Question 1

(a) Christine Phillips is in charge of planning and coordinating next spring's sales management training program for her company. Christine has listed the following activity information for this project:

 

Activity

 

Activity Description

Immediate

Predecessors

Estimated

Duration

A

B

C

D

E

Select location

Obtain speakers

Make speaker travel plans

Prepare and mail brochure

Take reservations

-

-

A, B

A, B

D

2 weeks

3 weeks

2 weeks

2 weeks

3 weeks

Construct the project network for this project.

(b) Christine has done more detailed planning for this project and so now has the following expended activity list.

Construct the new project network.

Question 2

(I) Alfred Lowenstein is the president of the research division for Better Health, Inc., a major pharmaceutical company. His most important project coming up is the development of a new drug to combat AIDS. He has identified 10 groups in his division which will need to carry out different phases of this research and development project. Referring to the work to be done by the respective groups as activities A, B, ........, J, the precedence relationships for when these groups need to do their work are shown in the following project network.

2026_figure.jpg

 

Duration

Activity

Estimated Mean

Estimated Variance

A

B

C

D

E

F

G

H

I

J

4 months

6 months

4 months

3 months

8 months

4 months

3 months

7 months

5 months

5 months

5 months

10 months

8 months

6 months

12 months

6 months

5 months

14 months

8 months

7 months

(a) Find earliest start, earliest finish, latest start and latest finish time for each activity of this project.

(b) Find the mean critical path for this project.

(c) Use this mean critical path to find the approximate probability that the project will be completed within 22 months.

(d) Now consider the other three paths through this project network. For each of these paths, find the approximate probability that the path will be completed with 22 months.

Reference no: EM132210354

Questions Cloud

Explain the interlinking model of quality and profitability : Explain the interlinking model of quality and profitability (Exhibit 4.2). How does it connect to business and operations strategy?
Write a program that will input two arrays of information : Write a program that will input two arrays of information. Each array will contain exactly 4 floating point values.
Explain which method of communication you prefer : Compare the following communication tools that could be used to create a response, and explain which method of communication you prefer
Compute future bank balances : Write a program that an investor can use to compute future bank balances. The program asks the user for two pieces of information:
Construct the new project network : MTH601 - Operation Research - Construct the new project network - find the approximate probability that the project will be completed within 22 months
Designing organizations for the international environment : Analyze the material in the article using concepts and frameworks.Designing Organizations for the International Environment
Ask the user to input a set of row and column values : Write a program to implement the simulation of life as described in Scientific American by Martin Gardner
How coordinated care gives patients freedom to stay home : The PBS News Hour “How coordinated care gives patients the freedom to stay home” looks at keeping patients healthy and at home.
Write a program in the java which takes as input an integer : Write a program in the java which takes as input an integer (positive or negative) in base 10, and returns a string representation in 32-bit of the number.

Reviews

Write a Review

Mathematics Questions & Answers

  Questions on ferris wheel

Prepare a Flexible Budget Gator Divers is a company that provides diving services such as underwater ship repairs to clients in the Tampa Bay area.

  Logistic map

This assignment has two question related to maths. Questions are related to bifurcation cascade and logistic map.

  Finding the probability of cards

This assignment has questions related to probabiltiy.

  Systems of ode

Find all the xed points, and study their stability and Draw the phase portrait of the system, as well as the graphs of the solutions in all relevant cases.

  Derive the boolean expression

Derive the Boolean Expression and construct the switching circuit for the truth table stated

  System of equations

Evaluate which equations are under-identified, just-identified, and over-identified.

  Linear programming problem

Linear programming problem consisting of only two constraints with one objective function.

  Find the natural domain

Find the natural domain of the given functions.

  Introduction to numerical methods

Compute the coecients of the polynomials using the term recurrence relation.

  Chart of the topological manifold

De?nition of smoothness of functions on a smooth manifold is chart independent and hence geometric.

  Mathematics in computing

Questions related on mathematics in computing.

  Complex problems

Complex problems

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd