CON4510 Construction Technology and Building Temporary Works

Assignment Help Civil Engineering
Reference no: EM132481409

CON4510 - Construction Technology and Building Temporary Works - Hong Kong Institute of Vocational Education

Part (a) A retaining wall of 12.0 m long as shown in Fig Q.1 is to be cast by concrete in one goal from top. Site condition during concreting is recorded as follows:

• Concrete temperature : 13°C ~ 25°C
• Unit weight of concrete : 25 kN/m3
• Rate of concrete delivery . 3.5 trucks per hour each delivering 6.2 m3

Calculate the designed concrete pressures in kN/m2 at each 1.0 m vertical interval along the height of the retaining wall. Then sketch the variation of the concrete pressure along the height of the fence wall.

Given the formula (from CIRIA Report 108) in computing concrete pressure on formwork as follows:

Pmax = D[C1√R +C2K√H - C1√R] or Dh, in kPa

(whichever is smaller)

Where C1 = 1.0; C2 = 0.45 and also K = [36/T+16]2

214_figure.jpg

Fig. Q.1 Cross Section of mass concrete retaining wall (NTS)

Part (b) Please state what kind of load types should be considered for formwork design.

Reference no: EM132481409

Questions Cloud

What rate of interest did you earn : One year ago, you invested $1800. Today it is worth $1924.62. What rate of interest did you earn?
Should robbins co make or buy the part : Should Robbins Co. make or buy this part? Robbins Co. has been producing a part for a camera they manufacture.The costs for this part
What is the amount of mortgage payment : The loan terms require monthly payments for 15 years at an annual percentage rate of 7.75 percent, compounded monthly. What is the amount of each mortgage payme
Calculate gross profit margin : Calculate gross profit margin, How are gross profit and net income changing, as dollar values? Are sales increasingly profitable?
CON4510 Construction Technology and Building Temporary Works : CON4510 Construction Technology and Building Temporary Works Assignment help and solution, Hong Kong Institute of Vocational Education - assessment writing
What the lake would record goodwill of : What the Lake would record goodwill of? Lake Incorporated purchased all of the outstanding stock of Huron Company paying $963,000 cash.
Calculate current multifactor productivity per month? : Calculate Current multifactor productivity per month?. After increasing the number of work hours to 800 per month?, the multifactor productivity
What is the balance due on april : He pays $800 on August 17 and $400 on November 20 of 2010 and $500 on February 2, 2011. What is the balance due on April 18, 2011?
Calculate total manufacturing costs : If there is no beginning work in process inventory and ending work in process inventory is $50,000, what is the cost of goods manufactured?

Reviews

Write a Review

Civil Engineering Questions & Answers

  Engineering ethics and ethical issue

what is the engineering ethics course where to write about any engineering ethical case and discuss the ethical issue?

  Engineering ethics and concept and cases

what is the engineering ethics case related to civil engineering with reference and discuss all the engineering ethics issues which covered the "Engineering etics concepte and cases?

  Transportation and management

In the construction management, there is a lot of procurement route that are necessary and suitable for the construction industry.

  Supporting Investment Promotion: ERNST & YOUNG

Ernst & young is currently providing support to various sectors. In this regards it was felt that if this report is able to document good practices currently being adopted or planned in ceramic sector.

  Personalized Cancer Therapy-A step forward

Cancer is the uncontrolled growth of abnormal cells in the body resulting in tumours that can be benign or malignant (cancerous cells). A proper treatment is necessary to fight with this serious disease.

  Discuss the different environmental companies

Discuss the different agencies, institutes, centers, different environmental companies that are active in UAE.

  Develop a simple urban constructed wetland design

Develop a simple urban constructed wetland design.

  Evaluate company performance in relation to GRI standards

Evaluate company performance in relation to GRI standards and comment on Stigler's theory.

  Water system design

Determine the corresponding error in the computed discharge

  Hydraulic behaviour in open channel

Describe how test flumes and associated equipment are used to assess and confirm hydraulic behaviour in open channel

  Write a paper on steel sustainability

Write a paper on steel sustainability.

  Writing case study about bridge collapse

Writing case study about bridge collapse

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd