Construct a network diagram

Assignment Help Project Management
Reference no: EM135245 , Length: Word count:1500

 

Q1.

Table 1 indicates the sequence and interdependence of the 10 activities (A - K) which together are required to develop a bespoke system. The durations (in weeks) of each of the activities are given in the table

Activity

Description

Duration (wks)

Precedence

A

Requirement Gathering

27

-

B

Business Analysis

24

-

C

Systems Analysis

21

-

D

Coding

21

A

E

Unit Test

22

B

F

Module Testing

27

C

G

Systems Testing

22

F

H

User Acceptance Testing

22

G,E

J

Implementation

22

H

K

Handover

23

D, J

(a) Construct a network diagram identifying the following:

i. Earliest Start Time(EST)
ii. Latest Finish Time (LFT)
iii. Total Float on each activities D, F & J
iv. Critical Path for the project

b) Assume that there is a delay of 3 weeks in completing activityH. Analyseone action that the Operations Manager could take to avoid exceeding the current length of the critical path.

Q2.

The resource-based view of the firm is one of the most influential current theories in operations strategy (Slack, 2007). Critically evaluate and argue how firms' should consider resource based view during the location selection process?

Differentiate and accurately distinguish between the need for organised interaction between the role of design and management within operations strategy.

Word count:1500

Reference no: EM135245

Questions Cloud

What is the magnitude of the runners total displacement : What is the magnitude of the runner's total displacement . What is the phase difference between the two waves next they reach the observer.
Prepare a powerpoint presentation on stakeholders : You are a high level manager who has been asked to show a PowerPoint Presentation to your employees on the ideas of stakeholders and corporate social responsibility.
What is the total mass of the reagents : What is the total mass of the reagents used in the combustion throughout the 30 days . The ball makes 17 oscillations in 16 seconds. What is it the mass of the ball.
What is the minimum distance from the slits to the screen : Suppose that the light is incident at right angles to the film. what is the minimum distance from the slits to the screen when 580 nm light is used.
Construct a network diagram : The resource-based view of the firm is one of the most influential current theories in operations strategy (Slack, 2007). Critically evaluate and argue how firms' should consider resource based view during the location selection process?
What should be the minimum initial speed of the dart : What should be the minimum initial speed of the dart so that combination makes a complete circular loop after the collision. find the minimum diameter of the raft that would prevent the diamond from being seen.
Discover an angular velocity of the weather vane : The flywheel of an engine has a moment of inertia 2.50 about its rotation axis. What constant torque is required to bring it up to the angular speed of 390 in a time of 8.50, starting from rest? What is its last kinetic energy . Discover an angular..
What least distance are they from each other : A fully loaded station wagon has a mass of 1690 kg. If each of its four tires is inflated to a gauge pressure of 211 kPa, what is the total tire area in contact with road . What least distance are they from each other? The angle might be too large ..
What is the height of the hill : What is the height of the hill . Find the coefficient of kinetic friction between flight bag and floor.

Reviews

Write a Review

Project Management Questions & Answers

  What do you understand by net present value

You are the project manager of a leading textile engineering company. The company opened its door in year 2000. Today, after 13 years of existence, it is being challenged with a loss in profitability approximating a 65% loss in net revenue

  List key stages of a typical procurement cycle

List key stages of a typical procurement cycle

  What are the project communication methods

What are the project communication methods

  Formulate a reasonable investment policy statement

Formulate a reasonable Investment Policy Statement

  Discuss relevance of re-work in project management

Discuss relevance of Re-Work in Project Management.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Analysis of the overall project risk

Analysis of the overall project risk

  Role of project management in development

Write a paper which explore Results Based Management topic and how it plays the role of project management in development.

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Questionaire on project management

Questionaire on Project Management

  Discuss five uses of a wbs in project management

The Work Breakdown Structure (WBS) subdivides the scope of work into manageable work packages that can be reliably estimated and assigned to a responsible person for completion. Discuss five uses of a WBS in Project Management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd