Construct the appropriate control chart

Assignment Help Project Management
Reference no: EM13537602

Question: Workers at a packaging operation shovels a granular product from a large pile into sacks that are then sealed and placed on pallets for shipping. A sequence of 25 subgroups each consisting of the weights of 5 sacks has been recorded as follows:

 

Observations

Subgroup #

Sack 1

Sack 2

Sack 3

Sack 4

Sack 5

1

35.4

35.6

34.8

34.7

34.8

2

36

35.6

34.9

34.8

35.9

3

35.2

35

35

35.4

35.1

4

34.8

35.8

35.2

35

34.9

5

34.2

35

36.1

34.9

35.1

6

36

35

35.2

34.8

34.9

7

36.1

34.9

34.5

35

35.1

8

35.1

35

35.6

34.9

36.2

9

35

35.6

36.1

34.8

35.6

10

35.4

35.8

36

34.2

36

11

35.2

35.3

35.2

35.9

34.8

12

35.9

36

35.1

35.1

35.6

13

35.2

35.6

35

34.9

35

14

35.2

35.6

35.8

35

35.1

15

34.9

34.8

35

35.2

34.9

16

35.2

35.3

35.2

35.6

35.1

17

35.6

35.8

35.2

35.4

34.9

18

35.2

35.6

35.4

35.6

35.2

19

34.7

34.9

35.6

35.2

35

20

35

35.1

35.6

35

35.1

21

35.6

35

35.8

35.2

34.6

22

34.9

35.1

35.6

35

35.2

23

35.9

36

35.2

36

35.2

24

35.2

35.1

35.4

34.9

35.1

25

35.2

35.2

35.1

35.6

34.9

a- What is the appropriate control chart that can be used by the quality engineer in this case?

b- Determine the control limits (show your calculations)

c- Construct the appropriate control chart for the data above using MINITAB.

d- Is the process in-control? If not, when does the out-of-control behavior occur?

e- If the process is found to be out of control, drop the out-of-control points and use MINITAB to re-construct the control chart.

f-  Is the process now in-control? If not, what to do next?

Reference no: EM13537602

Questions Cloud

Explain the frequency of radiation it uses to communicate : Many people have 900 MHz phones where this refers to the frequency of radiation it uses to communicate. What energy does this correspond to (in joules/photon)
Single valence electron of a rubidium atom : The ground state for a single valence electron of a rubidium atom (Z=37) is 5s and its energy is –4.18 eV. The valence electron is excited into the 5g state. We want to determine the energy of this 5g electron. Assume that the wave function for th..
Equation relating energy levels of the harmonic oscillator : A lithium atom, mass 1.17 x 10-26 kg, is vibrating with simple harmonic motion in a crystal lattice, where the force constant is 71.0 N/m. Write the equation relating the energy levels of the harmonic oscillator to the quantities given.
When does the out-of-control behavior occur : What is the appropriate control chart that can be used by the quality engineer and determine the control limits (show your calculations)
Construct the appropriate control chart : What is the appropriate control chart that can be used by the quality engineer in this case, determine the control limits and construct the appropriate control chart for the data above using MINITAB.
Explain solution is cloudy after precipitation and heating : If the solution is cloudy after precipitation and heating, what does this indicate. Can the solution be filtered at this point
Determine the centerline and control limits : Determine the centerline, determine the control limits, Use MINITAB to develop the appropriate control chart and are there any indications of lack of control
Evaluate the agno3 needed to precipitate : If a 400 mg sample is assumed to be pure NaCl, calculate the millimeters of 0.1M AgNo3 needed to precipitate it completely
Explain the movable plunger on a syringe : Because of the movable plunger on a syringe, the gas inside the syringe can be held at a constant pressure of 1.00 atm while allowing the volume of the gas to increase or decrease.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd