Construct a network diagram for the project

Assignment Help Operation Management
Reference no: EM13743537

Problem 1

The following data were obtained from a project to create a new portable electronic.

Activity           Duration         Predecessors 

A                     5 Days             ---

B                     6 Days             ---

C                     8 Days             ---

D                     4 Days             A, B

E                      3 Days             C

F                      5 Days             D

G                     5 Days             E, F

H                     9 Days             D

I                       12 Days           G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) What is the Scheduled Completion of the Project?

b) What is the Critical Path of the Project?

c) What is the ES for Activity D?

d) What is the LS for Activity G?

e) What is the EF for Activity B?

f) What is the LF for Activity H?

g) What is the float for Activity I?

Problem 2

The following data were obtained from a project to build a pressure vessel:

Activity           Duration         Predecessors 

A                     6 weeks           ---                               

B                     6 weeks           ---                               

C                     5 weeks           B                                

D                     4 weeks           A, C                           

E                      5 weeks           B                                

F                      7 weeks           D, E, G                       

G                     4 weeks           B

H                     8 weeks           F

I                       5 weeks           G

J                       3 week             I

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the slack time (float) for activity A?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity G?

Problem 3

The following data were obtained from a project to design a new software package:

Activity           Duration         Predecessors 

A                     5 Days             ---                               

B                     8 Days             ---                               

C                     6 Days             A                                

D                     4 Days             C, B                            

E                      5 Days             A                                

F                      4 Days             D, E, G                                   

G                     4 Days             B, C

H                     3 Day              G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path(s)

c) What is the slack time (float) for activity B?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity G?

Problem 4

The following data were obtained from an in-house MIS project:

Activity           Duration         Predecessors 

A                     5 Days             ---                               

B                     8 Days             ---                               

C                     5 Days             A                                

D                     4 Days             B

E                      5 Days             B                                

F                      3 Day              C, D               

G                     7 Days             C, D

H                     6 Days             E, F, G

I                       9 Days             E, F

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the slack time (float) for activity A?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity F?

Reference no: EM13743537

Questions Cloud

Explain growth and spread of religious revivalism in muslim : Explain the growth and spread of religious revivalism in Muslim countries since the late 1960s.
Income statement from the information : Create a two-year forecast of the income statement from the information provided in problem number one. Please create three columns of data: current year, year 2, and year 3. Assume that sales increase ten percent per year for year's two and th..
Write a book report of frederick douglas by williams douglas : Write a book report of Frederick Douglas by William's Douglas.
Recent rise of the indian pharmaceutical industry : How might (a) U.S. pharmaceutical companies and (b) U.S. consumers benefit from the rise of the Indian pharmaceutical industry - who might have lost out as a result of the recent rise of the Indian pharmaceutical industry?
Construct a network diagram for the project : The following data were obtained from a project to create a new portable electronic. Construct a network diagram. What is the Scheduled Completion of the Project? for the project.
Review and identify the blood transfusion requirements : Blood transfusion- Review and identify the blood transfusion requirements within that consent form; explain where and how each element is noted within the actual form itself
What were kerma and meroe known for : What were Kerma and Meroe known for?
Discuss how china fared during the fast two decades : Discuss how China fared during the fast two decades of the 20th century Did Yuan Shikai abide by the republican principles advocated by Sun Yat-sen?
Testing for proteins : Testing for Proteins-How did your a priori predictions compare to your actual results in Table 2? If there were any inconsistencies, explain why this occurred

Reviews

Write a Review

Operation Management Questions & Answers

  Team to ensure diversity and expertise to fill various role

Teams have different needs, and people in organizations should be selected for a team to ensure diversity and expertise to fill various roles. Study the nine team roles and share one role you personally played in a team. How did it go? Be sure to ..

  At what point does break-even occur

Also calculate the overall return on investment of the project and then present a break-even analysis. At what point does break-even occur?

  Illustrate what are determining factors that may lead

Illustrate what are determining factors that may lead to a decision to proceed with outsourcing. A gift shop sells 1000 boxes of scented candles a year.

  Analyzing the financial statements of a company

Investors and creditors are typically not interested in the same thing. Investors are typically interested in whether a company is going to turn a profit over time, while a creditor is interested in short-term cash flow. Decide whether you are an ..

  Productservices either developing a new productservice or

either developing a new productservice or redesigning the current productservices requires a strong identity or

  Creat a rfp for a bpo in a ficticous organization

Creat a RFP for a BPO in a ficticous organization and explain why you would use different parts. Defend you choices to the executive team tasked with the outsourcing project.

  Formulate mixed integer programming model

Lauren Moore has sold her business for $500,000 and wants to invest in condominium units (which she intends to rent) and land (which she will lease to a farmer).

  Describe the types of learning objectives

Describe the types of learning objectives for which each training method is most suited.

  Project management strategy

Select one tool, other than MS Project, that you could use in order to manage project costs and scheduling. Next, speculate on the overall different project management strategy that you would apply based on the tool that you have selected

  The capacities of each and every plant demands of each

sweetland sugar nbspampco. produces cane sugar in its four plants in charlotte kansas city indianapolis and flagstaff.

  Develop a strong talent management program

The goal is to develop a strong talent management program globally to develop and retain talent that you have been losing to competitors.

  Define renewal strategies to create a successful turnaround

Research once failed companies Tyco and Best Buy. In a 2-3 page document, describe in detail, their organizational renewal strategies to create a successful turnaround. Compare the new corporate strategy to the old. Did it work

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd