Consecutive wet days with a probability of occurence

Assignment Help Civil Engineering
Reference no: EM13542324

During the rainy season in a tropical country, the probability of a day being dry is 0.10. A dry day is defined as one without significant rainfall. Assuming that the number of days until the next dry day is geometrically distributed, what is the length of consecutive wet days that has a probability of occurence of no more than 0.05? Hint: calculate the probability of one wet day, then, 2, then 3, and so on until you hit a number of consecutive wet days with a probability of occurence of less than 0.05.

Reference no: EM13542324

Questions Cloud

What is the length of consecutive wet days that has : During the rainy season in a tropical country, the probability of a day being dry is 0.10. A dry day is defined as one without significant rainfall. Assuming that the number of days until the next dry day is geometrically distributed.
What is the probability that one can travel to city three : There are two ways to get from City One to City Three, (a) directly or (b) via City Two. Let A be the event that the road from City One to Three is open. Similarly, B is for City One to Two and C is for City Two to Three. If snow is forecast for the ..
Calculate the viscous drag force on this plate : An engineer is designing a horizontal, rectangular conduit that will be part of a system that allows fish to bypass a damn. Inside the conduit a flow of water at 40 F will be divided
Compare the effectiveness of the zinc coating with a typical : Compare the effectiveness of the zinc coating with a typical epoxy coating on reinforcement. How does the epoxy coating protect reinforcement and what happens if the coating is nicked.
Consecutive wet days with a probability of occurence : During the rainy season in a tropical country, the probability of a day being dry is 0.10. A dry day is defined as one without significant rainfall. Assuming that the number of days until the next dry
What are the specifications need to be specified while creat : What are the specifications need to be specified while creating a design for waterways?what are their uses?how are they maintained?
Find the total head loss if the flow velocity : Water at 72 degress Fahreneit flows through a 110-ft-long, 5-in-diameter wrought-iron pipe that contains the following fittings: one open globe valve, one medium-radius elbow
Find the flow rate and the pressure head at the base of : An 8-in-diameter pipeline (f=0.028) 500 ft long discharges a 3-in-diameter water jet into the atmosphere at a point that is 250 ft below the water surface at intake.
Find the pressure head just upstream of c and just down : A pipeline 900 ft long discharges freely at a point 200 ft lower than the water surface at intake. The pipe intake projects into the reservoir. The first 600 ft is of 10-in diameter, and the remaining 300 ft is of 6-in diameter. Find the rate of disc..

Reviews

Write a Review

Civil Engineering Questions & Answers

  Engineering ethics and ethical issue

what is the engineering ethics course where to write about any engineering ethical case and discuss the ethical issue?

  Engineering ethics and concept and cases

what is the engineering ethics case related to civil engineering with reference and discuss all the engineering ethics issues which covered the "Engineering etics concepte and cases?

  Transportation and management

In the construction management, there is a lot of procurement route that are necessary and suitable for the construction industry.

  Supporting Investment Promotion: ERNST & YOUNG

Ernst & young is currently providing support to various sectors. In this regards it was felt that if this report is able to document good practices currently being adopted or planned in ceramic sector.

  Personalized Cancer Therapy-A step forward

Cancer is the uncontrolled growth of abnormal cells in the body resulting in tumours that can be benign or malignant (cancerous cells). A proper treatment is necessary to fight with this serious disease.

  Discuss the different environmental companies

Discuss the different agencies, institutes, centers, different environmental companies that are active in UAE.

  Develop a simple urban constructed wetland design

Develop a simple urban constructed wetland design.

  Evaluate company performance in relation to GRI standards

Evaluate company performance in relation to GRI standards and comment on Stigler's theory.

  Water system design

Determine the corresponding error in the computed discharge

  Hydraulic behaviour in open channel

Describe how test flumes and associated equipment are used to assess and confirm hydraulic behaviour in open channel

  Write a paper on steel sustainability

Write a paper on steel sustainability.

  Writing case study about bridge collapse

Writing case study about bridge collapse

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd