Reference no: EM13972331
1. General Foundry, Inc., a metal works plant in Milwaukee, has long been trying to avoid the expense of installing air pollution control equipment. The local environment protection group has recently given the foundry 16 weeks to install a complex air filter system on its main smokestack. General Foundry has been warned that it may be forced to close unless the device installed in the allotted period. Lester Harky, the managing partner, wants to make sure that installation of the filtering system progressed smoothly and on time.
General Foundry has identified the following eight activities that need to be performed and their sequential relationship.
Activity
|
Description
|
Time
(weeks)
|
Immediate
Predecessors
|
A
|
Build internal components
|
2
|
--
|
B
|
Modify roof and floor
|
4
|
--
|
C
|
Construct collection stack
|
2
|
A
|
D
|
Pour concrete and install frame
|
4
|
A, B
|
E
|
Build high-temperature burner
|
4
|
C
|
F
|
Install pollution control system
|
3
|
C
|
G
|
Install air pollution device
|
5
|
D, E
|
H
|
Inspect and test
|
2
|
F, G
|
a. Construct the appropriate network diagram.
b. Which jobs can be delayed without delaying the project completion time?
c. Can General Foundry complete the project on time? Why or why not?
d. Suppose Lester wants to shorten the completion time and his options are:
(1) Reduce activity D by one week, which costs $700/week;
(2) Reduce activity E by one week, which costs $800/week;
(3) Reduce activity G by one week, which costs $1000/week;
If General Foundry will save $2000 for each week that the earliest completion time is reduced, which single option, if any, should Lester choose?
2. The following table represents a plan for a project:
|
Time Estimates (days)
|
Job No.
|
Predecessor Job(s)
|
Optimistic
|
Most likely
|
Pessimistic
|
A
|
-
|
1
|
2
|
3
|
B
|
-
|
2
|
3
|
4
|
C
|
A
|
4
|
5
|
6
|
D
|
B
|
8
|
9
|
10
|
E
|
C, D
|
2
|
5
|
8
|
F
|
D
|
4
|
5
|
6
|
G
|
E
|
1
|
2
|
3
|
a. Construct the appropriate network diagram.
b. What is the critical path?
c. What is the expected completion time for the project and what is the variance of project completion time?
d. Is the probability that the project will take less than 18 days to complete larger than 50% or smaller than 50%?
Compute the cost of the cash discount based
: Compute the cost of the cash discount based on the three policies under consideration. Recall the total credit sales were $18 million. Multiply total credit sales times the percent that use the discount for each new discount policy times the size of ..
|
Discuss some of corporate finance challenges face by company
: Discuss some of the corporate finance challenges faced by this company. Write a 350-700 word summary of your discussion.
|
How each theory addresses ethics and morality
: A personal experience to explain the relationship between virtue, values, and moral concepts as they relate to one of the three theories
|
Table of present value of an annuity
: Compute the internal rate of return for each investment. Use the above table of present value of an annuity of $1. If required, round your present value factor answers to three decimal places and internal rate of return to the nearest percent.
|
Construct the appropriate network diagram
: Construct the appropriate network diagram. Which jobs can be delayed without delaying the project completion time? Can General Foundry complete the project on time? Why or why not
|
A brief discussion of the opposition''s point of view.
: This is a good time to reconsider the initial thoughts you had earlier in the module about your thesis (or hypothesis): do you need to rewrite it? If you have trouble filling in the sections below, an improperly formed thesis might be the problem.
|
What is the effective six month interest
: What is the effective six-month interest for 8.9% APR compounded daily?A. 4.54%B. 4.5%C. 9%D. 9.08%
|
What is the new balance
: On August 10 the business made a payment of $700, and on August 17 they borrowed $4,800. If the current prime rate is 6%, what is the new balance?
|
What is the marginal cost of the thirteenth worker
: A retailer has to pay $9 per hour to hire 13 workers. If the retailer only needs to hire twelve workers, a wage rate of $7 per hour is sufficient. What is the marginal cost of the 13th worker?
|