You are completing your weekly status report and find that one activity will be delayed three weeks and that will affect the project completion date. You have analyzed the schedule, but considering the constraints to scope and cost, you know that you will not be able to make up the three weeks between now and the end of the project. Who should review and approve this change in the project plan? (Select the 1 best answer)
A.Sr. Management; they have the most interest in the plan
B. Change Control Board; it's their responsibility to review and approve all changes
C. Project manager; you can make this change yourself
D. Project Team; they are the ones that need to do the work and will be tied up for three more weeks
Create a project schedule and align resources, Analyze project schedule and resource allocation
Write a report on Managerial Roles and Gap Analysis
Questionaire on Project Management
Describe the market growth rate for product and service.
Design an online system for the human resources department to manage available job positions.
How does a project risk management approach pro-vide an early warning signal for impending problems or issues
Calculate the payoff and the profits for investments
Describe the features or characteristics of your product or service.
Write paper on Inventory Management System.
Analysis of the overall project risk
Evaluate the usefulness of ROCE
Distribution strategy and project management
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd