1. Use the following information to construct a "Tracking Gantt" chart using MS Project.
Activities |
Duration |
Preceding |
A |
5 days |
none |
B |
4 days |
A |
C |
3 days |
A |
D |
6 days |
B, C |
E |
4 days |
|
F |
2 days |
D, E |
Highlight project status on day 14 using the tracking option and assuming that all tasks to date have been completed on time. Print/capture the output file.
2. Using the information in Problem 1, highlight the project's status on day 14 but assume that activity D has not yet begun. What would the new tracking Gantt chart show? Print/capture the output file.
3. Use the following table to calculate project schedule variance based on the units listed. (Figures are in thousands.)
Schedule Variance Work Units
|
A
|
B
|
C
|
D
|
E
|
F
|
Total
|
Planned Value
|
20
|
15
|
10
|
25
|
20
|
20
|
110
|
Earned Value
|
10
|
10
|
10
|
20
|
25
|
25
|
|
Schedule variance
|
|
|
|
|
|
|
|
4. Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June. Complete the earned value column on the right. Assume the project is planned for a 12-month duration and $250,000 budget.
Activity Jan Feb Mar Apr May Jun Plan % C Value
Staffing 8 7 15 100_______
Blueprinting 4 6 10 100_______
Prototype
Development 2 8 10 70 _______
Full Design 3 8 10 21 67________
Construction 2 30 32 25________
Transfer 10 10 0
Monthly Plan ____________________________________________________
Cumulative _______________________________________________
Monthly Actual 10 15 6 14 9 40
Cumul. Actual____________________________________________________________
5. Using the data from Problem 4, calculate the following values:
Schedule Variances
Planned Value (PV)
Earned Value (EV)
Schedule Performance Index (SPI)
Estimated Time to Completion
Cost Variances
Actual Cost of Work Performed (AC)
Earned Value (EV)
Cost Performance Index (CPI)
Estimated Cost to Completion
Write paper that includes security concerns for enterprise
: Write a 2 to 3-page paper that includes the Security concerns for the enterprise, suggestions for additional information to be documented with examples and consideration of network bandwidth capacity considerations in the design documents.
|
What potential constitutional issues arise at sentencing
: Compare and contrast sentencing guidelines and mandatory minimum sentences. Identify three aims of both sentencing guidelines and mandatory minimum sentences. What potential constitutional issues arise at sentencing? Use the internet to research a..
|
Explain why the results differ between the two cases
: Show that licensing can be beneficial for firm 1 in this case and therefore increase innovation incentives. Explain why the results differ between the two cases.
|
Determine the changes to the balance sheet income statement
: determine the changes to the balance sheet, income statement, job cost ledger, and equipment ledger as the result of leasing a $55,000 dump truck (Dump Truck 11). The lease extends for five years at which time the dump truck may be purchased for $5,0..
|
Construct a tracking gantt chart using ms project
: Construct a Tracking Gantt chart using MS Project - calculate project schedule variance based on the units listed. (Figures are in thousands.)
|
The role of communication in your daily job
: Revise the following interview questions to make them more effective. In a brief paragraph for each, explain why you have revised the question as you have.
|
Characterize the equilibrium number of varieties
: Characterize the equilibrium number of varieties (at which all monopolistically competitive variety producers make zero profits) and compare this number with the answers to the previous two parts. Explain the sources of differences between the equ..
|
The managing director of your company explaining
: Prepare a report for the managing director of your company explaining how costs may be classified by their behaviour, with particular reference to the effects both on total and on unit costs.
|
One sample t test computations
: One-Sample T-Test Computations Thirty anorexic girls were treated with cognitive behavioral therapy (CBT). They were weighed before and after the treatment. The weight gains, which are positive scores, and weight losses, which are negative scores, ar..
|