Problem 1

The following data were obtained from a project to create a new portable electronic.

Activity           Duration         Predecessors 

A                     5 Days             ---

B                     6 Days             ---

C                     8 Days             ---

D                     4 Days             A, B

E                      3 Days             C

F                      5 Days             D

G                     5 Days             E, F

H                     9 Days             D

I                       12 Days           G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) What is the Scheduled Completion of the Project?

b) What is the Critical Path of the Project?

c) What is the ES for Activity D?

d) What is the LS for Activity G?

e) What is the EF for Activity B?

f) What is the LF for Activity H?

g) What is the float for Activity I?

Problem 2

The following data were obtained from a project to build a pressure vessel:

Activity           Duration         Predecessors 

A                     6 weeks           ---                               

B                     6 weeks           ---                               

C                     5 weeks           B                                

D                     4 weeks           A, C                           

E                      5 weeks           B                                

F                      7 weeks           D, E, G                       

G                     4 weeks           B

H                     8 weeks           F

I                       5 weeks           G

J                       3 week             I

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the slack time (float) for activity A?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity G?

Problem 3

The following data were obtained from a project to design a new software package:

Activity           Duration         Predecessors 

A                     5 Days             ---                               

B                     8 Days             ---                               

C                     6 Days             A                                

D                     4 Days             C, B                            

E                      5 Days             A                                

F                      4 Days             D, E, G                                   

G                     4 Days             B, C

H                     3 Day              G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path(s)

c) What is the slack time (float) for activity B?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity G?

Problem 4

The following data were obtained from an in-house MIS project:

Activity           Duration         Predecessors 

A                     5 Days             ---                               

B                     8 Days             ---                               

C                     5 Days             A                                

D                     4 Days             B

E                      5 Days             B                                

F                      3 Day              C, D               

G                     7 Days             C, D

H                     6 Days             E, F, G

I                       9 Days             E, F

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the slack time (float) for activity A?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity F?

Reference no: EM13743537

Questions Cloud

Explain growth and spread of religious revivalism in muslim : Explain the growth and spread of religious revivalism in Muslim countries since the late 1960s.
Income statement from the information : Create a two-year forecast of the income statement from the information provided in problem number one. Please create three columns of data: current year, year 2, and year 3. Assume that sales increase ten percent per year for year's two and th..
Write a book report of frederick douglas by williams douglas : Write a book report of Frederick Douglas by William's Douglas.
Recent rise of the indian pharmaceutical industry : How might (a) U.S. pharmaceutical companies and (b) U.S. consumers benefit from the rise of the Indian pharmaceutical industry - who might have lost out as a result of the recent rise of the Indian pharmaceutical industry?
Construct a network diagram for the project : The following data were obtained from a project to create a new portable electronic. Construct a network diagram. What is the Scheduled Completion of the Project? for the project.
Review and identify the blood transfusion requirements : Blood transfusion- Review and identify the blood transfusion requirements within that consent form; explain where and how each element is noted within the actual form itself
What were kerma and meroe known for : What were Kerma and Meroe known for?
Discuss how china fared during the fast two decades : Discuss how China fared during the fast two decades of the 20th century Did Yuan Shikai abide by the republican principles advocated by Sun Yat-sen?
Testing for proteins : Testing for Proteins-How did your a priori predictions compare to your actual results in Table 2? If there were any inconsistencies, explain why this occurred

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd