Q1.
Table 1 indicates the sequence and interdependence of the 10 activities (A - K) which together are required to develop a bespoke system. The durations (in weeks) of each of the activities are given in the table
Activity
Description
Duration (wks)
Precedence
A
Requirement Gathering
27
-
B
Business Analysis
24
C
Systems Analysis
21
D
Coding
E
Unit Test
22
F
Module Testing
G
Systems Testing
H
User Acceptance Testing
G,E
J
Implementation
K
Handover
23
D, J
(a) Construct a network diagram identifying the following:
i. Earliest Start Time(EST)ii. Latest Finish Time (LFT)iii. Total Float on each activities D, F & Jiv. Critical Path for the project
b) Assume that there is a delay of 3 weeks in completing activityH. Analyseone action that the Operations Manager could take to avoid exceeding the current length of the critical path.
Q2.
The resource-based view of the firm is one of the most influential current theories in operations strategy (Slack, 2007). Critically evaluate and argue how firms' should consider resource based view during the location selection process?
Differentiate and accurately distinguish between the need for organised interaction between the role of design and management within operations strategy.
Word count:1500
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd