Cost to prepare bottom-up estimates

Assignment Help Accounting Basics
Reference no: EM13917789

1) The cost to prepare bottom-up estimates will typically run how much more than the costs to prepare the top-down estimates?
A. About the same
B. About twice as much
C. About three times as much
D. About four times as much
E. About five times as much]

2) Resource shortages, in the form of people, equipment, or materials, is a good example of
A. Hidden interaction costs
B. Things going wrong on a project
C. Normal conditions not applying
D. Changes in project scope
E. None of these are correct

3) The accuracy of top-down estimates will typically be in the range of
A. Minus 50% to plus 50%
B. Minus 0% to plus 75%
C. Minus 20% to plus 60%
D. Minus 35% to plus 35%
E. Minus 10% to plus 30%

4) Design flaws being revealed after the fact, extreme weather conditions, and accidents occurring are examples of:
A. Hidden interaction costs
B. Things going wrong on a project
C. Normal conditions not applying
D. Changes in project scope
E. None of these are correct

5) In practice, estimating processes are frequently classified as
A. Top down/bottom up
B. Rough/polished
C. Precise/order of magnitude
D. Draft/final
E. Both A and B are correct

6) Which of the following is a good condition for top-down estimating?
A. Cost and time important
B. Fixed price contract
C. Customer wants details
D. Internal, small project
E. All of these are good conditions for top-down estimating

7) Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $25,000 in expenses will cover her needs. Because management typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction. Which of the following factors is illustrated in this situation?
A. Padding estimates
B. Planning horizon
C. Project structure
D. People
E. Organization culture

8) A/an _________ activity has more than one dependency arrow flowing from it.
A. Parallel
B. Critical path
C. Burst
D. Merge
E. Independent

9) ________ activities are to be completed immediately following a particular activity.
A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical

10) When translated into a project network, a work package will become
A. A single activity
B. One or more activities
C. A milestone
D. A critical path
E. An arrow

11) Activities which can take place at the same time are termed
A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity

12) The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:
A. Hammock
B. Laddering
C. Lag
D. Cushion
E. Buffer

13) The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:
A. Hammock
B. Laddering
C. Lag
D. Cushion
E. Buffer

14) Which of the following is not one of the steps in the risk management process?
A. Risk response development
B. Risk assessment
C. Risk identification
D. Risk tracking
E. Risk response control

15) One of the keys to success in risk identification is
A. Critical thinking
B. Optimism
C. Pessimism
D. A "can do" attitude
E. All of these are correct

16) The 1999 NASA Mars Climate Orbiter is an example of
A. Disaster avoidance through proactive risk management
B. Murphy's Law
C. Proper use of critical thinking
D. Mismanaged risk control
E. Using historical records to assess risk

17) A list of questions that address traditional areas of uncertainty on a project is termed a risk
A. Risk profile
B. Questionnaire
C. Research
D. Query
E. Checklist

18) One common mistake made early in the risk identification process is to
A. Not all possibilities are considered
B. Participants are over-optimistic
C. Participants are over-pessimistic
D. Focus on objectives and not on the events that could produce consequences.
E. Too much attention is given to past events

19) In the beginning the focus of risk management should be on risks that
A. Impact the whole project
B. Impact the critical path
C. Are known
D. Have the greatest cost impact
E. Have the greatest schedule impact

20) More common problems associated with managing multiproject resources include all of the following except
A. Inefficient resource utilization
B. Delays in one project cause delays in other projects
C. Reducing "downtime" created by lack of tasks to perform
D. Resource bottlenecks
E. All of these are common problems

21) Which of the following is not one of the types of project constraints?
A. Physical
B. Technical
C. Resource
D. Time
E. All of these are types of project constraints

22) In a resource-constrained project, the first priority in assigning resources is usually given to activities with the
A. Smallest duration
B. Least slack
C. Most slack
D. Lowest identification number
E. Highest cost

23) . If resources are not adequate to meet peak demands, the resulting reschedule is termed
A. Resource-constrained scheduling
B. Time-constrained scheduling
C. Mandatory leveling
D. Project resource adjustment
E. Allocation

24) Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a _________ constraint.
A. Physical
B. Technical
C. Resource
D. Scheduling
E. Time

25) . In a resource-constrained project the third priority in assigning resources is usually given to activities with the
A. Smallest duration
B. Least slack
C. Most slack
D. Lowest identification number
E. Highest cost

Reference no: EM13917789

Questions Cloud

Data showing the results of six subjects on a memory test : Below are data showing the results of six subjects on a memory test. The three scores per subject are their scores on three trials (a, b, and c) of a memory task.
How does a project manager track project variance : Describe the use of a work break down structure (WBS) in project planning. What considerations and issues would you explore in developing the organizational structure for a large mission critical project?
Components of a financial reporting : Describe the meaning and the components of a financial reporting system. Explain the budget cycle and process. Write a description of how management should use an activity based budget instead of an operating budget
Convergence project between us gaap and ifrs : Provide a detailed history of the convergence project between US GAAP and IFRS. Discuss in detail the major differences between US GAAP and IFRS applications.
Cost to prepare bottom-up estimates : The cost to prepare bottom-up estimates will typically run how much more than the costs to prepare the top-down estimates?
Evaluating the financial condition of the company : Suggest the financial ratio that most financial analysts would use to evaluate the financial condition of the company. Provide support for your rationale.
Exposures-financial contracts and operational techniques : Your company is considering expanding into the international markets. The Board of Directors has asked you create a 5-to-8-page report that defines and explains the various types of exposure the company could experience and the types of financial ..
Cost structure analysis with employers : We can use the cost structure analysis with our employers simply by analyzing the fixed costs of a company and the variable costs of the company.
Percentiles and hypothesis testing with z-tests : Be sure you have reviewed this module/week's lesson and presentations along with the practice data analysis before proceeding to the homework exercises. Complete all analyses in SPSS, then copy and paste your output and graphs into your homework d..

Reviews

Write a Review

Accounting Basics Questions & Answers

  Depreciation insurance and property taxes represent 9000 of

sage learning systems inc. was organized on september 30 2012. projected selling and administrative expenses for each

  Streit inc provides business security systems in an

streit inc. provides business security systems. in an effort to increase revenue the sales manager has begun

  You are auditing the accounts receivable balance of a cable

you are auditing the accounts receivable balance of a cable television provider. individual accounts receivables tend

  Machine b the recorded cost of this machine was 160000 pele

on january 1 2008 pele company purchased the following two machines for use in its production process.machine a the

  At december 31 2010 kifer company had 500000 shares of

at december 31 2010 kifer company had 500000 shares of common stock outstanding. on october 1 2011 an additional 100000

  Amount at which the ovens should be recorded

Determine the amount at which the ovens should be recorded in Great Harvest's equipment account.

  The requirement that only transaction data capable of being

1- the requirement that only transaction data capable of being expressed in terms of money be included in the

  Strengths and weaknesses of capital investment evaluation

Using information from your text and at least one scholarly source, compare strengths and weaknesses of capital investment evaluation methods

  What is the difference between equity and debt securities

What is the difference between equity and debt securities

  When using the gross profit method of valuing ending

when using the gross profit method of valuing ending inventory if the gross profit is quoted as a percentage of cost

  Shut down condition for a competitive firm-norm fish

orm Fish makes cheap fishing rods and operates in a competitive market.  The company has a fixed cost of $20,000 per period.  In addition the firm incurs production or variable costs depending on its output as follows:

  Compute the amount of gain or loss to elton

Elton, Inc., which owes Boston Co. $900,000 in notes payable, is in financial difficulty. To eliminate the debt, Boston agrees to accept from Elton land having a fair market value of $680,000 and a recorded cost of $510,000.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd