for any damages Mechanicals incurred as a result of the defective stub ends. What result? Explain.

  Identify tensions or inconsistencies or contradictions

Identify tensions, inconsistencies, contradictions, or conflicts that emerge within the text and explain how those conflicting perspectives reflect and represent its larger social context - both within the work and beyond it.

  Types of cost reimbursable contracts

What are the types of Cost Reimbursable contracts? Describe the benefits of using these types of contracts and explain how these types of contracts could be use

  Shared activity leadership values

This unit is about the values and principles that underlie leadership behaviour. For this Shared Activity, you will discuss whether leadership values are universal or whether they can be contextual or culturally derived.

  Apply project management learnings and techniques

As a small project team (3 - 4 members) you are to look at an Oil and Gas project (Option 1: Solar Panels OR Option 2: Knowledge Management System) and to apply project management learnings and techniques to deliver the following milestone:

  What is required to prove promissory estoppel

List the four types of consideration described in the text.-  What is required to prove promissory estoppel when consideration is missing?

  Marketing research is extremely important

As a business owner, marketing research is extremely important, yet many small business owners do not have the time to conduct their own research. If they also cannot afford to hire a marketing firm to conduct this research for them, what would you r..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd