Reference no: EM13979313
Problem 1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?
Problem 2. A project has just completed its 87th item in the project plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The project manager estimates that the value of the work actually finished is nearly $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?
Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project.
Activity
|
Predecessor
|
Duration (wks)
|
Budget ($)
|
Actual Cost ($)
|
%Complete
|
a
|
-
|
2
|
300
|
400
|
100
|
b
|
-
|
3
|
200
|
180
|
100
|
c
|
a
|
2
|
250
|
300
|
100
|
d
|
a
|
5
|
600
|
400
|
20
|
e
|
b,c
|
4
|
400
|
200
|
20
|
Problem 4. Solve the following Case:
Stoneworth Paving Company specializes in highway paving jobs for state of Virginia. When the State first awarded Stoneworth the contract, they stipulated a 1% penalty for each week Stoneworth was late on a completion date. Preston Flintrock, the project coordinator for Stoneworth, began to notice that the last two jobs were three weeks late, and the paving job that was due to be completed in the next two weeks was behind schedule. When Preston went in the field to investigate, he found the job to be understaffed, supplier delays, and a high work rejection/repaving needed. As a result, Preston decided to establish a better system of project control and present it to the boss.
Question 1: If you were Preston, what characteristics would you be looking for in a new control system? Explain
Question 2: Will a new control system be adequate for the problem? Explain
Why are policies procedures and standards viewed
: Why are policies, procedures, and standards viewed as examples of operational controls?
|
What factors shift the labor supply curve to the right
: What factors shift the labor supply curve to the right?
|
If the slope of the ae function was 0.8, from the mpc
: If the slope of the AE function was 0.8, from the MPC, before taxes, and government introduced net taxes NT = 0.2Y, the slope of AE would be: A) 1.0. B) 0.6.
|
The mpc for the closed economy with no government is 0.8
: 38. If the MPC for the closed economy with no government is 0.8, the: A) MPS is 1/0.8. B) the multiplier is 5.
|
Cost and schedule variances for the project
: A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?
|
What are operational controls
: What are operational controls? What purpose do they serve?
|
Defining the interrelated activities necessary
: The size of the team can be essential to a team's success. The optimal size is between six and ten members who have a breadth of both specialty and people skills
|
Maximum expected monetary value
: 1. Suppose that the management of Theme Park, Inc., has decided that three is a .35 probability that the motel's application will be approved. Chapter 5 Supplement, problem a. If management uses maximum expected monetary value as the decision crite..
|
What is the reliance placed in system software working
: What is the reliance placed in system software working? And when operating systems do not work properly, what are the consequences in business terms?
|