1. The scope validation process is similar to the control quality process in what way?
A. Control quality control can use Pareto charts.
B. Control quality relies on inspection.
C. Control quality uses root-cause analysis.
D. Control quality is a project scope management process.
2. What input to the control scope process relies on earned value management?
A. The project management plan
B. Historical information
C. Work performance data
D. Organizational process assets
3. Which tool and technique does control scope use the most?
A. Data analysis
B. Project-integrated change control
C. Root-cause analysis
D. The project management information system
4. Which of the following is not an output of the control scope process?
A. Project document updates
B. Project management plan updates
C. Change requests
D. Cost estimate updates