1) Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.

 

Budget

Begun?

Complete?

Actual cost

Earned Value

Task A

3,100

Yes

Yes

3,100

 

Task B

4,000

Yes

Yes

4,500

 

Task C

2,500

Yes

Yes

2,250

 

Task D

4,000

Yes

No

3,500

 

Task E

3,500

Yes

Yes

4,000

 

Task F

2,500

No

No

0

 

  • Using the 50-50 Rule, what is earned value for this project?
  • Using the 0-100 Rule, what is earned value for this project?
  • Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.
  • Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?
  • What is the schedule performance index (SPI)?
  • Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?
  • What is the cost performance index (CPI)?
  • If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).
  • Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.

Reference no: EM13967639

Questions Cloud

Why alcohol should be illegal : PERSUASIVE PAPER TOPIC: Why Alcohol should be illegal(NOT LEGAL)
Perform a work breakdown structure and gantt analysis : Perform a Work Breakdown Structure (WBS) and Gantt analysis for the project in your scenario and identify and briefly describe the project planning tools you would use for your scenario.
Why do we spend so much of our resources fighting death : Why do we spend so much of our resources fighting death? What are the implications (for our economy, our resources) of a longer-lived population?
Prepare a critique of two project planning tools : You will continue to explore project planning tools, focusing on the Work Breakdown Structure (WBS) and Gantt chart - Identify and briefly describe the project planning tools you would use for your scenario, explaining why you would use each one.
Cost variance for the project : Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported? What is the schedule performance index (SPI)? Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?
Describe the basic structure of stage : A writer to write one page double space paper. in the paper, just describe the basic structure of stage. like audio, light and layout something else like that. I dont need a very pro writing skill and art konwlege. Just make a easy essay.
An argument paper about solar panels : An argument paper about solar panels and why residential should install them. This is an argument paper so I need to fight about WHY should they have solar panels vs not having solar panels. The paper has to have a thesis and the rest of the general ..
Income statement for the year ended : Income Statement for the Year Ended interest from money market account Aspen Ridge maintains its books using GAAP
Calculate and plot torque-speed characteristic for motor : If the motor is connected cumulatively compounded as shown in Figure and if Radj = 175 Ω, what is its no-load speed? What is its full-load speed? What is its speed regulation? Calculate and plot the torque-speed characteristic for this motor.

Reviews

Write a Review

Management Theories Questions & Answers

  Learning in action

Learning contract proposal that will form the basis of your learning contract report.

  Change is the only constant

"Change is the only constant " Evaluate the different types of change that have occurred in Sony.

  How do advertisers try to use group influence

How do advertisers try to use group influence?  Will you find any specific examples and explain the relevant theory of group behavior and influence?

  Case study:saving sony

You have been appointed by Sony as a consultant on change management. Advise Sony on how they could implement the change by using the various theories of change you have learnt.

  How the stock market works

The purpose of this project is to help you to gain an understanding of how the stock market works and of the relationship between theory and practice.

  Find the optimal production quantities

Find not only the optimal production quantities, but also the optimal total cost.

  Describe the management process

Describe the management process and identify the skills required to manage business organizations.

  Case study : bert''s bonsai and aquatic sport museum

Case Study : Bert's Bonsai and Aquatic Sport Museum Prepare a knowledge management system.

  Knowledge management techniques

Demonstrate understanding of the many-sided nature of knowledge management

  Theory of transtheoretical model

Demonstrate understanding of the many-sided nature of knowledge management

  Write a paper on historical trends of management

Write a paper on Historical Trends of Management.

  Theory of reasoned action

Theory of Planned Behavior and Integrated Behaviors Model

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd