Bright Star Dance Company will be producing a modern dance show over a three-month period of time in October-December. It needs to employ designers and a construction crew to build a stage set for the show. The employees it will hire to construct the set are contract workers.
Shown below is the schedule for the construction effort, plus information on the costs of resources.

RESOURCES
Design stage set (10% chance 3 days delayed)
1 designer @ $1,000/wk (Weeks 1, 2, 3).
Fabricate stage set items (20% chance 3 days delayed)
2 carpenters @ $700/wk each (Weeks 4, 5, 6)
2 painters @ $600/wk each (Weeks 5, 6)
Assemble stage set (20% chance 3 days delayed)
2 carpenters @ 700/wk each (Weeks 7,8)
1 painter @ $600/wk (Week 7)
Engage in electrical work (10% chance half day delay)
2 electricians @ $1,000/wk each (Half week 7 plus full week 8)
Materials
Materials cost: $15,000
(Payments of $5,000 in weeks 1, 3, and 5)
Rental
Rent equipment (tools) @ $200/wk during weeks 4, 5, 6, 7, and 8
Assignment
1. Create a budget for the set design and construction project
2. Why don't you need to take into account fringe benefit costs for the workers?
3. Using the expected monetary value concept, calculate what contingency reserve should be set aside to deal with the prospects of cost overruns.
(Hint: As a first step, you need to estimate the possible cost of the specified overruns, using the data in the table.)
Time for you to be the symphony orchestra
: When you are used to hearing music played on only one instrument, what could be more captivating than listening to a full symphony orchestra? This week, it is time for you to be the symphony orchestra, i.e., pull out all of the stops.
|
What is the percent regulation of the line
: Find the voltage, current, real and reactive power, and the power factor at the sending end in both per unit and absolute units.
|
Wired and wireless technology
: Review the chart in the "Networking Technologies Used for Internet Connections" section of Chapter 16. What types of technology (wireless or wired) are used in business today? Include at least two examples. Which wireless technology types do you t..
|
Prepare a balance sheet and statement of cash flows
: Explain why a difference does or does not exist between net income and net cash flow from operating activities - Prepare an income statement, balance sheet, and statement of cash flows.
|
Create a budget for the set design and construction project
: Create a budget for the set design and construction project. Why don't you need to take into account fringe benefit costs for the workers. Using the expected monetary value concept, calculate what contingency reserve should be set aside to deal with ..
|
Determine the percent regulation of the line
: The sending-end Voltage, current, real and reactive powers, and the power factor.
|
What are the different types of listening styles
: What are the different types of listening styles, and what style do you most closely identify with? Explain what your listening style is and what you have observed about how you listen.
|
Compare and contrast the four motivation theories
: discuss the criticism of each theory. Which theory you identify with the most and why? You can identify with more than one, but it is not required. Development of idea and grammar.
|
Different types of correspondence in the workplace
: You are working as the communications officer for a company located in a large office building with designated areas for employee breaks and lunches, located on each floor.
|