Reference no: EM1335838
1. A project had a budget of $750,000 and was completed on time. The project expenses, however, were 15 percent more than what the project called for. What is the variance at completion for this project?
A. Impossible to know-not enough information
B. $112,500
C. $637,500
D. $750,000
2. Linda is a project manager for a large insurance company. Her current project is to organize all of the paper files to match the electronic structure of the IT system's servers. It is not an exciting project. Linda has just completed a performance report for her project. Her cost of performance index (CPI) is listed as .79, and her schedule performance index (SPI) is .69. Joey, her manager, has responded with a change request. Why?
A. The project is not performing well, so a change request is submitted to the project manager
B. The project is not performing well, so a change request is made to cancel the project
C. The project is not performing well, so Joey will likely issue a change request to remove Linda
from the project
D. The project is performing well, so Joey will likely be adding requirements to the project scope.
Explain marketing core strategy
: Explain Marketing Core Strategy and Provide a quick overview of the product or service you created you should continue using the content from the U3 Discussion Board
|
Hotel manage information as an asset
: Explain How does a hotel manage information as an asset and Assess the effectiveness of the different methods
|
Juvenile probation officer
: Job description for a juvenile probation officer Include a description of required job duties, as well as how probation fits into the juvenile justice system in general.
|
Common discretionary and contingent assessment methods
: Find the imilarities and differences between the common discretionary and contingent assessment methods
|
Computing variance at completion for project
: A project had a budget of $750,000 and was completed on time. The project expenses, however, were 15 percent more than what the project called for. What is the variance at completion for this project?
|
What value does a performance management program
: Explain What value does a performance management program bring to the organization and Which performance management programs did you consider
|
Measuring verbal and computational skills
: Measuring verbal and computational skills to a group of applicants for a specific job.
|
Direct and indirect costs
: Fee Setting - As the executive director of Advocates for Children, you have had a change of heart - perform all the computations necessary to set a fee. What will your fee be?
|
Define problem with criteria range
: problem with criteria range. I do not know how to set two different criterias in one column. I need to ADVANCE FILTER all of the Clerks (1 and 2) and the Sect. 1 workers who create more than $5.50/hr. I do not understand how to set the title crite..
|