Construct work breakdown structure of project

Assignment Help Business Management
Reference no: EM133085542

Task briefing:

How to manage an Industrial Development.

As a Project Leader, you have to organize the steps of the development of a new product:

The first activity is to define detailed specifications before starting the prototype. In this phase, we will create a preliminary design, made by William and Louis, two engineers, in twenty-five days.

Once the design is made, Louis and Peter (a new engineer) will determine the functional characteristics and specifications. They need for this task seven days. When the specifications are defined, we will create the prototype. The first operation to do is to construct the basic structure in 13 days, made by Peter and Susan, his assistant. At the same time, we have to design an electronic system, independent to the structure. For this task we will need John and he will spend 10 days.

Once we finish both activities, we have to assembly the prototype. This task is for Peter and John and they will take two days.

When the designs and prototype are made, we start the tests. The first test will be made by Mary, a Quality Department technician, in five days. William and Susan will work in the second test, and they will spend other five days. After these two test, John and Susan will make a simulation. For this new test we need to work in the laboratory for twelve days. Finally, the product will be accepted (milestone).

Once we know the project is valid, we must write the project report. To do this document, Robert, after the second test, writes a draft in two days. This preliminary document is the base for the final report, written by two assistants in two weeks. The report is corrected, and the final version is available in three weeks.

With this report we can start the training program for all the employees. The responsible of this training are Susan and Mary. This activity can start when the report is corrected. The first session is for Top Management (we need only one day) and then, the rest of workers.

Finally, the company must launch the new product. After the training program, Joseph, the Marketing Manager will develop the Marketing Plan in seven days.

After this, Tom and George, the sellers, will study in fifteen days the specifications and the Marketing Plan to guarantee the success of the product in the market.

At the same tame we prepare the launch, Victor, the Production Manager, starts to organize the production. He says that in twenty-five days the first units will be available

1. Construct the Work Breakdown Structure of this project, including Tasks, times, resources, and predecessors.

2. Draw the Project Timing with a Gantt Chart and a PERT or Network Diagram. What is the total project completion time?

3. Determine the Critical Path.

4. Draw the Resource Graph. What are the maximum and minimum resource needs?

Reference no: EM133085542

Questions Cloud

Visually persuading your viewer : Prepare and evaluate the use of media visuals to improve persuasive and marketing communication.
Virtual and face to face team dynamics : Identify and explain some differences between virtual teams and face to face teams. Identify tools that a leader can use to assist a virtual team with conflict.
Health care service and running the facility : Write a paper that considers the cost of providing the health care service and running the facility you have proposed.
The matrix trilogy : The Matrix Trilogy. Do so by tracing details of this development throughout the three films, citing scenes and events throughout in careful and thorough manner
Construct work breakdown structure of project : Construct the Work Breakdown Structure of this project, including Tasks, times, resources, and predecessors.
Pros and cons of equity financing and debt financing : Identify the pros and cons of equity financing and debt financing, which are two main ways companies raise capital.
Hypothetical scenario-how will the plan increase revenue : What degree is this type of price discrimination? How will the plan increase revenue? Why will both groups of customers be satisfied with the deal?
Unfocused strategies was explored : As part of the reading, the problem of unfocused strategies was explored. One of the main pitfalls is trying to be all things to all stakeholders.
The problem is shortage with staff : The problem is shortage with staff and As the work cannot properly distribute due to shortage of staff therefore it is not possible to complete the work within

Reviews

Write a Review

Business Management Questions & Answers

  Caselet on michael porter’s value chain management

The assignment in management is a two part assignment dealing 1.Theory of function of management. 2. Operations and Controlling.

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. Due to increase in the preference for light beer drinkers, Chris Prangel wants to introduce light beer version in Mountain Man. An analysis into the la..

  Mountain man brewing company

Mountain Man Brewing, a family owned business where Chris Prangel, the son of the president joins. An analysis into the launch of Mountain Man Light over the present Mountain Man Lager.

  Analysis of the case using the doing ethics technique

Analysis of the case using the Doing Ethics Technique (DET). Analysis of the ethical issue(s) from the perspective of an ICT professional, using the ACS Code of  Conduct and properly relating clauses from the ACS Code of Conduct to the ethical issue.

  Affiliations and partnerships

Affiliations and partnerships are frequently used to reach a larger local audience? Which options stand to avail for the Hotel manager and what problems do these pose.

  Innovation-friendly regulations

What influence (if any) can organizations exercise to encourage ‘innovation-friendly' regulations?

  Effect of regional and corporate cultural issues

Present your findings as a group powerpoint with an audio file. In addition individually write up your own conclusions as to the effects of regional cultural issues on the corporate organisational culture of this multinational company as it conducts ..

  Structure of business plan

This assignment shows a structure of business plan. The task is to write a business plane about a Diet Shop.

  Identify the purposes of different types of organisations

Identify the purposes of different types of organisations.

  Entrepreneur case study for analysis

Entrepreneur Case Study for Analysis. Analyze Robin Wolaner's suitability to be an entrepreneur

  Forecasting and business analysis

This problem requires you to apply your cross-sectional analysis skills to a real cross-sectional data set with the goal of answering a specific research question.

  Educational instructional leadership

Prepare a major handout on the key principles of instructional leadership

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd