Assignment:
The table below represents the raw data for developing a project schedule. Generate the PERT Chart showing earliest/latest start/complete free/total float for each task. Create a CPM diagram for the project and identify the critical path. Generate a Gantt chart showing total floats for all tasks. Try to optimize task scheduling to minimize the number of hiring's and firings (calculate the number), and draw the resulting manpower chart. Using a labor rate of $50/hr ($2000/wk) per head, generate a cumulative expenditure curve for the duration of the project.
Deliverables:
• Critical values- minimum Project Completion (PC) time, Total project cost ($)
• CPM Diagram- Show critical path; Identify task symbol & duration
• PERT chart- ES, EC, LS, LC, TF, FF for each task
• Gantt chart- Schedule to minimize staff turnover
• Manpower chart- Showing the headcount required in each week/day of the projectr
• Cumulative Expenditure curve- Using Gantt chart schedule; burn rate from pert chart
You should include a copy of well-organized supporting documentation for the creation of each of these management tools.
Resource Data:
Use a labor rate of $2100/week per engineer. Headcount is expressed in engineer labor force for each task and the listed duration.
Task Expenses are expressed in $ 1k increments.
Task Symbol
|
Task Dependencies
|
Duration (wks)
|
Head Count
|
Task
Expenses (Thousand S)
|
A
|
|
2
|
1
|
48
|
B
|
A
|
4
|
1
|
|
C
|
h
|
4
|
2
|
|
D
|
j, m
|
2
|
2
|
22
|
E
|
k, m
|
3
|
4
|
15
|
F
|
l, m, n
|
2
|
1
|
4
|
G
|
n, o, d, e, f
|
2
|
2
|
|
H
|
b. g
|
1
|
2
|
2
|
J
|
a
|
5
|
4
|
1
|
K
|
a
|
6
|
3
|
1
|
L
|
a
|
4
|
2
|
1
|
M
|
J, k, l
|
5
|
3
|
2
|
N
|
j, k, m
|
2
|
2
|
8
|
0
|
m, n, e
|
2
|
1
|
4
|
What is the probability that the sum is nine or greater
: Draw a graph of the resulting probability distribution of the sum and calculate its mean and variance. What is the probability that the sum is 9 or greater?
|
How was the value of the art determined
: What formal visual elements are used in the piece? (color, texture, value, form, etc). What medium/media and techniques were used. What is its present physical condition? Has it been damaged or enhanced. How long did it take to make. How was the val..
|
How measure the displacement
: measure the displacement,
|
What is the probability that x will exceed
: Calculate P(X . What is the probability that X will exceed 0.5? Given that X > 0.5, what is the probability that X will be less than0.75?
|
Create a cpm diagram for the project
: Create a CPM diagram for the project and identify the critical path. Generate a Gantt chart showing total floats for all tasks. Try to optimize task scheduling to minimize the number of hiring's and firings (calculate the number), and draw the res..
|
What is strategic management and what are some of its major
: What is strategic management and what are some of its major objectives? Explain in two paragraphs.
|
Summary on the axis on the march and the fall of france
: Please write the one page summary of the topic (your choice) has to be related to the course which is World War 2, and the questions as stated.
|
How does the line-drawing approach help solve ethical
: What makes engineering a true profession
|
Compute descriptive statistics for time and pages viewed
: Compute descriptive statistics for TIME, PAGES VIEWED, and AMOUNT SPENT [Hint: Use the DATA ANALYSIS tool in Excel; choose DESCRIPTIVE STATISTICS.
|